Law Portal
Zimbabwe

Welcome To Law Portal

Welcome, Guest!
[Help?]

HH146-09 - ELLIOT MUTANGADURA vs T.S. TIMBER BUILDING SUPPLIES

  • View Judgment By Categories
  • View Full Judgment


Law of Contract-viz specific performance re specific performance ex contractu.
Law of Contract-viz specific performance re specific performance ex contractu iro damages in lieu of specific performance.
Law of Contract-viz purchase and sale re conditional sale.
Law of Contract-viz specific performance re specific performance ex contractu iro impossibility of performance.
Law of Contract-viz purchase and sale re quotations.
Procedural Law-viz rules of evidence re documentary evidence.
Law of Contract-viz purchase and sale re orders.
Law of Contract-viz specific performance re specific performance ex contractu iro debtors mora.
Law of Contract-viz specific performance re specific performance ex contractu iro letter of demand.
Law of Contract-viz specific performance re specific performance ex contractu iro interpellatio.
Procedural Law-viz rules of evidence re evidence on behalf of a corporate entity iro institutional memory.
Procedural Law-viz rules of evidence re unchallenged evidence.
Procedural Law-viz rules of evidence re undisputed averments.
Procedural Law-viz rules of evidence re uncontroverted submissions.
Damages-viz contractual damage.
Law of Contract-viz Deed of Settlement re compromise agreement iro settlement offers.
Law of Contract-viz compromise agreement re settlement offers iro the obligation to mitigate damages.
Law of Contract-viz compromise agreement re settlement refund iro the obligation to mitigate losses.

Contract of Sale re: Conditional, Unconditional, Suspensive Sales and the Officious Bystander Test

The plaintiff in this case claims the delivery of 1,200 bags of PC15 cement or, in the alternative, damages for breach of contract equivalent to the current market value of the cement, being US$11,400=, and costs of suit.

The defendant resists the claim on several grounds, to wit, that delivery of the cement was conditional on the defendant receiving the same from its supplier, that it was unable to deliver due to supervening impossibility and that it is no longer able to deliver the cement and has offered a refund to the plaintiff in the sum of ZW$336 million.

Evidence for the Plaintiff

Elliot Mutangadura, the plaintiff, testified as follows. In July 2007 he approached the defendant to purchase various building materials. The defendant then submitted a quotation on the 18th of July 2007 listing those materials that it was able to supply - including the cement in question [Exhibit 1]. At that time, PC15 cement was available on the market and also in the defendant's warehouse (though he was not aware of the quantity thereof). This was confirmed by the defendant's Branch Manager (Mavengere) as well as its Sales Manager (Jongwe) without any condition as to having to await delivery from the defendant's suppliers.

The plaintiff then paid the full purchase price for all the materials in six instalments amounting to $3.51 billion, as was confirmed in a letter from Jongwe dated the 30th of August 2007 [Exhibit 2]. In that letter, Jongwe also confirmed that “we had promised delivery early August.” The defendant thereafter delivered all the purchased items - save for the cement.

On the 19th of September 2007, Mavengere wrote a letter stating that the defendant was “unable to supply PC15 cement as per agreement” and offered to supply masonry or other building materials equivalent to the amount paid [Exhibit 3]. The plaintiff rejected the offer as the PC15 cement was specifically required for the building work in question.

On the 21st of September 2007 the plaintiff's lawyers wrote a letter of demand to the defendant [Exhibit 5]. In response, on the 1st of October, the defendant's lawyers offered a refund of the original purchase price of $336 million [Exhibit 4]. The plaintiff rejected this offer through a letter from his lawyers on the 9th of October [Exhibit 6] because the money tendered was insufficient to pay for 1,200 bags of cement at that time.

Subsequently, from October 2007 to June 2008, the plaintiff sourced 1,200 bags of cement, on loan, from his uncle's hardware business. The return of the cement borrowed is now overdue. The requisite PC15 cement is currently available on the market at US$9.50 to US$10 per bag.

Evidence for the Defendant

Thomas Jongwe was the Sales Manager of the defendant's Harare branch at the relevant time. His evidence was as follows.

Before giving the original quotation to the plaintiff, on the 18th of July 2007, he made enquiries with the defendant's suppliers and told the plaintiff that PC15 cement was available for supply to the plaintiff. However, before the first payment was received, on the 20th of July, he verbally informed the plaintiff that the cement was not immediately available and would be sourced from Unichem, a supplier in Bulawayo. He then placed an order for 1,200 bags with Unichem on the 31st of July [Exhibit 7]. Unichem did not have any clinker, a critical raw material in cement, and he verbally informed the plaintiff of that fact.

