CHIWESHE
JA:
This is an appeal against the whole judgement of the High Court (the
court a
quo)
sitting at Harare, dated 11 January 2023, wherein it declared that
the procurement contract entered into between the appellant and the
respondent was valid and binding between them. The court a
quo
proceeded, consequently, to grant an order of specific performance of
the contract. It also dismissed the appellant's counter claim and
ordered that the appellant pays the respondent's costs in the claim
in reconvention.
Aggrieved
by the decision of the court a
quo,
the appellant has noted the present appeal.
THE
FACTS
On
23 October 2015, the parties entered into a Public Procurement
Engineering, Procurement and Construction Contract (the contract). In
terms of that contract, the respondent was required to construct one
solar Photovoltaic Power Station to the capacity of 100MV in Gwanda
(the project).
A
dispute arose during the implementation of the project.
The
respondent issued summons in the court a
quo
seeking the following relief:
“1.
An order declaring that the procurement contract for the Engineering,
Procurement and Construction (EPC) of the 100 MV Gwanda Solar Project
(ZPC 304/2015) between the parties as amended is valid and binding
between the parties.
2.
Consequent to the declaration of the validity of the EPC contract, an
order for specific performance.
Alternatively:
Damages
in the sum of US$25,000,000-00 (twenty five million United States
dollars) for repudiatory breach of the EPC contract by the defendant.
3.
Costs of suit at the attorney and client scale.”
In
its declaration the respondent amplified its claim as follows:
The
agreed contract price for the project was US$172,848,597-60 exclusive
of taxes. The respondent was to secure and facilitate the funding of
the project as well as bear most of the risks associated with the
construction of the plant up to the point of commissioning. The
contractual terms were derived from the FIDIC Silver Book (General
Conditions of Contract for EPC/Turnkey Project) 1999, First Edition.
The General Conditions were applicable to the extent that they were
amended by the Particular Conditions of contract agreed to by the
parties.
The
appellant was to borrow the funds sourced by the respondent in its
name, superintend over both the construction works and facilitate
payments due to the respondent.
The
appellant would only take over the risk and liability in the power
infrastructure upon successful completion of the solar plant, that
is, at the “turn of the key”.
The
commencement of the contract was subject to certain suspensive
conditions which were to be satisfied or achieved by both parties
within a period of 24 months reckoned from 23 October 2015, the date
of signature of the contract. The period within which the suspensive
conditions were to be satisfied (the Conditions Precedent
Satisfaction Period”) could be extended by a period of 6 months
through an amendment to the contract. Such extension was to be done
before the expiry of the tenure of the conditions precedent
satisfaction period.
Beyond
the conditions precedent satisfaction period, either party became
entitled to terminate the contract, provided that the party seeking
to terminate the contract was not responsible for the delays in the
fulfilment of the conditions precedent.
Before
the expiry of the conditions precedent satisfaction period on 23
October 2017, the parties agreed to enter into an addendum to the
contract, the terms of which would allow the appellant to pay some of
the respondent's subcontractors directly in order to carry out the
pre-commencement works at the project site.
The
arrangement was in anticipation of the commencement of the contract.
The
addendum was executed on 21 September 2017, prior to the expiry of
the conditions precedent satisfaction period set for 23 October 2017.
The
addendum set different timelines for the conclusion of the
pre-commencement works. The appellant undertook to pay for that work.
The
appellant, however failed to pay for such works and as a result,
these were not executed at all or were not executed timeously.
The
appellant sought to extend the conditions satisfaction period by a
period of six months on 29 November 2017. The extension was to be
reckoned from 23 October 2017.
The
respondent objected to the extension which it regarded as a breach of
the contract, given the new terms of the addendum to the contract and
the appellant's failure to perform its obligations under the
addendum.
According
to the respondent, the appellant unilaterally demanded that the
suspensive conditions be completed on or before 23 April 2018, a
demand that respondent viewed as a material breach of the express
provisions of the contract.
By
way of notices dated 10 April 2018, 6 July 2018 and 31 July 2018, the
appellant informed the respondent that the contract had expired by
operation of law.
All
contractual obligations between the parties were, in terms of these
notices, terminated.
The
appellant insisted on such termination despite its admission that it
had failed to perform its obligations to pay the respondent's
subcontractors.
The
respondent further contended that the termination was also unlawful
in view of the appellant's direct liability in causing delays in
the fulfilment of the conditions precedent within the agreed time
frames.
It
was thereafter that the respondent approached the court a
quo
by way of application seeking a declaration of validity of the
contract and an order for specific performance.
The
application was granted on 13 December 2018 under HC 8159/18.
The
appellant appealed that determination to this Court under SC 39/21.
In
the meantime, the respondent applied for leave to execute judgment
pending appeal.
The
court a
quo
granted that application on 19 June 2019 under HC 2425/19.
The
respondent claims that during the two year period in which the
parties awaited the outcome of the appeal at the Supreme Court, the
parties implemented the contract as amended and engaged in a series
of meetings that culminated in the drafting of an amended and
restated contract.
On
13 May 2021 this court upheld the appellant's appeal and set aside
the judgment of the court a
quo.
This Court determined that the matter was replete with material
disputes of fact which could not have been resolved on the papers
before the court a
quo.
It
was for that reason that the respondent returned to the court a
quo
and instituted action procedure, seeking the same relief.
In
its plea in the court a
quo,
the appellant raised two points.
(i)
Firstly, it contended that the contract never took off because the
conditions precedent were not fulfilled. There was thus no basis at
law for the respondent to seek the declaration of validity.
(ii)
Secondly, it averred that this court had dismissed the respondent's
claim. It therefore pleaded res
judicata.
The
appellant also filed a counter claim seeking an order in the
following terms:
“(a)
An order that the EPC contract and the Addendum entered into by the
parties did not commence due to the plaintiff's failure to meet the
prescribed conditions precedent.
(b)
Damages for breach of contract and misrepresentation in the sum of
US$96,673,236-30 (ninety-six million six hundred and seventy-three
thousand two hundred and thirty-six United States dollars thirty
cents.”
The
matter was referred to trial on the following agreed issues:
In
respect of the main claim:
“(a)
Is the procurement contract entered into by and between the plaintiff
and the defendant dated 23 October 2015 valid and binding on the
parties?
(b)
Depending on the conclusion reached on the above question, did the
plaintiff suffer damages, and what is the quantum thereof?
In
respect of the claim in reconvention:
(a)
Was the agreement entered into by and between the parties induced by
misrepresentation on the part of the plaintiff?
(b)
If the plaintiff breached the agreement, then did the defendant
suffer damages as pleaded by it or at all and what is the quantum?”
At
the commencement of the trial in the court a
quo
the appellant abandoned the claim in para (b) of its prayer, that is
the claim for damages for breach of contract and misrepresentation
action in the sum of US$96,673,236.
The
appellant, however, persisted with the claim for US$3,330,736-30,
being the advance payment made to the respondent in respect of the
pre-commencement works.
PROCEEDINGS
BEFORE THE COURT A
QUO
The
respondent's evidence
The
respondent's sole witness was its managing Director, Wicknell
Munodaani Chivhayo. His evidence was summarized by the court a
quo
as follows:
He
told the court that when the tender for the project was flighted, the
appellant had no funds for the project. For that reason, the
appellant was looking for a contractor that would also assist it in
raising funds for the project.
The
respondent's partner, CHINT, was roped into the project to bring in
the required funds. He told the court that CHINT had the required
financial and technical capacity to execute the project.
The
contract price was US$172,848,597-60.
Mr
Chivhayo said that the commencement of the contract was subject to
the satisfaction of the conditions precedent set out in clause 5 of
the contract. These included the sourcing of the funds for the
project and the completion of the feasibility studies. The appellant
was responsible for funding the pre-commencement works and the
respondent was required to assist with the fundraising.
To
that end the respondent had engaged financial consultants and
financial partners such as the China Exim Bank and the Ministry of
Finance and Economic Development. These engagements were done before
the commencement of the project.
The
witness blamed the appellant for the collapse of the engagements that
were intended to birth the necessary financial agreements.
China
Exim Bank required that the Government of Zimbabwe guarantees the
loan facility.
The
witness approached the Ministry of Finance on behalf of the
appellant. The Ministry indicated its interest to support the project
and had agreed, at the witness's suggestion, that the project be
given national status.
The
Ministry of Finance undertook to provide the government guarantees
required by China Exim Bank and had written a letter dated 10 March
2016, addressed to the Export-Import bank of China undertaking to
issue a sovereign guarantee for the project in the sum of
US$147,000,000-00.
However,
the government of Zimbabwe had been blacklisted for defaulting on a
loan of US$400 million. For that reason, the China Export and Credit
Insurance Corporation (China Sinosure), a state funded insurance
company established to support China's foreign and trade
development cooperation, refused to secure the loan.
Thereafter
the parties mooted other sources from which to raise capital.
One
of these was the proposed raising of energy bond through the CBZ
Bank. This proposal had the full support of the SPB (State
Procurement Board). However, the appellant was not interested even
after its own Ministry directed it to pursue that route.
The
witness further told the court that the appellant frustrated the
signing of the financial arrangements, contrary to the spirit of
clause 5(a) of the contract.
The
witness had this to say about the advance payment demand guarantee.
