CHATUKUTA J: This is an application
in terms of r 63 of the Rules of the
High Court, 1971 for the rescission of a judgment granted in default on 24 June
2009 in case no HC 1247/07. In addition,
the applicant sought for an order that the proceedings of the Pre-trial Conference
held on 18 November 2008 and the result thereof be declared null and void and
that a date for another Pre-trial Conference be allocated.
The background to the matter is that
sometime in May 2003, the parties entered into a contract in terms of which the
applicant agreed to construct a house for the respondent on stand No. 6224
Tynwald, Bloomingdate, Harare. The applicant did not complete the
construction of the house resulting in the respondent issuing summons for
specific performance failing which the applicant would be required to pay damages
being the market cost of completing the construction. The applicant defended the matter. After closure of pleadings, the matter was
referred for a Pre-trial Conference.
The default judgment emanated from
the directives of the court during a Pre-trial Conference which was held on 28 November
2008. Both the parties attended the Pre-trial
Conference with their legal practitioners.
However, there are divergent contentions as to the directives of the
court. The applicant contended that the
court directed that the respondent was to file a notice to amend her claim by
18 November 2008 and the applicant his plea by 21 November 2008. Thereafter the matter would proceed to
trial. His legal practitioner also heard
that the matter was referred to trial. Both the applicant and his legal
practitioner did not hear the judge postponing the Pre-trial Conference to 18
November 2008. The applicant did not therefore
attend the Pre-trial Conference on 18 November 2008. His plea was struck off and the matter was
referred to the unopposed roll. Default
judgment was then issued on 24 June 2009.
He became aware of the default judgment on 15 July 2009. He proceeded to file the present application
on 21 July 2009.
The respondent contended that the
court directed that the Pre-trial Conference be postponed to 18 November
2008. The respondent was to file her
notice of amendment by 9 November 2008 and the applicant was to plead before 18
November 2008. She attended the Pre-trial
Conference with her legal practitioner on 18 November 2008. The rest of the facts are common cause as to
how she obtained the default judgment.
A rescission of judgment under r 63 can only be granted where an
applicant shows “good and sufficient cause” entitling him to rescission of
judgment. The words 'good and sufficient
cause' have been construed to mean that the applicant must:
(a) give a reasonable and acceptable
explanation for his/her default;
(b) prove
that the application for rescission is bona fide and not made with the
intention of merely delaying plaintiff's claim; and
(c) show that he/she has a bona fide defence to plaintiff's claim.
(see Songore v Olivine
Industries (Pvt) Ltd 1988 (2) ZLR 210,; Bishi v Secretary for
Education 1989(2) ZLR 240 (HC); Ndebele v Ncube 1992(1) ZLR
288(S); Dewera Farm (Pvt) Ld & Ors v
Zimbabwe Banking Co-operation 1997 (2) ZLR 47 (H) Zimbabwe Banking Corporation Ltd
v Masendeke 1995 (2) ZLR 400 (S) and Apostolic Faith Mission in Zimbabwe & others v Titus I Murufu SC 28/03)
In Songore v Olivine Industries
(Pvt) Ltd 1988 (2) ZLR 210 and at 211E-F McNally JA held that:
“While the courts
are inclined to frown on plaintiffs who "snatch at their judgments"
the impression must not be gained that the Rules may be flouted with impunity
and that as long as you are only a day or two late rescission will be granted
on request. A reason for the delay must be given and it must be an acceptable
reason. A defendant who admits that he was negligent in his tardiness may
nonetheless be found to merit rescission if he shows bona fides. But
one who puts forward a "reason" which is an insult to the
intelligence of the court may have more difficulty in satisfying the court of
his good faith. (own
emphasis) (See also V Saitis & Co (Pvt) Ltd v Fenlake (Pvt) Ltd 2002 (1) ZLR 378 at 381A).
It appears to me that the reason
advanced by the applicant is unreasonable under the circumstances and shows
lack of bona fide. The court endorsed
the results of the PRE-TRIAL CONFERENCE of 28 October as follows:
“PP 18/11/08 at 9
am
Pl to file an
amendment to the claim by 9/11/08
Defendant to plead
b4 PTC.”