The plaintiff made six payments in all, from the 20th of July to the 16th of August 2007, as shown on the receipts therefor [Exhibit 8]. There was no indication on the receipts as to the specific items paid for. The payments were made towards the total quotation amount, with appropriation in respect of each item being made at the time of invoicing. No invoice was raised for the cement as it was not in stock to deliver. In accordance with the defendant's internal accounting system, an invoice is raised after payment is received and is given to the customer at the delivery point as a delivery note.

Under cross-examination, Thomas Jongwe accepted that by the date of the last payment, on the 16th of August 2007, the plaintiff had discharged his obligation under the contract. He also conceded that he made enquiries with the defendant's suppliers and made certain that the cement was available before issuing the quotation to the plaintiff. He further confirmed that PC15 cement is presently available on the market.

Issues for Determination

The agreed issues for determination herein are as follows:

(a) What terms and conditions were agreed to or can be implied from the contract concluded between the parties?

(b) Whether the defendant is liable for specific performance in terms of the contract.

(c) What amount of compensation, if any, is the defendant liable to pay to the plaintiff?

Terms and Conditions of Contract

The evidence before the Court shows that after the plaintiff initially approached the defendant, its Sales Manager, Thomas Jongwe, made enquiries with the defendant's suppliers and received positive confirmation as to the availability of PC15 cement. Jongwe then made out the quotation [Exhibit 1] and upon handing it to the plaintiff on the 18th of July 2007 gave a firm assurance that the cement would be delivered in early August.

At that time, the defendant did not, as it contends, stipulate any condition as to the fulfilment of the contract being subject to delivery from its suppliers. Thereafter, the plaintiff paid the full amount of the quotation in six instalments, beginning on the 20th of July and finishing on the 16th of August 2007. The defendant only raised the non-availability of PC15 cement from its suppliers over one month after full payment had been made and received.

All the payments made by the plaintiff were towards the total quotation and not towards any specific materials thereon. The defendant's invoicing process involved the appropriation of the amounts paid to particular items as and when delivery was effected and the invoices served as delivery notes. However, this was quite clearly a process that was internal to the defendant's accounting system and totally irrelevant to the conclusion of the contract between the parties.

It is quite clear from the foregoing that the contract in casu was concluded unconditionally on the 20th of July 2007 when the defendant accepted the plaintiff's first instalment as part payment towards the entire quotation - including the PC15 cement. The terms and conditions of the contract were that the defendant would deliver the cement in early August against payment by the plaintiff of the full amount of the quotation in instalments. 

In effect, the parties concluded an unconditional and binding contract for the supply of 1,200 bags of cement to the plaintiff in early August 2007.

Negligence or Dolus re: Liability iro Voluntary Assumption of Risk

The general rule in our law is that, if a supervening physical or legal factor renders the performance of a contract impossible, through no fault of the debtor, the obligations of the parties under the contract are thereby extinguished and cannot be enforced. See Beitbridge-Bulawayo Railways (Pvt) Ltd v Commercial Union Insurance Company of Zimbabwe Ltd SC91-07.

However, this general rule does not override the terms of the implications of the contract. The court must have regard to, inter alia, the nature and circumstances of the contract and the nature of the impossibility that is relied upon. If, for instance, it is ascertained that the parties contemplated the situation that gives rise to the impossibility and accepted the risk of the supervening event, the general rule does not apply and the parties are bound to perform their contract. See Beitbridge-Bulawayo Railways (Pvt) Ltd v Commercial Union Insurance Company of Zimbabwe Ltd SC91-07; Bekker N.O. v Duvenhage 1977 (3) SA 884 (ECD)…,.; Bischofberger v Van Eyk 1981 (2) SA 607 (WLD)…,.; CHRISTIE: The Law of Contract in South Africa (3rd ed.)…,.

Specific Performance re: Approach, Impossibility of Performance and the Exceptio Non Adimpleti Contractus

The plaintiff in this case claims the delivery of 1,200 bags of PC15 cement or, in the alternative, damages for breach of contract equivalent to the current market value of the cement, being US$11,400=, and costs of suit.

The defendant resists the claim on several grounds, to wit, that delivery of the cement was conditional on the defendant receiving the same from its supplier, that it was unable to deliver due to supervening impossibility and that it is no longer able to deliver the cement and has offered a refund to the plaintiff in the sum of ZW$336 million.

