Law Portal
Zimbabwe

Welcome To Law Portal

Welcome, Guest!
[Help?]

Approach re: Staggered Performance Contracts or Execution in Stages and Progress Payment Transactions

SC127-21 : MIDLANDS STATE UNIVERSITY vs GALAXY ENGINEERING DESIGN CONSULTANTS (PRIVATE) LIMITED
Ruled By: GWAUNZA DCJ, BHUNU JA and MATHONSI JA

This is an appeal against the judgment of the High Court (the court a quo) rendered in favour of the respondent on 24 July 2019 following a full trial. The judgment directed the appellant to pay to the respondent interest on the sum of $84,827=17 at the rate of 19.5% ...
More

SC143-21 : HAPPISON MUCHECHETERE vs ZIMBABWE BROADCASTING CORPORATION (PVT) LTD and RETIRED JUSTICE JAMES DEVITTE N.O. and GIBSON MUNYORO
Ruled By: GWAUNZA DCJ, UCHENA JA and MAKONI JA

In Van Der Post v Twyfelhoek Diamond Prospecting Syndicate (1903) 20 SC 213..., the following was held:“Where several or a series of contracts between the same parties are concluded to effect a single purpose, they should be treated as one contractual document, and, where there is doubt as to the ...
More

SC127-23 : ZIMBABWE POWER COMPANY vs INTRATREK ZIMBABWE
Ruled By: MAKONI JA, CHIWESHE JA and MUSAKWA JA

This is an appeal against the whole judgement of the High Court (the court a quo) sitting at Harare, dated 11 January 2023, wherein it declared that the procurement contract entered into between the appellant and the respondent was valid and binding between them. The court a quo proceeded, consequently, ...
More

SC127-23 : ZIMBABWE POWER COMPANY vs INTRATREK ZIMBABWE
Ruled By: MAKONI JA, CHIWESHE JA and MUSAKWA JA

“GROUNDS OF APPEAL1. The court a quo erred in law in that it failed to consider the respondent's case as pleaded in its declaration and proceeded, instead, to determine the matter on the basis of issues not pleaded in the declaration.2. The court a quo erred in law by finding, ...
More

SC127-23 : ZIMBABWE POWER COMPANY vs INTRATREK ZIMBABWE
Ruled By: MAKONI JA, CHIWESHE JA and MUSAKWA JA

ANALYSISAPPLYING THE LAW TO THE FACTS(2) Whether the court a quo erred in finding that the conditions precedent had been waivedAs already stated, the effect of the Addendum to the contract was that certain works, by their nature and scope, could not be completed by 23 October 2017 when the ...
More

Back Main menu

Categories

Back to top