It is difficult to understand how
the applicant and the respondent and their respective legal practitioners would
have heard differently the directive given by the court in their presence. In fact the averments by the applicant and
his legal practitioner in their respective affidavits in support of the
application insult the intelligence of the court. Both were adamant that the court had in fact
indicated that the matter was to proceed to trial upon the filing of the notice
of amendment by the respondent and the plea by the defendant. Philip Nyakutombwa, applicant's legal
practitioner who was in attendance on 28 October 2008 stated as follows in his
supporting affidavit
“4.5 It was beyond doubt that the option of an
out of court settlement was now clearly inconceivable at this stage to the
extent that I recall the Honourable Judge stating she would “refer this matter
for trial”.
4.6 At this point, I will clearly state that
this was the directive I heard and soon thereafter the Honourable Judge dealt
with the need before trial date for Respondent (Plaintiff) to file their
Amendment to summons as per their request and for Applicant (defendant) to file
a plea in response.”
The applicant stated as follows in
paragraph 17 of the answering affidavit:
“This is denied. Gross negligence is denied as applicant and
his Legal Practitioner have stated that the words heard from the Honourable
judge were to the effect that “failing to settle, the matter shall be
referred to trial” which was the most prominent feature the Judges (sic) ruling, what was endorsed on the
record differed from what was heard and understood (human error).”
The
import of the averments is that the judge who presided over the PRE-TRIAL
CONFERENCE was deceitful. She said one
thing and endorsed a totally different thing on the result sheet. Had the applicant been a self actor, he would
have been forgiven for the averments.
But the applicant made those averments with the assistance of an officer
of the court. The officer of the court
himself also implied that the court was deceitful. I find the conduct of the legal practitioner
deplorable under the circumstances. He
did not only insult the court's intelligence by proffering the unbelievable explanation
but he also insulted the court that presided over the Pre-trial Conference by
imputing a high degree of dishonesty thereby attacking her integrity.
I further find it to be unreasonable
that the applicant's legal practitioner would believe that the matter had been
referred to trial before the Pre-trial Conference was concluded with the
identification of issues for referral to trial.
Mr Nyangoni conceded that when the court directed that the respondent
amend her summons, the pleadings had been reopened and would have been closed
with the applicant filing his plea. He
further conceded that the matter would only have been referred to court after
the parties had agreed to the issues that would be referred for adjudication at
trial. The purpose of a Pre-trial
Conference is to afford the parties an opportunity to clearly define issues to
be referred to trial so as to expedite or curtail proceedings (see r 182 of the High Court Rules). The parties, with the assistance of the court,
must be satisfied that the case which the plaintiff seeks to make has been
fully and fairly disclosed and the defence raised thereto has properly been
pleaded to the extent that is required.
The summons in their original form was not sounding in money. It did not disclose the cost of the completing
the construction of the respondent's house.
The applicant would not have properly defended the claim in the absence
of the cost. The parties were agreed
that this is the reason why the court had directed that the parties amend their
pleadings. It is only then, after the
amendments had been filed that the parties would have been able to crystallise
the issues for trial. That is trite. It is therefore surprising that Mr
Nyakutombwa would have “heard” that the matter was referred to trial before
pleadings had been closed and without the parties agreeing on the issues to be
determined at trial.
The
conduct of Mr Nyakutombwa amounts, in my view to gross negligence. The negligence is further compounded by the
attempt to blame the court for the applicant's default. In Kodzwa v Secretary for Health and Anor
(supra) at 317E, SANDURA J cited with approval, STEYN CJ in Saloojee
& Anor v Minister of Community Development 1965 (2) SA 135 (A) at 141
C-E that:
“I should point out, however, that it has not at any
time been held that condonation will not in any circumstances be withheld if
the blame lies with the attorney. There
is a limit beyond which a litigant cannot escape the results of his attorney's
lack of diligence or the insufficiency of the explanation tendered. To hold otherwise might have a disastrous
effect upon the observance of the rules of this court. Consideration ad misericordiam should
not be allowed to become an invitation for laxity. In fact, this court has been lately burdened
with an undue and increasing number of applications for condonation in which
the failure to comply with the rules of this court was due to negligence on the
part of the attorney. The attorney,
after all, is the representative whom the litigant has chosen for himself, and
there is little reason why, in regard to condonation for failure to comply with
a rule of court, the litigant should be absolved from the normal consequences
of such a relationship.”
(See also Kombayi v Berkhout 1988 (1) ZLR 53 (SC), Ndebele
v Ncube (supra) and Masama v
Borehole Drilling (Pvt) Ltd 1993 (1) ZLR 116 (SC)).
I share the same sentiments and am
of the view that the applicant cannot, under the circumstances, escape the
results of his legal practitioner's lack of diligence and the unreasonableness
of the explanation tendered for the default.