Evidence for the Plaintiff

Elliot Mutangadura, the plaintiff, testified as follows. In July 2007 he approached the defendant to purchase various building materials. The defendant then submitted a quotation on the 18th of July 2007 listing those materials that it was able to supply - including the cement in question [Exhibit 1]. At that time, PC15 cement was available on the market and also in the defendant's warehouse (though he was not aware of the quantity thereof). This was confirmed by the defendant's Branch Manager (Mavengere) as well as its Sales Manager (Jongwe) without any condition as to having to await delivery from the defendant's suppliers.

The plaintiff then paid the full purchase price for all the materials in six instalments amounting to $3.51 billion, as was confirmed in a letter from Jongwe dated the 30th of August 2007 [Exhibit 2]. In that letter, Jongwe also confirmed that “we had promised delivery early August.” The defendant thereafter delivered all the purchased items - save for the cement.

On the 19th of September 2007, Mavengere wrote a letter stating that the defendant was “unable to supply PC15 cement as per agreement” and offered to supply masonry or other building materials equivalent to the amount paid [Exhibit 3]. The plaintiff rejected the offer as the PC15 cement was specifically required for the building work in question.

On the 21st of September 2007 the plaintiff's lawyers wrote a letter of demand to the defendant [Exhibit 5]. In response, on the 1st of October, the defendant's lawyers offered a refund of the original purchase price of $336 million [Exhibit 4]. The plaintiff rejected this offer through a letter from his lawyers on the 9th of October [Exhibit 6] because the money tendered was insufficient to pay for 1,200 bags of cement at that time.

Subsequently, from October 2007 to June 2008, the plaintiff sourced 1,200 bags of cement, on loan, from his uncle's hardware business. The return of the cement borrowed is now overdue. The requisite PC15 cement is currently available on the market at US$9.50 to US$10 per bag.

Evidence for the Defendant

Thomas Jongwe was the Sales Manager of the defendant's Harare branch at the relevant time. His evidence was as follows.

Before giving the original quotation to the plaintiff, on the 18th of July 2007, he made enquiries with the defendant's suppliers and told the plaintiff that PC15 cement was available for supply to the plaintiff. However, before the first payment was received, on the 20th of July, he verbally informed the plaintiff that the cement was not immediately available and would be sourced from Unichem, a supplier in Bulawayo. He then placed an order for 1,200 bags with Unichem on the 31st of July [Exhibit 7]. Unichem did not have any clinker, a critical raw material in cement, and he verbally informed the plaintiff of that fact.

The plaintiff made six payments in all, from the 20th of July to the 16th of August 2007, as shown on the receipts therefor [Exhibit 8]. There was no indication on the receipts as to the specific items paid for. The payments were made towards the total quotation amount, with appropriation in respect of each item being made at the time of invoicing. No invoice was raised for the cement as it was not in stock to deliver. In accordance with the defendant's internal accounting system, an invoice is raised after payment is received and is given to the customer at the delivery point as a delivery note.

Under cross-examination, Thomas Jongwe accepted that by the date of the last payment, on the 16th of August 2007, the plaintiff had discharged his obligation under the contract. He also conceded that he made enquiries with the defendant's suppliers and made certain that the cement was available before issuing the quotation to the plaintiff. He further confirmed that PC15 cement is presently available on the market.

Issues for Determination

The agreed issues for determination herein are as follows:

(a) What terms and conditions were agreed to or can be implied from the contract concluded between the parties?

(b) Whether the defendant is liable for specific performance in terms of the contract.

(c) What amount of compensation, if any, is the defendant liable to pay to the plaintiff?

Terms and Conditions of Contract

The evidence before the Court shows that after the plaintiff initially approached the defendant, its Sales Manager, Thomas Jongwe, made enquiries with the defendant's suppliers and received positive confirmation as to the availability of PC15 cement. Jongwe then made out the quotation [Exhibit 1] and upon handing it to the plaintiff on the 18th of July 2007 gave a firm assurance that the cement would be delivered in early August.

At that time, the defendant did not, as it contends, stipulate any condition as to the fulfilment of the contract being subject to delivery from its suppliers. Thereafter, the plaintiff paid the full amount of the quotation in six instalments, beginning on the 20th of July and finishing on the 16th of August 2007. The defendant only raised the non-availability of PC15 cement from its suppliers over one month after full payment had been made and received.

All the payments made by the plaintiff were towards the total quotation and not towards any specific materials thereon. The defendant's invoicing process involved the appropriation of the amounts paid to particular items as and when delivery was effected and the invoices served as delivery notes. However, this was quite clearly a process that was internal to the defendant's accounting system and totally irrelevant to the conclusion of the contract between the parties.