During
meetings with the appellant's officials, feasibility studies had
been carried out and the appellant owed the respondent funds for the
work done. There was no need for such guarantee once work had been
completed and payment now due to plaintiff. The advance payment
received was therefore in respect of the feasibility studies that had
been performed.
With
regards the performance security the witness said it was not provided
for partly because the appellant still had some outstanding amounts
still to be paid and, that, at any rate, it had not been asked for.
He
also confirmed that the appellants had carried out its due diligence
in terms of clause 5(f) of the contract.
Both
parties representatives travelled to China for the purpose of
evaluating the respondent's partner CHINT. Both parties were aware
that CHINT had successfully carried out some projects in Zimbabwe.
The
witness stated that the production of the Environmental Impact
Assessment was the responsibility of the appellant. It was only
produced through his intervention when he directly engaged the
responsible Ministry.
The
land for the project was also acquired through his efforts when he
approached the Ministry of Lands.
He
confirmed that both parties had secured the necessary authorizations
as required by clause 5(f) of the contract.
Only
one condition remained outstanding, that is, the financing
agreements.
He
said that the amendments of the contract through the addendum were
occasioned by the loss of time.
In
terms of the agreement, as re-affirmed by the addendum, the total
cost of the pre-commencement works was US$5,111,224-50. The
respondent was supposed to contribute to that amount in the sum of
US$1,000,000-00, with the appellant contributing the remainder.
The
respondent did not pay its contribution as it was only required to
perform work of an equivalent value.
He
said that after the payment of the feasibility studies and part of
the fee for the pre-commencement works, the appellant still had an
outstanding liability in the sum of US$1,232,322-87 for part of the
pre-commencement works carried out.
The
respondent's sub-contractors were to be paid from that outstanding
amount.
He
stated that the appellant caused his arrest by ZACC officials for
non-performance of the contract. He wrote to the appellant's
managing director complaining about the unfounded allegations of
corruption. His arrest negatively affected the execution of some of
the works by the respondent's subcontractors.
He
insisted that the conditions precedent satisfaction period was
extended by the parties, and yet the appellant went on to raise a
criminal complaint for non-performance.
He
made reference to clause 5(i) of the contract which provided that if
the conditions precedent were not satisfied on or before 24 months
after the date of signature of the contract, the parties should meet,
and, if need be, the appellant could, in its sole discretion on or at
any time before the lapse of the 24 month period, elect to extend the
conditions precedent satisfaction period by a further six months.
He
referred to a letter from the appellant to the respondent dated 29
November 2017 in terms of which the period was extended by a further
6 months from 23 October 2017 to 23 April 2018.
The
witness made reference to various correspondences between the parties
and other stakeholders tending to show that the appellant was
responsible for the failure to sign financial agreements during the
extended period.
He
averred that in terms of clause 5(i) of the contract, the appellant
was estopped from relying on its own breach to cancel the contract.
He
said that the respondent declared a dispute between the parties in
terms of the contract. The dispute was declared through a letter
dated 15 January 2018. In terms of the contract the dispute was to be
adjudicated by the Dispute Adjudication Board which was duly
constituted.
The
appellant's attitude was that there was no need for the
constitution of the board as the parties could meet and resolve the
dispute.
The
respondent then sought to refer the matter to arbitration, but the
appellant objected saying that it was not an arbitration matter. It
was then that the respondent approached the court a
quo
for an order of specific performance, alternatively, damages.
It
succeeded in its quest for specific performance. The appellant
appealed that decision to this Court.
Pending
the hearing of the appeal, the respondent applied in the court a
quo
for an order to execute the judgment of that court pending appeal.
That application was granted but the appellant did not comply with
it.
In
the meantime, according to the witness, the Ministry of Energy
directed that the parties further engage in order to give effect to
the contract. The directive was contained in a letter dated 15 June
2020.
As
a result, the parties prepared an amended contract which they are yet
to sign.
That
development was seen by the witness as dispelling the notion that
specific performance was no longer possible.
Thereafter,
various engagements were initiated by the Ministry of Energy to iron
out the problems bedeviling the implementation of the contract. On 6
July 2020 the Minister of Energy wrote to the Executive Chair of ZESA
Holdings intimating to the Chair that his office was required “to
urgently conclude the drafting of all the pertinent agreements and
financial instructions necessary for the available financier to avail
the funds required to implement the project.”
This
letter was copied to the witness.
The
witness asserts that the government of Zimbabwe, through the Ministry
of Energy, as the shareholder in the appellant, wanted the project to
be implemented without delay. It was for that reason that the
Ministry had intervened calling on both parties to implement the
project.
However,
the appellant remained defiant.
The
witness indicated that in July 2020 the parties arranged a joint
visit to the site. The purpose of the visit was to assess the work
done and that which remained to be done since both parties were
negotiating a revised contract.
Thereafter,
the parties prepared a report comprising pictures and video evidence
demonstrating their findings on the ground. The report was jointly
signed by the parties representatives. The appellant was represented
by its project manager Mr Mugwagwa and its officials Mr Fambi and Mr
Chinho. On the other hand, the respondent was represented by the
witness, its project manager Mr Magweza and an official called Mr
Mubviri.
The
witness participated in both the joint visit and in the compilation
of the joint report. The witness opined that the exercise was an
indication that the contract was temporarily on hold.
The
witness stated that appellant's counter claim for the sum of
US$3,310,736-30 was devoid of merit if considered in the context of
the joint report. It was made on the premise that the
pre-commencement works were not carried out, yet the report showed
otherwise. The report confirmed that the appellant owed the
respondent some money for work done at the conclusion of the
pre-commencement works. It also confirmed that the advance payment
guarantee was no longer necessary.
He
was adamant that the objective of the pre-commencement activities as
set out in the contract were satisfied. In that regard, he was of the
view that the appellant was being malicious in suggesting that the
contract was not implemented at all.
The
witness justified the respondent's alternative claim for damages as
follows.
The
respondent had incurred expenses to do with the tendering process as
well as the due diligence exercise when the parties had to travel to
countries such as China and India. That included the cost of air
fares of the appellant's personnel that had to be covered by the
respondent. The respondent also claimed risk, occupational damages
and damages for reputational loss occasioned by the negative
publicity caused by the appellant. The witness also stated that the
respondent's security guards were kicked off the project site by
the appellant at a time the respondent was prepared to carry on with
the project.
Under
cross examination, he insisted that discussions for a new contract
started in earnest in 2020 after the new Minister of Energy had
assumed office.
He
said the Minister was unhappy over the delays, in implementing the
project. The Minister was displeased with the appellant's failure
to comply with CHITAPI J's order granting the respondent leave to
execute the High Court judgment pending appeal.
The
parties met again to discuss the way forward with no positive
results.
He
insisted that there were financiers ready to fund the project but for
the obstinacy of the appellant, a fact he communicated to the
Minister. He said that the execution of the Amended and Restated
Contract Agreement was not an admission that respondent had failed to
perform. The idea was simply to kick start the project with the
respondent required to source funds for the initial phase of 10MW
with the rest of the MW coming later as provided in the contract.
He
said it was the EPC contract that is sought to be enforced and not
the Amended Restated Contract.
The
respondent had even offered to reduce the price to demonstrate its
commitment to the implementation of the contract.
Asked
whether a guarantee was provided by the respondent as required by the
contract, the witness stated that CHINT wrote to the appellant
advising that they had the guarantee in place but the appellant
dithered. The offer was not accepted by the appellant because it had
no money. However, the appellant did make payments for the
feasibility and pre-commencement works without an advancement payment
guarantee.
This
was justifiably so because the respondent had delivered those
activities.
He
insisted that the appellant's letters of 7 and 10 April 2018 and 6
July 2018, which confirmed the non-extension of the condition
satisfactions period beyond 23 April 2018 prevented the respondent
from fulfilling the conditions precedent as set out in clause 5a.
This was because the appellant failed to pay the respondent's
subcontractors and, as a result, the pre-commencement works could not
be completed.
He
further stated that although the actual project had not yet
commenced, save for the pre-commencement works, the respondent needed
only 6 months to complete the first 10MW once it secured the
necessary funding.
He
accepted that the respondent had revised the project costs downwards
in the Amended and Restated Contract because the costs of solar
products had generally gone down on the international market.
He
dismissed the ADB integrity report on the debarment of CHINT on the
basis that the respondent was not seeking funding from ADB. In any
case, the debarment was lifted as CHINT was never found guilty of any
fraudulent conduct.
Asked
how the project could be implemented since the appellant did not have
financial resources, he responded as follows.
The
respondent had presented to the appellant China Exim Bank as a
willing financier in 2015. The respondent could not access the
funding set aside by China Exim Bank because the appellant's
shareholder owed the bank's export credit insurance adviser,
Sinosure and its account was in arrears, China Exim Bank said it
could still lend the money using other insurers. There were
alternative funders that did not even require underwriters. The
respondent introduced other local financiers such as CBZ and the
African Transmission Cooperation (ATC) as prospective funders. The
Ministry of Energy even approved the funding proposal by ATC in June
2020.
The
appellant was mandated to amend and restate the terms of the contract
to give effect to the new funding model but it failed to do so.
The
witness said he had also approached NSSA, on behalf of the appellant,
requesting assistance in raising US$25,927,289.
The
offer was also not taken up by the appellant.
The
witness stated that the annexure to the joint report prepared during
the joint visit to the site dated 13 July 2020, was part of the main
report prepared by the parties representatives. He said that the
report together with the annexure was actually sent to the respondent
by the appellant after the joint visit.