I
turn now to the bona fides of the applicant's defence to the respondent's
claim. The applicant contended in his
plea that the contract between the parties was on a fix and supply basis. The respondent was required to pay the amount
for the construction of the property in “bulk”.
It is assumed that the bulk payment was payment of 75% of the cost of
construction as indicated in the letter dated 16 May 2003, which letter constitutes
the agreement between the parties. The applicant
appears to have been satisfied with manner in which the respondent had been making
her payments as reflected in the letter dated 27 October 2003. In that letter he expressed satisfaction at
the progress that had been made with the financial support of the
respondent. He certainly would not have expressed
satisfaction at the progress he had made had the respondent not been making
timeous payments.
In fact the respondent appears to
have been up to date with her payments because the applicant refunded her a sum
of $3 000 000. The applicant conceded in
his answering affidavit that the final cost of construction was $21 200 000. The respondent had paid a total of $24 200
000. It is therefore understandable that
the respondent would have believed that she had discharged her obligations when
she received the refund of $3 000 000 being the difference between the cost of
construction of $21 200 000 and the total amount of $24 200 000 that she had
paid to the applicant.
The applicant explained
that the refund was made because the $3 000 000 was not adequate to complete
the roofing of the house. He however
could not explain why it was necessary to make a refund instead of retaining the
amount and requesting the respondent to pay the balance. It appears this would have been the best
course of action to take given the alleged changes in the cost of the roofing
given the then hyperinflationary environment.
The only inescapable conclusion for the refund appears to be that the
respondent had in fact discharged her obligations.
If I am correct in
concluding that the respondent had discharged her obligations under the
contract, it follows that the applicant does not have a bona fide defence to the respondent's claim. I am bolstered in my
conclusion by the letter dated 17 July 2007 and written by the applicant to the
respondent during the negotiations conducted in order to reach an amicable
settlement of the respondent's claim. In the letter, the applicant's legal
practitioners wrote:
“(a) Our client acknowledges the undue difficulties
and hardships this case may bring upon both parties and is therefore willing to accept fault on his part.
(b) After
accepting fault, there is need to map a strategy way (sic) forward to bring the matter to a finality (sic).” (own emphasis)
It appears the reason why the
applicant wanted a settlement was because of the hardships that would be
occasioned in completing the construction without any further financial
assistance from the respondent given the then hyperinflationary
environment. He was however accepting
blame for the delays in completing the construction. I believe the acceptance of fault was in view
of the fact that the respondent had paid the full cost for the construction and
had in fact received a refund.
The
applicant also contended that he had a bona
fide defence to the claim on the basis that the amendment of summons by the
respondent was a nullity. The nullity is
said to be premised on the fact that the applicant did not consent to the
amendment and in the absence of the consent, the applicant did not file an
application for an order to amend the summons.
The applicant relies on the decisions in ZFC Ltd v Taylor
1999 (1) ZLR 308 and UDC Ltd v Shamva
Flora (Pvt) Ltd 2000 (2) ZLR 210.
The respondent contended that the
applicant is estopped from denying having consented to the amendment because it
pleaded to the notice amendment.
The
decision in ZFC Ltd v Taylor is distinguishable from the
present matter. In that case, the
plaintiff was applying for default judgment.
He proceeded to file the notice of amendment after the defendant had
been barred. The notice of amendment
was not served on the defendant. That is
the reason why GILLESPIE J referred to the notice of amendment as unilateral
and therefore unprocedural. The decision
in UDC Ltd v Shamva Flora (Pvt) Ltd, is
also distinguishable. The defendant,
upon service of the notice of amendment, had requested for further documents to
enable it to make a decision on how to respond to the pleading. The plaintiff assumed that the request for
the documents was a refusal to give its consent to the amendment hence the
application before that court.
In the present case, as rightly
submitted by the respondent, the applicant did not raise any issues with the
notice of amendment. He proceeded to
plead to the plaintiff's amended summons and declaration. It appears to me that the applicant cannot
now turn around and deny having consented to the amendment. What was he pleading to if he had not
consented to the notice of amendment? It
is my view that the applicant is precluded by its own conduct from denying that
it had consented to the amendment. I
therefore do not believe that this constitutes a bona fide defence to the plaintiff's claim.
In
the result, the application is dismissed with costs.
Hute & Partners, applicant's legal
practitioners
Messrs Chihambakwe,
Mutizwa & Partners, respondent's legal
practitioners