It is quite clear from the foregoing that the contract in casu was concluded unconditionally on the 20th of July 2007 when the defendant accepted the plaintiff's first instalment as part payment towards the entire quotation - including the PC15 cement. The terms and conditions of the contract were that the defendant would deliver the cement in early August against payment by the plaintiff of the full amount of the quotation in instalments. In effect, the parties concluded an unconditional and binding contract for the supply of 1,200 bags of cement to the plaintiff in early August 2007.

Specific Performance and Supervening Impossibility

The defendant avers that at the end of August 2007 it was unable to source PC15 cement from its suppliers because a requisite component (clinker) was not available at that time. It therefore contends that this market factor constituted a supervening event rendering impossible the performance of the contract for the supply of PC15 cement.

It is trite that a party to a binding agreement has the right to demand from the other party, as far as it is possible, performance of his undertaking in terms of the contract where he is in a position to do so. Such specific performance can only be avoided in compelling circumstances. In this respect, the onus lies on the party seeking to avoid the contract to establish the facts and circumstances justifying the court's exercise of its discretion to refuse specific performance. See International Trading (Pvt) Ltd v Nestle Zimbabwe (Pvt) Ltd 1993 (1) ZLR 21 (H)…,.

The general rule in our law is that, if a supervening physical or legal factor renders the performance of a contract impossible, through no fault of the debtor, the obligations of the parties under the contract are thereby extinguished and cannot be enforced. See Beitbridge-Bulawayo Railways (Pvt) Ltd v Commercial Union Insurance Company of Zimbabwe Ltd SC91-07.

However, this general rule does not override the terms of the implications of the contract. The court must have regard to, inter alia, the nature and circumstances of the contract and the nature of the impossibility that is relied upon. If, for instance, it is ascertained that the parties contemplated the situation that gives rise to the impossibility and accepted the risk of the supervening event, the general rule does not apply and the parties are bound to perform their contract. See Beitbridge-Bulawayo Railways (Pvt) Ltd v Commercial Union Insurance Company of Zimbabwe Ltd SC91-07; Bekker N.O. v Duvenhage 1977 (3) SA 884 (ECD)…,.; Bischofberger v Van Eyk 1981 (2) SA 607 (WLD)…,.; CHRISTIE: The Law of Contract in South Africa (3rd ed.)…,.

There is a further situation more pertinent to the facts in casu where the general rule does not override the obligation of the parties to perform their contract. This arises where a party is only temporarily disabled from fulfilling his contractual obligations, in contradistinction to the position where the contract becomes finally and completely impossible of performance. See Field N.O. & Another v Compuserve (Pvt) Ltd 1990 (2) ZLR 253 (HC)…, citing Beretta v Rhodesia Railways Ltd 1947 (2) SA 1075 (R)…., as follows:

The law is clear that when a contract becomes finally and completely impossible of performance by reason of an act of State it is discharged. Peters Flamman & Co v Kokstad Municipality 1919 AD 427. But this does not cover the situation in which one party is temporarily disabled from fulfilling his obligation.

It is nowhere suggested that the immediate effect of such temporary disability is to end the contract, and this is not surprising, for any such suggestion would involve consequences so extreme as to be unthinkable.”

On the evidence before the Court, there is nothing to indicate that the non-availability of clinker on the market was permanent and irreversible. According to Thomas Jongwe's testimony, this non-availability only occurred towards the end of August 2007 when the defendant's suppliers intimated their inability to supply PC15 cement. This would mean that the defendant was merely temporarily unable to source the 1,200 bags of cement and deliver the same to the plaintiff. Certainly, there was no evidence adduced to contradict the plaintiff's testimony that PC15 cement was available on the market from October 2007 onwards. In any event, the shortage of clinker on the market occurred one month after the promised date of delivery, and, therefore, it could not and should not have affected the defendant's undertaking to deliver the cement to the plaintiff in early August 2007.

It follows that the defendant's defence of supervening impossibility cannot be sustained, either at the time when delivery of the cement was to be effected as contemplated by the parties, i.e. in early August 2007, or at any time from October 2007 onwards, when cement was available on the market. It also follows that the defendant has failed to establish any basis for declining specific performance and must therefore be held bound to its undertaking to deliver PC15 cement to the plaintiff.

Quantum of Damages

Assuming that I am wrong in finding that the plaintiff is entitled to claim specific performance on the facts in casu, it is necessary to consider the measure of damages properly due to the plaintiff.

In this regard, the defendant submits that the plaintiff should have accepted the refund that was tendered by the defendant in October 2007. By refusing to accept that refund, so it is argued, the plaintiff has failed to mitigate his damages and must therefore bear the penalty of a commensurate reduction in the quantum of damages to be awarded.

In my view, these submissions are devoid of merit for several reasons.