The
Appellant's Evidence
The
appellant called one witness, Cleopas Fambi, its assistant project
manager.
During
the period 2015-2017 his duties included the management of the
project between the appellant and the respondent. He was involved in
the tendering stage, contract negotiations and the pre-commencement
works. His evidence was to the following effect.
Sometime
in 2013 the appellant, through the State Procurement Board (SPB)
floated a tender for the construction of 3 x 100 MW photovoltaic
solar plants at Gwanda, Insukamini and Munyati. The respondent was
awarded the tender to construct the solar plant at Gwanda.
The
parties concluded the contract on 23 October 2015. The contract was
to commence in full force and effect after the satisfaction of the
conditions precedent stipulated in the contract.
The
respondent failed to fulfil the conditions precedent under clause 5
of the contract and the conditions remain unfulfilled to this date.
As a result, the contract did not commence because of the
respondent's failure to fulfil those conditions.
He
stated that the addendum to the contract dealt with the
pre-commencement works listed in schedule 11 of the contract. The
appellant paid for the pre-commencement works in advance. The
respondent however, failed to provide the bank guarantee for the
advance payments. It also failed to provide its portion that it was
meant to contribute to the pre-commencement works. The respondent
also misrepresented its capacity to perform the contract.
The
witness said that he was part of the joint team that visited the
project site on 13 July 2020. The visit took place in the context of
a proposal to implement the project in phases. The works had been
partially completed on the ground. No maintenance or repairs had been
carried out since July 2020.
With
regards the documentation attached to the joint report showing the
various activities of the pre-commencement works undertaken on site
and the bill of quantity amounts, the witness said that he was seeing
these papers for the first time in court.
He
said that the amount of US$2,031,230 representing the value of the
ground site clearing was overstated since there was still need to
carry out ripping of the top soil, clearing and site levelling.
He
dismissed the allegation that the appellant did not wish to implement
the project, saying that the appellant's conduct was consistent
with a desire to see the project completed. It was for that reason
that the appellant had paid for the pre-commencement works.
Under
cross examination, the witness admitted that the appellant was a
state commercial entity and therefore subject to the law governing
procurement by State entities.
He
agreed that according to the law, the appellant's accounting
officer was its managing director who was wholly responsible for the
administration of the project.
He
conceded that he could not account for the project within the
contemplation of the law as he was not the appellant's accounting
officer. The accounting officer was the person with the complete
records of all the transactions.
Asked
whether he could provide insight on the issue of financing
agreements, he stated that his insight was limited. He could not
comment as to why there was no financial closure because he did not
have the required information. He could also not comment on whether
the appellant deliberately frustrated the financial closure as
alleged by the respondent. He could not deny that CHINT had procured
funding from China since he was not the accounting officer. Neither
could he deny that the respondent had, as an alternative, engaged
domestic funders to finance the project and that its efforts had been
frustrated by the appellant's ambivalence. He could also not deny
that CHINT had offered a US$52 million guarantee but the appellant
had not embraced it because it did not have the required funds.
He
said the best person to comment would be the accounting officer since
all correspondence was directed to him.
The
witness admitted that the parties did not refer their dispute to a
consultant or engineer because there was no disagreement on the value
of the pre-commencement works carried out. The witness was also part
of the team that carried out a site visit in July 2020. The parties
agreed that the fence was erected and completed. He agreed that the
appellant therefore received value at the conclusion of that part of
the project. He also agreed that the feasibility study had been done
and completed. Repairs and maintenance works had also been carried
out.
Although
he denied the value delivered ascribed to the pre-commencement works
in the sum of US$3,382,697-00 as recorded in the bill of quantities
report, he conceded that he could not tell the value that had been
delivered to date.
Further,
he could not comment on how the sum of US$3,310,736-30 representing
the appellant's counter claim, was arrived at. It would require the
accounting officer, his team and the contractor to confirm how the
figure was arrived at.
He
also admitted that at some point the appellant had ordered the
respondent's workmen off the site.
The
witness could not comment on the Ministry's directive that the
project be completed.
His
attention was drawn to the fact that on 6 July 2020 the minister had
by letter of that date communicated Government's position to the
chairperson of ZESA Holdings. Another letter dated 15 June 2020 had
been written to the ZESA chairperson by the minister. In it the
minister had reiterated Government's desire for the parties to move
with speed to implement the project without delay.
The
witness could not deny that the contract was still capable of
performance and that the respondent could still secure funding to
achieve financial closure. He also admitted that the appellant was
desirous of addressing power shortages. That desire is what had given
impetus for the project.
SUBMISSIONS
IN THE COURT A
QUO
At
the end of the trial, the parties filed written closing submissions.
The
respondent submitted that the only issue that remained for
determination was whether or not the contract remained valid and
capable of performance. As to the counter claim it submitted that the
issue to be determined was whether the respondent was liable for the
advance payment made for the pre-commencement works. The respondent
submitted that no evidence had been adduced to support the counter
claim. The respondent submitted that it was ready to perform the
contract and that it had the capacity to perform the contract.
It
also submitted that it was able to provide the required finances. It
relied on the case of His
Holiness Acharya Swami Dasji
(1996) 4 SC 526 for that contention.
The
respondent argued that the onus rested on the appellant to show that
performance was no longer possible.
It
contended that at law, where one party to a contract repudiated the
agreement, the innocent party could elect to claim specific
performance of the contract or damages in
lieu
of specific performance.
It
submitted that specific performance was in the court's discretion
and that its case had to be determined on its own merits.
The
respondent cited the case of Benson
v SA Mutual Life Assurance Society
1986 (1) SA 776 (A) where it was held that the plaintiff had the
right to elect whether to hold a defendant to his contract and claim
performance by him of what he bound himself to do or claim damages
for the breach. On the other hand, the defendant did not have that
right of election.
According
to the respondent, the appellant did not lead any evidence to show
that specific performance was impossible. It contended that the
appellant could not rely on evidence in prior litigation because it
had not led that evidence in the present matter.
The
respondent submitted that the evidence showed that it had done enough
to secure the finances required for the project but the appellant
failed to come to the party. It further blamed the conduct of the
respondent's shareholder, the Government of Zimbabwe, as being
partly to blame for the appellant's failure to perform.
The
respondent dismissed the evidence given by the appellant's sole
witness as ineffectual because the witness admitted that he was not
competent to testify on matters which only the appellant`s CEO could
shed light on. This witness was, according to the respondent, unable
to give evidence proving the value of the pre-commencement work done,
nor could he dispute the contention that it was the appellant that
actually owed the respondent.
The
respondent insisted that the addendum to the contract was not a
separate document running parallel to the main agreement as contended
by the appellant. Rather, the addendum should be interpreted as an
integral part of the main agreement.
Further,
the respondent contended that the appellant had frustrated the
financing agreements and, for that reason, the court should deem the
condition precedent to have been fulfilled in line with the doctrine
of fictional fulfilment.
Reliance
was placed on the case of Scott
& Anor v Poupard & Anor
1971
(2) SA 373 (A) wherein the factors to be established in order to
invoke the doctrine of fictional fulfilment were set out as follows:
(i)
Non fulfilment of the condition;
(ii)
The defendant's breach of his duty with intent to frustrate the
fulfilment; and
(iii)
A causal link between the non-fulfilment and the defendant's
intentional frustration of the fulfilment of the condition.
The
respondent averred that generally the court does not have a
discretion to refuse to enforce a term contained in a lawfully
concluded agreement. In determining whether or not to enforce such a
term, the court will be guided by the dictates of public policy.
It
submitted that the evidence adduced showed that the appellant had
frustrated the conclusion of financial agreements. The appellant,
argued the respondent, should not be allowed to benefit from its own
wrongdoing.
The
appellant had not placed before the court the FIDIC document despite
its plea that the agreement should be read in light of the provisions
thereof. For this reason the respondent contends that the FIDIC
cannot be a factor in the interpretation of the agreement.
The
appellant's closing remarks were to the following effect.
It
submitted that Mr Chivhayo's evidence was unreliable and thus the
respondent had failed to discharge the onus on it to prove its claim.
It accused this witness of changing his evidence when it suited him.
It said that his evidence was inconsistent with contemporaneous
documents and that he referred to non-existent documents.
The
appellant also made reference to the proceedings in case number SC
39/21 and submitted that in that case this Court made a finding that
the respondent had failed to meet the conditions precedent set out in
clause 5 of the contract.
This
Court, according to the appellant, had established that the
respondent had conveniently avoided the action procedure in a bid to
stay away from the truth and hoodwink the court.
The
appellant also argued that in its evidence, the respondent based its
claim on contentious issues raised by the appellant in its
replication and not based on its own declaration. The appellant
argued that the respondent ought to have amended its declaration to
incorporate the claims that were never pleaded in the declaration.
The
areas of evidence of concern included the China-Exim Bank financing
issue, the CBZ and ATC funding and the allegation that the appellant
filed fictitious and malicious charges of fraud and corruption
against Mr Chivhayo.
The
appellant also submitted that the letters of 10 April, 6 July and 31
July 2018 which were alleged to constitute a breach of the contract
in the respondent's declaration were never referred to in the
examination in chief of the respondent's witness.
The
court a
quo
observed
that the matters complained against in this regard are matters of
evidence which would not ordinarily be set out in the pleadings but
in the evidence.