It cannot be disputed that the plaintiff's entitlement to damages must entail him being placed in the position he would have been in but for the defendant's breach of contract. The plaintiff's unchallenged evidence was that in order to complete his building project he borrowed the requisite cement and presently remains obligated to replace the borrowed cement. More particularly, he rejected the defendant's offer to refund the purchase price originally paid specifically because the amount tendered would not have placed him in the position he was in at the time that the contract was concluded due to the hyper-inflationary economic environment that prevailed at that time. No evidence was adduced on behalf of the defendant to counter the plaintiff's testimony in the above respects.

I accordingly find that the plaintiff did endeavour to mitigate his loss and that his rejection of the refund offered by the defendant was perfectly justifiable at the material time. Moreover, it is common cause that the plaintiff duly performed his contractual obligations and that the defendant has remained in possession and beneficial use of the money paid by the plaintiff for the cement. It also not disputed that the current minimum price for cement is US$9.50 per bag.

In the final analysis, the law requires that the plaintiff be put in a position to purchase the cement that he requires at the current minimum market price in order to meet his obligation to replace the cement that he has borrowed. He is therefore entitled to the measure of damages that he claims in the alternative.

Disposition

Although the plaintiff's claim for damages was originally framed as an alternative in the event of the claim for specific performance being refused, I believe that it would be just and equitable, at this juncture, having regard to the facts of this case and the circumstances of both parties, to grant both an order for specific performance and damages as alternative remedies.

In the result, judgement is hereby entered in favour of the plaintiff as against the defendant for:

(i) The delivery of 1,200 bags of PC15 cement within 7 days of the granting of this order, or, alternatively, the payment of damages for breach of contract in the sum of US$11,400= being the current market value of 1,200 bags of PC15 cement; and

(ii) Costs of suit.

Quotations and Orders

The plaintiff in this case claims the delivery of 1,200 bags of PC15 cement or, in the alternative, damages for breach of contract equivalent to the current market value of the cement, being US$11,400=, and costs of suit.

The defendant resists the claim on several grounds, to wit, that delivery of the cement was conditional on the defendant receiving the same from its supplier, that it was unable to deliver due to supervening impossibility and that it is no longer able to deliver the cement and has offered a refund to the plaintiff in the sum of ZW$336 million.

Evidence for the Plaintiff

Elliot Mutangadura, the plaintiff, testified as follows. In July 2007 he approached the defendant to purchase various building materials. The defendant then submitted a quotation on the 18th of July 2007 listing those materials that it was able to supply - including the cement in question [Exhibit 1]. At that time, PC15 cement was available on the market and also in the defendant's warehouse (though he was not aware of the quantity thereof). This was confirmed by the defendant's Branch Manager (Mavengere) as well as its Sales Manager (Jongwe) without any condition as to having to await delivery from the defendant's suppliers.

The plaintiff then paid the full purchase price for all the materials in six instalments amounting to $3.51 billion, as was confirmed in a letter from Jongwe dated the 30th of August 2007 [Exhibit 2]. In that letter, Jongwe also confirmed that “we had promised delivery early August.” The defendant thereafter delivered all the purchased items - save for the cement.

On the 19th of September 2007, Mavengere wrote a letter stating that the defendant was “unable to supply PC15 cement as per agreement” and offered to supply masonry or other building materials equivalent to the amount paid [Exhibit 3]. The plaintiff rejected the offer as the PC15 cement was specifically required for the building work in question.

On the 21st of September 2007 the plaintiff's lawyers wrote a letter of demand to the defendant [Exhibit 5]. In response, on the 1st of October, the defendant's lawyers offered a refund of the original purchase price of $336 million [Exhibit 4]. The plaintiff rejected this offer through a letter from his lawyers on the 9th of October [Exhibit 6] because the money tendered was insufficient to pay for 1,200 bags of cement at that time.

Subsequently, from October 2007 to June 2008, the plaintiff sourced 1,200 bags of cement, on loan, from his uncle's hardware business. The return of the cement borrowed is now overdue. The requisite PC15 cement is currently available on the market at US$9.50 to US$10 per bag.

Evidence for the Defendant

Thomas Jongwe was the Sales Manager of the defendant's Harare branch at the relevant time. His evidence was as follows.

Before giving the original quotation to the plaintiff, on the 18th of July 2007, he made enquiries with the defendant's suppliers and told the plaintiff that PC15 cement was available for supply to the plaintiff. However, before the first payment was received, on the 20th of July, he verbally informed the plaintiff that the cement was not immediately available and would be sourced from Unichem, a supplier in Bulawayo. He then placed an order for 1,200 bags with Unichem on the 31st of July [Exhibit 7]. Unichem did not have any clinker, a critical raw material in cement, and he verbally informed the plaintiff of that fact.

The plaintiff made six payments in all, from the 20th of July to the 16th of August 2007, as shown on the receipts therefor [Exhibit 8]. There was no indication on the receipts as to the specific items paid for. The payments were made towards the total quotation amount, with appropriation in respect of each item being made at the time of invoicing. No invoice was raised for the cement as it was not in stock to deliver. In accordance with the defendant's internal accounting system, an invoice is raised after payment is received and is given to the customer at the delivery point as a delivery note.

Under cross-examination, Thomas Jongwe accepted that by the date of the last payment, on the 16th of August 2007, the plaintiff had discharged his obligation under the contract. He also conceded that he made enquiries with the defendant's suppliers and made certain that the cement was available before issuing the quotation to the plaintiff. He further confirmed that PC15 cement is presently available on the market.

Issues for Determination

The agreed issues for determination herein are as follows:

(a) What terms and conditions were agreed to or can be implied from the contract concluded between the parties?

(b) Whether the defendant is liable for specific performance in terms of the contract.

(c) What amount of compensation, if any, is the defendant liable to pay to the plaintiff?

Terms and Conditions of Contract

The evidence before the Court shows that after the plaintiff initially approached the defendant, its Sales Manager, Thomas Jongwe, made enquiries with the defendant's suppliers and received positive confirmation as to the availability of PC15 cement. Jongwe then made out the quotation [Exhibit 1] and upon handing it to the plaintiff on the 18th of July 2007 gave a firm assurance that the cement would be delivered in early August.

At that time, the defendant did not, as it contends, stipulate any condition as to the fulfilment of the contract being subject to delivery from its suppliers. Thereafter, the plaintiff paid the full amount of the quotation in six instalments, beginning on the 20th of July and finishing on the 16th of August 2007. The defendant only raised the non-availability of PC15 cement from its suppliers over one month after full payment had been made and received.

All the payments made by the plaintiff were towards the total quotation and not towards any specific materials thereon. The defendant's invoicing process involved the appropriation of the amounts paid to particular items as and when delivery was effected and the invoices served as delivery notes. However, this was quite clearly a process that was internal to the defendant's accounting system and totally irrelevant to the conclusion of the contract between the parties.

It is quite clear from the foregoing that the contract in casu was concluded unconditionally on the 20th of July 2007 when the defendant accepted the plaintiff's first instalment as part payment towards the entire quotation - including the PC15 cement. The terms and conditions of the contract were that the defendant would deliver the cement in early August against payment by the plaintiff of the full amount of the quotation in instalments. In effect, the parties concluded an unconditional and binding contract for the supply of 1,200 bags of cement to the plaintiff in early August 2007.

Specific Performance and Supervening Impossibility

The defendant avers that at the end of August 2007 it was unable to source PC15 cement from its suppliers because a requisite component (clinker) was not available at that time. It therefore contends that this market factor constituted a supervening event rendering impossible the performance of the contract for the supply of PC15 cement.

It is trite that a party to a binding agreement has the right to demand from the other party, as far as it is possible, performance of his undertaking in terms of the contract where he is in a position to do so. Such specific performance can only be avoided in compelling circumstances. In this respect, the onus lies on the party seeking to avoid the contract to establish the facts and circumstances justifying the court's exercise of its discretion to refuse specific performance. See International Trading (Pvt) Ltd v Nestle Zimbabwe (Pvt) Ltd 1993 (1) ZLR 21 (H)…,.

The general rule in our law is that, if a supervening physical or legal factor renders the performance of a contract impossible, through no fault of the debtor, the obligations of the parties under the contract are thereby extinguished and cannot be enforced. See Beitbridge-Bulawayo Railways (Pvt) Ltd v Commercial Union Insurance Company of Zimbabwe Ltd SC91-07.

However, this general rule does not override the terms of the implications of the contract. The court must have regard to, inter alia, the nature and circumstances of the contract and the nature of the impossibility that is relied upon. If, for instance, it is ascertained that the parties contemplated the situation that gives rise to the impossibility and accepted the risk of the supervening event, the general rule does not apply and the parties are bound to perform their contract. See Beitbridge-Bulawayo Railways (Pvt) Ltd v Commercial Union Insurance Company of Zimbabwe Ltd SC91-07; Bekker N.O. v Duvenhage 1977 (3) SA 884 (ECD)…,.; Bischofberger v Van Eyk 1981 (2) SA 607 (WLD)…,.; CHRISTIE: The Law of Contract in South Africa (3rd ed.)…,.