The
appellant further submitted that it was common cause that the
conditions precedent satisfaction period expired on 23 October 2017
and that the purported extension of that period by six months after
that date, though not in accordance with the contract, was not a
nullity as the respondent could have accepted it.
It
averred that although its notice to terminate was not delivered in a
letter headed “Notice of Termination” it remained a valid notice.
It
contended that the issue is not about the absence of notice but,
rather, whether the appellant had the right to terminate the
contract, it being alleged that it (the appellant) was responsible
for the delay in the satisfaction of the conditions precedent.
The
appellant submitted that the respondent alleged a breach of Addendum
1, which breach would only affect Schedule 11 of the contract but not
clause 5 of the contract.
It
submitted that the respondent had failed to indicate
when these breaches had occurred.
It
further contended that Addendum 1 was only executed one month before
the expiry of the conditions precedent satisfaction period,
or 23 months after signature of the contract. An alleged breach of
Addendum 1, it is contended, could not explain the failure to
complete the conditions precedent in the preceding 23 months.
The
appellant argued that this was not a proper case in which the court
could exercise its discretion in granting specific performance
because the present position was at odds with the parties original
position. The original intention was that the project would take four
years. It is contended that the construction and hand over of the
solar plant would thus have been completed by October 2019.
The
appellant argued that if specific performance were to be granted as
requested, the project would be implemented between March 2029 to
2034, 10 to 15 years later than originally projected.
In
any event, argued the appellant, the project was no longer viable
because the cost of constructing the plant had decreased due to
advances in solar technology. As a result the respondent stands to
make an additional USD33 million profit should specific performance
be granted.
The
appellant further argued that the fact that the parties negotiated a
new contract after the judgment of the court a
quo
in
case number HC 8159/18, was testimony to the fact that the parties
had realised that the present contract was no longer viable.
It
was for that reason that the parties carried out a joint visit to the
project site on 13 July 2020. The Minister of Energy had urged the
parties to implement this amended contract. The appellant averred
that the Ministerial report related to the amended contract and not
the original contract. Another reason for negotiating the new
contract was that the African Development Bank had debarred CHINT for
fraudulent practices. Further, the appellant averred that the
introduction of a new currency regime in February 2019 had
implications on the funding of the project as all transactions in USD
terms done before February 2019 were now valued in RTGS dollars at
the rate of one to one with the USD.
It
was also the appellant's argument that the respondent had failed to
plead relief relating to fictional fulfilment and the factual basis
upon which the court could grant the relief of fictional fulfilment.
The
appellant further argued that fictional fulfilment would not make
sense because the project needed to be funded and that, in any event,
the appellant would not be able to pay the contractual amount.
It
was submitted by the appellant that its board could not authorise the
commencement of the project knowing fully well that it was not going
to be funded.
The
appellant also argued that if fictional fulfilment were granted,
there would be implications on third parties in line with the
definition of “financial agreements.”
It
was for example, a requirement that the Government of Zimbabwe be a
co-signatory to the financial agreements. That requires that the
Government be a fictional party to the fictional finance agreement.
It was submitted that there was no basis upon which the court could
exercise jurisdiction over Government when it was not cited as a
party to the present proceedings.
The
appellant denied that it intended to frustrate the project, citing
its actions in paying the sum of USD5.6 million to the respondent and
in extending, through its letter dated 29 November 2017, the
conditions precedent satisfying period.
It
argued that it was the one that took steps to secure funding for the
project by communicating with key stakeholders such as Ministry of
Finance, the procurement board and NSSA. It had also carried out all
the conditions precedent which required its attention such as the
feasibility studies, due diligence, getting the Environmental Impact
Assessment Certificate and acquiring land for the project.
On
the contrary, the appellant submitted that the respondent had failed
to provide an Advance Payment Guarantee and the performance security
as required in terms of the contract. The appellant also blamed the
respondent for the collapse of the China Exim Bank funding stating
that if the respondent had done its due diligence, it would have
known from the beginning that the financial institution would not be
in a position to assist in view of the Government of Zimbabwe's
arrears with the financial institution.
With
regards the respondent's claim for the sum of US$3 million for
expenses incurred, the appellant submitted that no evidence had been
led to prove that it was responsible for causing the damages
complained of. It argued that it cannot be held liable for the
expenses incurred by the respondent during the tendering process.
Such expenses could be recovered through performance of the contract
when profit is then earned.
The
appellant also denied liability for the respondent's loss of profit
arguing that such a claim is only tenable where the appellant had
terminated the contract. In casu
the
respondent avers that the contract was not terminated. There is
therefore no basis upon which it could raise such a claim.
Concerning
its claim in reconvention, the appellant submitted that it provided
the respondent with an advance of US$5.6 million. Of this amount, the
sum of US$2.3 million went towards the feasibility studies. Its claim
is for the balance in the sum of US$3,310,736.30.
The
respondent was required to contribute the sum of US$1 million towards
pre-commencement works. The contribution was to be done through the
carrying out of works, with no cash payments. However, the appellant
avers that the pre-commencement works were not completed as indicated
in the joint site visit report hence the claim for US$3,310,736.30.
Alternatively,
the appellant was willing to be compensated in terms of the
respondent's own computation which puts the figure at
US$2,299,563.13.
It
was on that basis that the appellant moved for dismissal of the
respondent's claim. It also prayed that its claim in reconvention
be granted with costs.
FINDINGS
OF THE COURT A
QUO
The
court a
quo
found in favour of the respondent and dismissed what remained of the
appellant's counter claim. Its specific findings on the issues
before it were as follows:
1.
The Supreme Court judgment in SC 39/21
The
appellant had raised the defence of res
judicata
premised on the decision of this Court in SC 39/21. That proved
untenable as the papers clearly showed that the appeal was determined
on a technicality, namely that the application in the court a
quo
had been replete with material disputes of fact which could not be
determined without hearing viva
voce
evidence. The court a
quo
held
that this Court had not delved into the merits of the matter as
alleged by the appellant. No decision on the merits had been made and
therefore the appellant's claim to the contrary was rejected.
2.
Whether the EPC contract remained valid and binding on the parties
The
court a
quo
noted that the appellant had abandoned its claim to the effect that
the contract had been induced by fraudulent misrepresentation on the
part of the respondent. That being the case, the court a
quo
noted that in the absence of the appellant's assertion to the
contrary it must be presumed that the validity of the contract is no
longer in contention.
That
being the case the court a
quo
took
the view that the only issue left for determination was the status of
that contract. It observed that the status of the contract was the
central issue upon which the consequential reliefs sought by the
respective parties would be determined.
The
respondent's contention was that the amended contract remained
valid and binding, hence its claim for consequential relief in the
form of specific performance. On the other hand, noted the court a
quo,
the appellant sought a declaratur to the effect that the contract
never commenced as a result of the respondent's failure to meet the
prescribed conditions precedent.
The
appellant also averred that it had cancelled the contract as a result
of that breach on the part of the respondent.
It
further claimed (falsely in the opinion of the court a
quo)
that the cancellation had been confirmed by this Court under SC
39/21.
The
court a
quo
reiterated its earlier findings, namely that this Court had merely
upheld the appellant's preliminary point to the effect that the
court a
quo
should have proceeded not by application, but by action, as there
were material disputes of fact which could not be resolved on the
papers. It did not determine the merits of the matter, let alone
confirm the appellant's cancellation of the contract.
The
count a
quo
proceeded to consider the clauses of the contract which the
respondent alleged had been breached.
Clause
5 provided that the contract would commence in full force when the
conditions listed in paras (a) to (i) were satisfied. These
conditions precedent were to be satisfied within a period of 24
months after signature of the contract.
It
was common cause that this period would expire on 23 October 2017.
The
appellant could, at its sole discretion, on or at any time prior to
that date, elect to extend the conditions precedent satisfaction
period by a further 6 months by giving notice to the respondent. More
importantly, clause 5 of the contract provided as follows:
“If
the conditions precedent are not satisfied on or before the expiry of
the CP satisfaction period (as may have been extended), either party
may elect to terminate the contract by notice to the other provided
that if a party is causing a delay to the satisfaction of any of the
conditions precedent as at the date on which it seeks to terminate,
such party shall not be entitled to exercise such right of
termination while such cause of delay subsists.”
The
court a
quo
noted the
implications of the above provisions, particularly with regards the
right of termination.
Clause
5 of the contract also provided for the waiver of conditions
precedent as follows:
“Each
party shall use its reasonable endeavours to ensure the satisfaction
of the conditions precedent set out above, provided that:
(a)
The employer may waive the contractor conditions precedent and such
waived contractor condition(s) precedent will be deemed satisfied for
the purposes of this Agreement;
(b)
The contractor may waive the employer conditions precedent and such
waived employer conditions precedent will be deemed satisfied for the
purposes of this Agreement; and
(c)
And, except where a party has failed to use its Reasonable Endeavours
to ensure the satisfaction of such conditions precedent, neither
party shall be liable in any damages to the other in respect of any
failure to satisfy any of its conditions precedent.”
The
court a
quo
analysed
and took note of these provisions.
Of
significance to the status of the contract, the parties signed
Addendum 1 to the contract. The court a
quo
noted
that in para 2 of the preamble to the Addendum 1 the parties
expressed their wish “to amend the contract through this addendum.”