There is a further situation more pertinent to the facts in casu where the general rule does not override the obligation of the parties to perform their contract. This arises where a party is only temporarily disabled from fulfilling his contractual obligations, in contradistinction to the position where the contract becomes finally and completely impossible of performance. See Field N.O. & Another v Compuserve (Pvt) Ltd 1990 (2) ZLR 253 (HC)…, citing Beretta v Rhodesia Railways Ltd 1947 (2) SA 1075 (R)…., as follows:

The law is clear that when a contract becomes finally and completely impossible of performance by reason of an act of State it is discharged. Peters Flamman & Co v Kokstad Municipality 1919 AD 427. But this does not cover the situation in which one party is temporarily disabled from fulfilling his obligation.

It is nowhere suggested that the immediate effect of such temporary disability is to end the contract, and this is not surprising, for any such suggestion would involve consequences so extreme as to be unthinkable.”

On the evidence before the Court, there is nothing to indicate that the non-availability of clinker on the market was permanent and irreversible. According to Thomas Jongwe's testimony, this non-availability only occurred towards the end of August 2007 when the defendant's suppliers intimated their inability to supply PC15 cement. This would mean that the defendant was merely temporarily unable to source the 1,200 bags of cement and deliver the same to the plaintiff. Certainly, there was no evidence adduced to contradict the plaintiff's testimony that PC15 cement was available on the market from October 2007 onwards. In any event, the shortage of clinker on the market occurred one month after the promised date of delivery, and, therefore, it could not and should not have affected the defendant's undertaking to deliver the cement to the plaintiff in early August 2007.

It follows that the defendant's defence of supervening impossibility cannot be sustained, either at the time when delivery of the cement was to be effected as contemplated by the parties, i.e. in early August 2007, or at any time from October 2007 onwards, when cement was available on the market. It also follows that the defendant has failed to establish any basis for declining specific performance and must therefore be held bound to its undertaking to deliver PC15 cement to the plaintiff.

Quantum of Damages

Assuming that I am wrong in finding that the plaintiff is entitled to claim specific performance on the facts in casu, it is necessary to consider the measure of damages properly due to the plaintiff.

In this regard, the defendant submits that the plaintiff should have accepted the refund that was tendered by the defendant in October 2007. By refusing to accept that refund, so it is argued, the plaintiff has failed to mitigate his damages and must therefore bear the penalty of a commensurate reduction in the quantum of damages to be awarded.

In my view, these submissions are devoid of merit for several reasons.

It cannot be disputed that the plaintiff's entitlement to damages must entail him being placed in the position he would have been in but for the defendant's breach of contract. The plaintiff's unchallenged evidence was that in order to complete his building project he borrowed the requisite cement and presently remains obligated to replace the borrowed cement. More particularly, he rejected the defendant's offer to refund the purchase price originally paid specifically because the amount tendered would not have placed him in the position he was in at the time that the contract was concluded due to the hyper-inflationary economic environment that prevailed at that time. No evidence was adduced on behalf of the defendant to counter the plaintiff's testimony in the above respects.

I accordingly find that the plaintiff did endeavour to mitigate his loss and that his rejection of the refund offered by the defendant was perfectly justifiable at the material time. Moreover, it is common cause that the plaintiff duly performed his contractual obligations and that the defendant has remained in possession and beneficial use of the money paid by the plaintiff for the cement. It also not disputed that the current minimum price for cement is US$9.50 per bag.

In the final analysis, the law requires that the plaintiff be put in a position to purchase the cement that he requires at the current minimum market price in order to meet his obligation to replace the cement that he has borrowed. He is therefore entitled to the measure of damages that he claims in the alternative.

Disposition

Although the plaintiff's claim for damages was originally framed as an alternative in the event of the claim for specific performance being refused, I believe that it would be just and equitable, at this juncture, having regard to the facts of this case and the circumstances of both parties, to grant both an order for specific performance and damages as alternative remedies.

In the result, judgement is hereby entered in favour of the plaintiff as against the defendant for:

(i) The delivery of 1,200 bags of PC15 cement within 7 days of the granting of this order, or, alternatively, the payment of damages for breach of contract in the sum of US$11,400= being the current market value of 1,200 bags of PC15 cement; and

(ii) Costs of suit.

Variation of Contracts re: Deed of Settlement, Compromise Agreement iro Tender of Settlement and Mitigation of Damages

The plaintiff in this case claims the delivery of 1,200 bags of PC15 cement or, in the alternative, damages for breach of contract equivalent to the current market value of the cement, being US$11,400=, and costs of suit.