More importantly, clause 4 of the Addendum provided that “the
parties agree and acknowledge that with effect from the effective
date of this Addendum that the contract shall be amended in
accordance with this Addendum and that the provisions of the
contract, except as amended by this Addendum, will remain in full
force and effect.”
The
court a
quo
concluded
that the Addendum amended the contract and that the two documents
must be read together.
The
court a
quo
analysed
the nature and scope of the amendments to the original contract
brought about by the provisions of Addendum 1. It observed as
follows.
At
the time that the parties signed the Addendum on 21 September 2017,
they were aware that in terms of the original contract, the period
during which the conditions precedent were to be fulfilled was to
lapse on 23 October 2017, a month after the date of signature of the
Addendum. However, the addendum gave lead times of the various
pre-commencement works well beyond 23 October 2017.
In
other words, the new lead times exceeded the effective date of 23
October 2017, when all conditions precedent should have been met and
hopefully, the main works would have commenced.
From
the above facts, the court a
quo
concluded
that by their conduct, the parties waived not only the commencement
date of the contract but, by the same token, the date of the
accomplishment of the conditions precedent upon which the
commencement date was predicated.
It
was for this reason that the court a
quo
held
that it would defy logic for the appellant to insist on the
termination of the contract on the grounds that the respondent had
failed to satisfy the conditions precedent when, only a month before
the expiry date, the parties had agreed to certain contractual
obligations that further tied them.
The
court a
quo
concluded, in the circumstances, that the conditions precedent
satisfying period did not lapse on 23 October 2017 as submitted by
the appellant.
The
parties must be regarded as having waived their right to enforce that
date as previously provided in the original contract before the
Addendum I was signed, amending it.
The
parties had set their eyes beyond 23 October 2017 concluded the court
a
quo.
Indeed,
the appellant had written to the respondent on 29 November 2017,
purporting to extend the conditions precedent satisfying period by a
further six months in terms of clause 5 of the main contract.
The
court a
quo
noted that such correspondence confirmed that the appellant did not
regard that this period ended on 23 October 2017, contrary to its
assertions.
Secondly,
the correspondence wrongly ignored the provisions of the Addendum 1,
amending the contract thus disregarding the effective date, of 23
October 2017, the date originally set for the expiry of that period.
Thirdly
in terms of section 5 of the original contract such election by the
appellant to extend such a period by a further six (6) months was to
be done in terms of clause 6 of the contract, which provides that the
contract may only be amended by a written document duly executed by
the parties.
In
this case the appellant acted unilaterally there being no evidence of
the parties agreement to such an amendment.
Further,
any such election could only be effected on or before 23 October
2017. In casu,
the appellant's election came on 29 November 2017, well out of
time.
The
court a
quo
also noted that in terms of clause 5(i) of the contract if the
conditions precedent were not satisfied within twenty-four (24)
months from the date of signature of the contract, the parties were
to meet and review progress towards the satisfaction of those
conditions.
Thus
the court a
quo
found that the election to extend the satisfaction period by a
further six (6) months could only be exercised after the parties had
reviewed their progress towards the satisfaction of those conditions
precedent.
No
such meeting was proved to have taken place and accordingly no valid
election to extend the period could have been exercised.
For
these reasons, the court a
quo
found that the purported extension of the conditions precedent
satisfying period by the appellant was inconsistent with the
provisions of the contract and consequently, null and void.
Accordingly,
the court a
quo
ruled that the contract remained valid and extant.
3.
Fictional
Fulfilment
Having
determined that the contract was not terminated and remained extant,
the court a
quo
considered the relief sought by the respondent, namely whether there
was fictional fulfilment of the contract and if so, whether it was
appropriate to grant the remedy of specific performance.
It
observed that the doctrine of fictional fulfilment was defined in
case law. It relied on the definition in MacDuff
& Company Limited v Johannesburg Consolidated Investments Company
Limited 1924
AD 573 where the court stated as follows:
“I
am therefore of the opinion that in our law a condition is deemed to
have been fulfilled as against a person who would subject to its
fulfilment be bound by an, obligation, and who had designedly
prevented its fulfilment, unless the nature of the contract or the
circumstances show an absence of
dolus
on his part.”
RH
Christie in “Business Law in Zimbabwe” at p56 explains that dolus
in this context does not allude to fraud or dishonesty, but a
deliberate intention to prevent the fulfilment of the condition, no
matter how laudable the motive.
Based
on both the documentary and viva
voce
evidence before it, the court a
quo
found
that the appellant purposefully prevented or frustrated the
fulfilment of the condition precedent pertaining to the signing of
the financing agreements.
The
court a
quo
also found the appellant's conduct to have been contrary to clause
5(i) of the contract which required each party to use its “reasonable
endeavours” to ensure the satisfaction of the conditions precedent.
The
court a
quo
noted
that the right to terminate the contract in terms of clause 5 was not
absolute because the party responsible for frustrating the fulfilment
of any of the conditions precedent was estopped from seeking the
termination of the contract.
For
that reason, having found that the appellant frustrated the
fulfilment of the financing arrangements, the court a
quo
ruled
that the appellant was precluded from asserting the right to
terminate the contract on the grounds that the condition precedent
concerned had not been met.
It
was in that context that the court a
quo
held
that the conditions precedent pertaining the financial arrangements
had been fictionally fulfilled.
4.
Specific Performance
In
determining whether it could grant the relief of specific performance
as sought by the respondent, or, the alternative relief of damages,
the court a
quo
relied
inter
alia,
on the decision in Grandwell
Holdings (Pvt) Ltd v Zimbabwe Mining Development Corporation & 3
Ors
SC 5/20 where this Court had this to say:
“However,
the right to claim specific performance is predicated on the concept
that the party claiming it must first show that he or she has
performed all his or her obligations under the contract or is ready,
willing and able to perform his or her side of the bargain. Even
then, the court has a discretion, which should be exercised
judicially, to grant or refuse a decree of specific performance. It
follows therefore that the court's discretion should not be
exercised arbitrarily or capriciously.”
The
court a
quo
also
relied on the case of Minister
of Public Construction and National Housing v Zescon (Pvt) Ltd
1989
(2) ZLR 311 (S) where at 318 G, this Court stated as follows:
“The
law is clear. This is a remedy to which a party is entitled as of
right. It cannot be withheld arbitrarily or capriciously.”
The
court a
quo
noted
that in exercising its discretion to grant an order for specific
performance it must look at the circumstances of this case and on
that basis map the way forward.
It
observed that the appellant had not placed before it any evidence to
show the measures it took in order to achieve financial closure. In
other words, nothing hand been put forward to show that specific
performance was no longer achievable. It noted that both parties had
accepted that the question of funding was central to the
implementation of the project.
The
court a
quo
rejected
the submission by the appellant that the project was no longer viable
and that it would take years to complete. It referred to clause
1.1.3.3 of the contract which gave the time of completion to be 540
days.
It
noted that it had ruled that the contract was still valid and not
terminated, that Addendum 1 had amended the main contract and
extended the conditions precedent satisfying period beyond the
contemplated date. It further noted that clauses 5(ii) and 6 oblige
the parties to meet and review progress on the project and effect
such appropriate measures and amendments as may from time to time be
required.
For
that reason, the court a
quo
was
of the view that any challenges arising from the effect of the
changes to the currency regime can be similarly resolved by the
parties in terms of clause 5(i) and clause 6.
In
short, the court a
quo
dismissed
the appellant's submissions against the grant of specific
performance.
The
court a
quo
noted
that at some point the parties could have agreed to implement the
project in phases and that the respondent had obtained funds for the
implementation of the initial phase. That position was captured in
the draft Amended Restated Contract, which the parties are yet to
sign.
It
concluded its observations as follows:
“The
point is that the question of the unavailability of funding is
clearly not an excuse going by the evidence that was placed before
the court.”
It
was for these reasons that the court a
quo
ordered
specific performance.
5.
Whether the claim in reconvention had merit
The
court a
quo
held
that the counter claim could only become relevant if it had held that
the contract did not commence as a result of the respondent's
failure to fulfil the conditions precedent.
In
view of its finding that the contract remained valid and binding on
the parties, the counter claim was no longer sustainable.
It
noted that the amount paid towards the pre-commencement works was not
entirely wasted and observed that this was an issue that the parties
could discuss in terms of clause 5(i) of the Contract. This clause
provided for periodical performance reviews.
Consequently,
the court a
quo
found in favour of the respondent and issued the following order:
“1.
The procurement contract for the Engendering, Procurement and
Construction (EPC Contract) of the 100 MW Gwanda Solar Project (ZPC
304/2015) between the plaintiff and the defendant as amended is valid
and binding between them.
2.
Consequent to the declaration of the validity of the EPC Contract, an
order for specific performance of the said contract is hereby
granted.
3.
The defendant's claim in reconvention is hereby dismissed with
costs.
4.
The defendant shall pay the plaintiff's costs in the claim in
convention.”
It
is that order that the appellant appeals against on no less than 17
grounds as follows:
“GROUNDS
OF APPEAL
1.
The court a
quo
erred in law in that it failed to consider the respondent's case as
pleaded in its declaration and proceeded, instead, to determine the
matter on the basis of issues not pleaded in the declaration.
2.
The court a
quo
erred in law by finding that the appellant had waived the conditions
precedent satisfaction period and/or the requirements to fulfil the
conditions precedent, when such a waiver was not pleaded by the
respondent in its declaration.
3.
The court a
quo
erred
in fact by finding that the appellant had waived the conditions
precedent satisfaction period and/or the requirements to fulfil the
conditions precedent when the factual basis of such a waiver was not
made out on the evidence.
4.
The court a
quo
erred in law and fact by holding that the appellant had effectively
waived the fulfilment of the conditions precedent by allowing some
pre-commencement work to be carried out before the fulfilment of the
conditions precedent.
5.
The court a
quo
erred in law and fact by holding that when the parties entered into
Addendum l, they only had one month before the contract lapsed, in
circumstances where the contract expressly provided that the parties
could extend the conditions precedent satisfaction period.
6.
The court a
quo
erred in law and fact by holding 'mero
motu'
that the activities set out in Addendum l “would certainly outlive
the contract” in circumstances where neither party asserted this to
be the case, nor introduced any evidence to that effect.
7.
The court a
quo
erred in law and in fact by holding that the appellant had waived the
application of the conditions precedent satisfaction period by
attempting to extend that same satisfaction period.
8.
The court a
quo
erred in law by relying on the appellant's purported extension as
amounting to or evidencing a waiver, having found that the same
purported extension was a nullity.
9.
The court a
quo,
having correctly found that Addendum l obliged the respondent to
provide an advance payment guarantee, erred in law and in fact by
finding that the appellant had waived that condition precedent by
entering into Addendum l.
10.
The court a
quo
erred in law by holding that the abandonment of the appellant's
misrepresentation claim meant that the continued existence of the
contract was no longer in issue and, as a result, failed to consider
the appellant's case relating to termination by notice.
11.
The court a
quo
erred in law by finding that the conditions precedent (or some of
them) were fictionally fulfilled, in circumstances where fictional
fulfilment was not pleaded by the respondent in its declaration.
12.
The court a
quo
erred in law by addressing only one particular condition precedent,
relating to funding, and ignoring the other conditions precedent
which the parties had expressly agreed.
13.
The court a
quo
erred in law by finding that the conditions precedent, or some of
them, were fictionally fulfilled, in circumstances where the
respondent had admitted before the Supreme Court that the respondent
had failed to meet the prescribed conditions precedent.
14.
The court a
quo
erred in law by finding that the conditions precedent had first been
waived and then subsequently fulfilled.
15.
The court a
quo
erred in law by considering the actions and attitudes of third
parties as relevant on the basis that those third parties were
shareholders or ultimate shareholders of the appellant.
16.
The court a
quo
erred in law and fact by granting specific performance of the
contract in circumstances where the project had not been funded. Its
performance would result in undue hardships and the respondent was
not able of performing in accordance with the express terms of the
contract.
17.
The court a
quo
erred in law and fact by rejecting the appellant's claim in
reconvention in circumstances where it received unchallenged evidence
that the appellant had received no benefit from the pre-commencement
works.”
RELIEF
SOUGHT
The
appellant seeks the following relief:
“1.
The appeal succeeds with costs; and
2.
The judgment of the court a
quo
be set aside and substituted with the following:
(a)
The plaintiff's claim be and is hereby dismissed with costs.
(b)
The defendant (read plaintiff) be and is hereby ordered to pay
damages in the sum of USD3,310,736-30 with costs, being advance
payment towards the pre-commencement works with costs.” (Own
brackets)
Rule
44(1) of the Supreme Court Rules 2018, requires that an appellant's
grounds of appeal be set out clearly, specifically and concisely.
The
grounds of appeal in
casu
appear not to have been drafted accordingly.
They
are repetitive, inconcise and seem to be aimed at every decision of
fact or law made by the court a
quo.
Mr
Tivadar,
for the appellant, was, at the hearing of this appeal, asked to
justify the state of the appellant's grounds of appeal, and explain
why the appeal should not be struck off the roll for defective
grounds of appeal.
Mr
Uriri
for the respondent, was not keen to go that route, preferring instead
to have the matter decided on the merits.
Indeed,
he did not persist with the objection he had lodged in the
respondent's papers. He was of the view that the grounds of appeal
may be distilled to only four issues, namely:
(1)
Was the judgment predicated on the pleaded case.
(2)
Were the findings of fictional fulfillment predicated on the facts
and evidence.
(3)
Were the findings of waiver of the conditions precedent founded on
the evidence.
(4)
Was the counterclaim properly dismissed.
On
his part, Mr Tivadar,
for the appellant, summarized the import of the grounds of appeal to
be as follows:
1.
That the court a
quo
erred by making a finding that was contrary to the position of the
respondent in SC39/21 where the respondent admitted that it had not
met the conditions precedent.
3.
The court a
quo
incorrectly found that the appellant had waived its right to cancel
the contract on the basis of unfulfilled conditions precedent.
4.
The court a
quo
wrongly found that there had been fictional fulfilment of the terms
of the contract.
5.
The court a
quo
erred when it ordered specific performance of the contract.
Although
both parties perceived grounds of appeal are largely similar, it is
noted that Mr Tavadar
has not included, in his summary of the grounds of appeal, ground 1
as proposed by Mr Uriri
which relates to the question whether the judgment was predicated on
the pleaded case.
Further,
Mr Tivadar
did not include in that summary ground 4 as proposed by Mr Uriri,
namely, whether the counter claim was properly dismissed.
As
it is not clear whether, by doing so, Mr Tivadar
was abandoning the grounds in question, this Court shall assume, as
appears on the papers, that the issues raised therein are alive,
requiring determination on the part of this Court.
This
Court identifies the following, arising from the parties submissions,
to be the grounds of this appeal.
1.
That the court a
quo
erred by making a finding that was contrary to the position of the
respondent in SC39/21 where the respondent admitted that it had not
met the conditions precedent.
2.
The court a
quo
incorrectly found that the appellant had waived its right to cancel
the contract on the basis of unfulfilled conditions precedent.
3.
The court a
quo
wrongly found that there had been fictional fulfilment of the terms
of the contract.
4.
The court a
quo
erred when it ordered specific performance of the contract.
5.
That the judgment was not predicated on the pleaded case.
6.
That the counter claim should not have been dismissed.
The
issues for determination
arise
from the above grounds of appeal.
ISSUES
FOR DETERMINATION
The
grounds of appeal raise six issues, namely;
(1)
Whether the court a
quo
made a finding which was contrary to the position of the respondent
in SC 39/21.
(2)
Whether the court a
quo
erred in finding that the conditions precedent had been waived.
(3)
Whether the court a
quo
erred when it held that fictional fulfilment of the contract had
occurred.
(4)
Whether the court a
quo
erred in ordering specific performance of the contract.
(5)
Whether the judgment of the court a
quo
was
predicated on the pleaded case.
(6)
Whether the counter claim was properly dismissed.
SUBMISSIONS
BEFORE THIS COURT
The
parties submissions before this Court were largely similar to the
submissions they made in the court a quo.
Submissions
by the appellant
Mr
Tivadar,
for the appellant, submitted that the court a
quo
erred when it failed to consider the respondent's case as was
pleaded in its declaration and instead proceeded to determine the
matter on the basis of issues not pleaded in the declaration.
Mr
Tivadar
also submitted that the court a
quo
erred in law by finding that the appellant had waived the conditions
precedent satisfying period, or the requirement to fulfil the same
when such a waiver was not pleaded by the respondent in its
declaration.
He
further submitted that, in any event, the actual basis of such waiver
had not been made out in the evidence.
He
also criticised the court a
quo
for concluding that by allowing some pre-commencement works to be
carried out before the fulfilment of the conditions precedent, the
appellant had waived the fulfilment of those conditions.
He
submitted that this conclusion runs foul to the provisions of the
contract wherein it is provided that pre-commencement works could be
undertaken prior to the satisfaction of the conditions precedent. He
cited clause 8 of the contract which provides that the respondent was
to carry out pre-commencement works as set out in schedule 11 of the
contract.
He
said that the parties had agreed that pre-commencement works could be
carried out prior to the satisfaction of the conditions precedent
satisfying period. This was meant to shorten the contract period. It
cannot be the basis for the inference of waiver of the conditions
precedent satisfying period.
Further,
it was submitted that the fact that the Addendum 1 was signed a month
before the anticipated date of completion of the conditions precedent
did not have a bearing on the contract. This is so because the
parties could extend the conditions satisfaction period by a further
six months.
Mr
Tivadar
also attacked the court a
quo
for holding that the abandonment of the appellant`s claim of
misrepresentation meant that the continued existence of the contract
was no longer in issue, and, as a result failed to consider the
appellant`s case relating to termination by notice. For that reason
he maintained that the contract was terminated by operation of law,
thereby effectively terminating the contractual obligations between
the parties.
It
was further submitted that the court a
quo`s
finding of fictional fulfilment of the conditions precedent was
without legal or factual basis.
It
was observed that in its declaration the respondent had not sought
any declaration as to fictional fulfilment of the conditions
precedent. For that reason, Mr Tivadar
argued that the court a
quo
ought not to have entertained the argument that there was fictional
fulfilment of any of the conditions precedent.
Further
he argued that the respondent had failed to plead the relevant
factual assertions to merit a finding of fictional fulfilment. In
particular, he argued that the respondent did not plead that the
appellant intended to frustrate the fulfilment of any of the
conditions precedent. Counsel further submitted that no evidence was
led to prove that the appellant had intentionally frustrated, the
fulfilment of any condition precedent. Fictional fulfilment implies
fictional funding. The appellant did not have the funds to pay out
the contractor and therefore fictional fulfilment was an exercise in
futility. Besides, fictional fulfilment would bind third parties,
such as the Government of Zimbabwe which, in terms of the contract,
was to be a co-signatory to the financing agreements. In any event,
the appellant never intended to frustrate the project and had wished
to deliver in terms of the contract.
Mr
Tivadar
also made reference to SC 39/21 alleging that in that case the
respondent made an admission with regards the non-fulfilment of the
conditions precedent and that this Court noted that the respondent
had failed to meet the prescribed conditions precedent under clause
5(a) of the contract. He argued that in light of that finding by
this Court, the court a
quo
could not have found that the conditions precedent had been
fictionally fulfilled.
It
was further submitted that having ruled that the conditions precedent
had been waived, the same court a
quo
could not have found that the conditions precedent had been
fictionally fulfilled.
The
appellant was of the view that the court a
quo
should not have considered the actions of third parties in
determining the issues before it. It was argued that although
Government is a shareholder of the appellant, its actions and
attitude cannot be visited on the appellant because the appellant is
a different legal persona, separate from its shareholder.
Mr
Tivadar
submitted that specific performance of the contract should not have
been granted. He cited authorities such as the case of Grandwell
Holdings Private Limited v Zimbabwe Mining Development Corporation &
3 Ors
SC 05/2020 which outline the factors to be considered in granting the
remedy of specific performance. Firstly, specific performance is a
discretionary remedy and in determining its grant, the court must
look at all the relevant facts. The remedy will not be granted if
compliance with the order is impossible or would cause undue hardship
or where the plaintiff is not ready to carry out its own obligation
under the contract.
Mr
Tivadar
submitted
that the project had not been funded and that its performance would
result in undue hardship to the appellant. Further the respondent was
not able to perform in terms of the contract. For these reasons he
submitted that specific performance should not have been granted.
RESPONDENT'S
SUBMISSIONS
Mr
Uriri
for the respondent, submitted that the appellant's case, as
presented in its heads of argument, is based on general principles of
law which principles the appellant failed to connect to the facts and
the evidence.
He
further submitted that the assertion by the appellant that the
respondent's case was predicated on matters not raised in its
declaration, but on matters only raised in its replication, was ill
informed. In making that assertion, the appellant had identified the
following issues as arising only in the respondent`s replication; the
China Exim Bank issue, the CBZ and ATC funding and the question of
the malicious allegations against the respondent`s Managing Director.
Mr
Uriri
submitted
that in doing so, the appellant had failed to recognise the
distinction between the cause of action, the facts giving rise to the
cause of action and the issues as joined in the pleadings.
In
particular he submitted that the law requires that a party pleads the
facts giving rise to the cause of action not the evidence by which
the facts are to be proved. Thus the evidence is not a matter for the
summons and declaration but for discovery and trial. The court a
quo
did
relate to the pleadings, the issues and the evidence and made a
determination.
Mr
Uriri
was
adamant that such determination could not be faulted.
He
also dismissed the submission by the appellant that the claim was
expanded in the replication and that the expansion is immaterial
without an amendment to the declaration. In that regard Mr Uriri
relied, inter
alia
on
the case of Shah
v Kingdom Merchant Bank
SC 4/2017, wherein this Court held that parties can extend their
issues and that once an issue was before the court, the court has the
prerogative to consider it. Mr Uriri
also relied on the case of British
Diesels Ltd v Jeram & Sons
1958 (3) SA 605 (N) where it was held that the importance of
pleadings should not be unduly magnified for “if it should appear
that any substantial issue was duly canvassed in the court below,
then in my opinion, we ought to regard it as an issue to be decided
between the parties, whether it has been formally pleaded or not.”
Similar sentiments were also expressed in Sentrachem
Bpk v Wenhold
1995 (4) SA 312 (A).
With
regards the question of whether or not the appellant had waived its
right to rely on the non-fulfilment of the conditions precedent as a
basis for termination of the contract, Mr Uriri
submitted that waiver is a legal principle which can be derived from
the facts of the case. In the instant case he argued that the court a
quo
based
its decision on the facts as presented to it. That finding of fact
cannot be lightly interfered with in the absence of gross
misdirection or irrationality. There being no allegation of such
irregularity, the finding of fact by the court a
quo
was
unassailable. He relied in that regard on the case of Hama
v National Railways of Zimbabwe
1996
(1) ZLR 250 (S).
Similarly,
Mr Uriri
argued that the grounds of appeal lack merit as the appellant failed
to appreciate that the “ratio
decidendi”
was predicated primarily on the issues and findings of fact. It was
for that reason that the agreement was found to be extant and
specific performance found to be possible.
With
regards the evidence adduced in the court a
quo,
Mr Uriri
noted
that the court a
quo
made a finding of credibility in favour of the respondent's sole
witness, Mr Chivhayo. He submitted that the evidence adduced by Mr
Fambi, on behalf of the appellant, left a lot to be desired.
He
chronicled Mr Chivhayo's evidence and noted that it was upon the
respondent to raise the necessary funding for the project. He
submitted that the evidence given by Mr Chivhayo shows how the
appellant had frustrated the respondent's efforts aimed at
financial closure for the project. Mr Chivhayo also told the court a
quo
that
the respondent wished to conclude the project. Mr Uriri
submitted that it was not shown that it was not possible to do so.
For that reason it was appropriate for the court a
quo
to
grant the remedy of specific performance.
He
further submitted that any evidence elicited from Mr Chivhayo under
cross examination as to the meaning of the contractual documents does
not bind the court.
As
regards the relationship between the appellant and the Government of
Zimbabwe, Mr Uriri
submitted that the distinction that the appellant sought to make
between the two was not tenable at law, as the Government exercises
control over the appellant as its shareholder. He said it is common
cause that the appellant is a State commercial entity. He relied on
the decision in Transnet
Ltd v Goodman Brothers Pty Ltd
2001 (1) SA 853 (SCA) at 870F where SHULTZ JA, said:
“I
do not think that anything can be made of the fact that Transnet is
now a limited company. The government still owns all the shares in it
and thus has ultimate control.”
Reliance
was also placed on Grandwell
Holdings Limited & Ors v Minister of Mines & Ors
HH 193/16 (a judgment upheld by this Court on appeal) wherein
MAFUSIRE J concluded that the Minister of Mines, the Zimbabwe Mining
Development Company and companies in which the State had an economic
interest, were a single economic unit. Thus the positive or negative
control of the shareholder cannot be divorced from the company. In
short, therefore, the appellant cannot escape the negative conduct of
its shareholder.
Mr
Uriri
submitted that the appellant's sole witness admitted that he was
not involved in the process of financial closure as this was the
preserve of the appellant's managing director. He was thus not in a
position to challenge the evidence proffered by the respondent and
its witness. Further, while disputing the value of the
pre-commencement works, neither the witness nor the appellant placed
evidence of the value of the works that were carried out. On the
contrary, the witness conceded that there was value in the works done
and that same had been completed. He also confirmed that the
respondent had been barred from site and thus could not do repair
work. He could not dispute that the appellant in fact owed the
respondent.
Mr
Uriri
said that notice of this computation had been given in the
respondent's plea to the appellant's counterclaim. The
appellant's replication did not address specifically this
allegation. Not having addressed this allegation, the appellant must
be presumed to have admitted it.
Mr
Uriri
submitted that the court a
quo
correctly
entered judgment for the respondent.
Mr
Uriri
further argued that fictional fulfilment of the financial conditions
precedent flowed from the conduct of the appellant in frustrating the
financial closure. This condition was for that reason presumed
fictionally fulfilled. The following cases were cited in support of
that assertion: Mia
v Verimark Holdings Pty Ltd
2010 (1) ALL SA 280 (SCA) and Standard
Chartered Bank Zimbabwe Ltd v Matsika
1997 (2) ZLR 389.
ANALYSIS
APPLYING
THE LAW TO THE FACTS
(1)
Whether the court a quo made a finding which was contrary to the
position of the respondent in SC 39/21
The
first issue is based on a ground that has no merit whatsoever. As
properly observed by the court a
quo,
this Court allowed the appeal in SC 39/21 on the basis of a
technicality. It held, on a preliminary point raised by the appellant
that the respondent should not have proceeded by way of application
in the court a
quo
because the matter was replete with disputes of fact which could not
be determined on the papers before the court a
quo.
In
short, the respondent should have proceeded by way of action.
That
is precisely what the respondent did in the matter presently before
this Court on appeal. No issues on the merits were touched on by this
Court under SC 39/21. This ground of appeal has absolutely no merit.
Even
if it were to be accepted that the respondent, in papers filed under
SC 39/21, agreed that conditions precedent had not been met, such
admission does not take either party's case further. The real
dispute is whether, the conditions precedent not having been met at
some point, the parties took remedial action. The parties could have
left the contract to terminate by operation of law, the conditions
precedent not having been met.
Neither
party took that route, both parties preferring to enter into an
Addendum to the contract, a month before the conditions precedent
satisfying period expired. The parties differ as to the effect of
that Addendum on the terms of the main contract.
(2)
Whether the court a
quo
erred in finding that the conditions precedent had been waived
As
already stated, the effect of the Addendum to the contract was that
certain works by their nature and scope could not be completed by 23
October 2017 when the conditions precedent satisfaction period was
due to lapse. By signing this Addendum, the appellant must have
waived or at least extended that period beyond 23 October 2017. The
decision of the court a
quo
cannot be faulted.
(3)
Whether Fictional Fulfilment occurred
Fictional
fulfilment is a doctrine that may be invoked under circumstances
where a party to a contract deliberately frustrates the fulfilment of
a condition stipulated in the contract.
In
casu,
the respondent submits that the appellant was guilty of such conduct
with regards the financing arrangements. It invited the court a
quo
to deem the conditions to have been fulfilled in line with the
doctrine of fictional fulfilment.
The
invitation was accepted and correctly so.
The
respondent's sole witness gave evidence to the effect that various
proposals for the financing of the project were brought to the table
but the respondent showed disinterest and declined to engage the
various would-be financiers, both local and foreign. The appellant's
witness, one Fambi, confessed that he had no knowledge of the
financing arrangements and how they had been handled. He told the
court a
quo
that such arrangements were the preserve of the appellant's Chief
Executive Officer.
The
Chief Executive Officer was not called to give evidence.
For
that reason, the evidence of the respondent's witness, one
Chivhayo, was virtually uncontroverted.
It
was on the basis of that witness's uncontested testimony that the
court a
quo
found that the appellant had frustrated the implementation of the
contract and invoked the doctrine of fictional fulfilment.
The
appellant, in other words, could not be allowed to benefit from its
wrong doing. See the dicta
in Standard Chartered Bank Zimbabwe Limited v Matsika, supra
at 389H.
The
case of Scott
& Anor v Poupard & Anor
1971 (2) SA 373 sets out the factors to be established in order to
invoke the doctrine of fictional fulfilment. The factors are:
Non-fulfilment
of the condition; the defendant's breach of his duty with an
intention to frustrate the fulfilment; and a causal link between the
non-fulfilment and the defendant's intentional frustration of the
fulfilment of the conditions.
The
court a
quo,
in line with case law and the uncontroverted evidence of Chivhayo,
found this an appropriate case in which the doctrine of fictional
fulfilment should be invoked.
Its
decision in this regard cannot be impugned.
(4)
Whether specific performance should have been granted
The
fourth issue is to do with the propriety of the decision of the court
a
quo
in ordering specific performance.
The
law on specific performance is well traversed.
In
the case of Grandwell
Holdings (Pvt) Ltd v Zimbabwe Mining Development Corporation & 3
Ors
SC 5/20, this Court remarked as follows:
“However,
the right to claim specific performance is predicated on the concept
that the party claiming it must first show that he or she has
performed all his or her obligations under the contract or is ready,
willing and able to perform his side of the bargain. Even then, the
court has a discretion, which should be exercised judicially, to
grant or refuse a decree of specific performance. It follows
therefore that the court's discretion should not be exercised
arbitrarily or capriciously. See Minister
of Public Construction and National Housing v Zescon (Pvt) Ltd
1989 (2) ZLR 311 (S), where at 318G, this Court stated:
'The
law is clear. This is a remedy to which a party is entitled to as of
right. It cannot be withheld arbitrarily or capriciously.'”
In
dealing with the question of specific performance, the court a
quo
was alive to the principles governing the grant or refusal of that
relief. It correctly noted that each case must be determined
according to its own circumstances and that the court must exercise
its discretion judiciously, without appearing to be making a contract
for the parties.
In
casu,
it noted that the appellant had not placed any evidence before it
showing the measures it took in its attempt to achieve financial
closure. Its sole witness, Mr Fambi, was unable to shed any light on
this crucial issue.
Resultantly,
the court a
quo
correctly concluded that there was nothing to show that specific
performance was unachievable.
On
the contrary, Mr Chivhayo, respondent's sole witness, had shown
that the respondent could secure funding for the project, the
procurement of funding being central to the implementation of the
project.
The
court a
quo
dismissed the appellant's assertions that the project is no longer
viable. It held that any issues pertaining to the viability of the
project and the effect of the changes in the currency regime (as
alleged by the appellant) must be left to the parties to take care of
in terms of clause 5(i) of the contract.
In
any event, clause 6 of the contract allows the parties to amend the
contract should they so wish.
The
court a
quo
made reference to an “Amended and Restated Contract” which would
have seen the project being implemented in phases. The respondent had
funding for the initial phase of 10 MW. This contract was never
signed but its existence shows that funding could be obtained.
At
p47 of its cyclostyled judgment, the court a
quo
makes the following finding of fact:
“The
point is that the question of the unavailability of funding is
clearly not an excuse going by the evidence that was placed before
the court.”
That
finding of fact cannot be impugned. See Hama
v National Railways
1996
(1) ZLR 66.
Mr
Tivadar,
for the appellant, submitted that an order for specific performance
would bring intolerable hardships on the appellant as the appellant
has no funds to implement the project.
We
note, however, that Mr Fambi, appellant's sole witness, did not say
so in his evidence before the court a
quo.
Secondly, it is the duty of the respondent to source funding.
If
there is any hardship to be borne at this stage, it has to be borne
by the respondent and not the appellant.
The
respondent has indicated that it is able to source funding for the
project.
That
being the case, there was no reason for the court a
quo
to deny the respondent the remedy of specific performance.
5.
Whether the judgment of the court a
quo
was
based on the pleaded case
The
appellant's contention is that in its evidence, the respondent
based its claim on matters canvassed in the replication to the
appellant's plea instead of its own declaration. In order to
competently do so, the respondent should have amended its declaration
to include those matters hitherto not so covered by its declaration.
For that reason, argued the appellant, the court a
quo's
judgment
was not based on the pleaded case and ought to be vacated.
The
matters allegedly not covered by the respondent's declaration
include the China-Exim Bank financing issue, the CBZ and ATC funding
and the filing of malicious and fictitious charges of corruption
against the respondent's CEO, Mr Chivhayo.
The
court a
quo
was
of the view that the matters referred to by the appellant were
matters of evidence that should not be pleaded in the pleadings but
set out in the evidence. In any event, the issues referred to are
covered in the papers and were presented in the court a
quo
for
determination.
The
court a
quo
was
duty bound to determine all the issues brought before it. Indeed,
this Court in Shah
v Kingdom Merchant Bank
SC 4/2017 held that parties can extend their issues and once an issue
was before the court, it had the prerogative to consider it.
Accordingly,
this ground of appeal has no merit.
6.
Whether the counterclaim was properly dismissed
The
residue of the counter claim (after the abandonment of that part of
it imputing misrepresentation to the respondent) relates to a refund
due to the appellant in the sum of USD3,000,000.00. The amount had
been advanced to the respondent to carry out pre-commencement works.
Through
the testimony of Mr Chivhayo, the respondent resisted this claim on
the basis that the pre-commencement works to that value, if not much
more, was in fact carried out. For that reason, the respondent did
not owe the appellant any money.
Mr
Chivhayo relied primarily on the report of the joint visit to the
project site which showed that substantial progress had been achieved
on the pre-commencement work.
On
the other hand, Mr Fambi, the appellant's sole witness, was unable
to substantiate the counter claim because he did not have the
material to do so as such matters were the preserve of the
appellant's CEO.
The
CEO was not called to testify.
In
the circumstances the appellant failed to prove its counterclaim. The
court a
quo's
decision
to dismiss the counter claim cannot be faulted.
DISPOSITION
Despite
Mr Tivada's
spirited
efforts, the appellant's case is weak in three cardinal respects.
Firstly, Mr Chivhayo gave detailed factual evidence in support of the
respondent's case. On the other hand, Mr Fambi, who gave evidence
on behalf of the appellant, was literally at sea as he admitted that
he had no useful information regarding the issues before the court.
He referred all material issues to the respondent's CEO who was,
surprisingly, not called to give evidence. In essence therefore, Mr
Chivhayo's evidence was not controverted.
Secondly,
the court a
quo
made
a finding of credibility in favour of Mr Chivhayo. To all intents and
purposes therefore the court a
quo
accepted
the veracity of the evidence as given by Mr Chivhayo and rejected any
evidence to the contrary.
It
is trite that an appeal court will not lightly interfere with the
findings of credibility of a trial court.
Thirdly,
following from the above, the court a
quo
made
findings of fact in favour of the respondent. There is no basis to
interfere with those findings.
We
are satisfied that the court a
quo
properly held that the contract between the parties was valid and
extant and that same was properly amended by the Addendum to it which
extended the period within which the conditions precedent should be
fulfilled. It correctly found that its purported termination by the
appellant was of no legal force or effect as such termination did not
meet the requirements of the termination clause of the contract.
The
court a
quo
exercised its discretion judiciously in ordering specific performance
of the contract, having found that the respondent was willing and
able to source funding for the project.
In
any event, no meaningful evidence was presented by the witness led by
the appellant.
The
witness was unable to lead satisfactory evidence with regards the
appellant's counter claim in the sum of US$3 million. The court
a
quo
correctly found that the counter claim had not been proved and
proceeded to dismiss it.
In
the circumstances the appeal stands to fail. Costs shall follow the
cause.
Accordingly,
it is ordered that:
(1)
The appeal be and is hereby dismissed.
(2)
The appellant shall pay the costs of suit.
MAKONI
JA:
I agree
MUSAKWA
JA:
I agree
Muvingi
Mugadza,
appellant's
legal practitioners
Manase
& Manase Legal Practitioners, respondent's legal practitioners