The defendant resists the claim on several grounds, to wit, that delivery of the cement was conditional on the defendant receiving the same from its supplier, that it was unable to deliver due to supervening impossibility and that it is no longer able to deliver the cement and has offered a refund to the plaintiff in the sum of ZW$336 million.

Evidence for the Plaintiff

Elliot Mutangadura, the plaintiff, testified as follows. In July 2007 he approached the defendant to purchase various building materials. The defendant then submitted a quotation on the 18th of July 2007 listing those materials that it was able to supply - including the cement in question [Exhibit 1]. At that time, PC15 cement was available on the market and also in the defendant's warehouse (though he was not aware of the quantity thereof). This was confirmed by the defendant's Branch Manager (Mavengere) as well as its Sales Manager (Jongwe) without any condition as to having to await delivery from the defendant's suppliers.

The plaintiff then paid the full purchase price for all the materials in six instalments amounting to $3.51 billion, as was confirmed in a letter from Jongwe dated the 30th of August 2007 [Exhibit 2]. In that letter, Jongwe also confirmed that “we had promised delivery early August.” The defendant thereafter delivered all the purchased items - save for the cement.

On the 19th of September 2007, Mavengere wrote a letter stating that the defendant was “unable to supply PC15 cement as per agreement” and offered to supply masonry or other building materials equivalent to the amount paid [Exhibit 3]. The plaintiff rejected the offer as the PC15 cement was specifically required for the building work in question.

On the 21st of September 2007 the plaintiff's lawyers wrote a letter of demand to the defendant [Exhibit 5]. In response, on the 1st of October, the defendant's lawyers offered a refund of the original purchase price of $336 million [Exhibit 4]. The plaintiff rejected this offer through a letter from his lawyers on the 9th of October [Exhibit 6] because the money tendered was insufficient to pay for 1,200 bags of cement at that time.

Subsequently, from October 2007 to June 2008, the plaintiff sourced 1,200 bags of cement, on loan, from his uncle's hardware business. The return of the cement borrowed is now overdue. The requisite PC15 cement is currently available on the market at US$9.50 to US$10 per bag.

Evidence for the Defendant

Thomas Jongwe was the Sales Manager of the defendant's Harare branch at the relevant time. His evidence was as follows.

Before giving the original quotation to the plaintiff, on the 18th of July 2007, he made enquiries with the defendant's suppliers and told the plaintiff that PC15 cement was available for supply to the plaintiff. However, before the first payment was received, on the 20th of July, he verbally informed the plaintiff that the cement was not immediately available and would be sourced from Unichem, a supplier in Bulawayo. He then placed an order for 1,200 bags with Unichem on the 31st of July [Exhibit 7]. Unichem did not have any clinker, a critical raw material in cement, and he verbally informed the plaintiff of that fact.

The plaintiff made six payments in all, from the 20th of July to the 16th of August 2007, as shown on the receipts therefor [Exhibit 8]. There was no indication on the receipts as to the specific items paid for. The payments were made towards the total quotation amount, with appropriation in respect of each item being made at the time of invoicing. No invoice was raised for the cement as it was not in stock to deliver. In accordance with the defendant's internal accounting system, an invoice is raised after payment is received and is given to the customer at the delivery point as a delivery note.

Under cross-examination, Thomas Jongwe accepted that by the date of the last payment, on the 16th of August 2007, the plaintiff had discharged his obligation under the contract. He also conceded that he made enquiries with the defendant's suppliers and made certain that the cement was available before issuing the quotation to the plaintiff. He further confirmed that PC15 cement is presently available on the market.

Issues for Determination

The agreed issues for determination herein are as follows:

(a) What terms and conditions were agreed to or can be implied from the contract concluded between the parties?

(b) Whether the defendant is liable for specific performance in terms of the contract.

(c) What amount of compensation, if any, is the defendant liable to pay to the plaintiff?

Terms and Conditions of Contract

The evidence before the Court shows that after the plaintiff initially approached the defendant, its Sales Manager, Thomas Jongwe, made enquiries with the defendant's suppliers and received positive confirmation as to the availability of PC15 cement. Jongwe then made out the quotation [Exhibit 1] and upon handing it to the plaintiff on the 18th of July 2007 gave a firm assurance that the cement would be delivered in early August.

At that time, the defendant did not, as it contends, stipulate any condition as to the fulfilment of the contract being subject to delivery from its suppliers. Thereafter, the plaintiff paid the full amount of the quotation in six instalments, beginning on the 20th of July and finishing on the 16th of August 2007. The defendant only raised the non-availability of PC15 cement from its suppliers over one month after full payment had been made and received.

All the payments made by the plaintiff were towards the total quotation and not towards any specific materials thereon. The defendant's invoicing process involved the appropriation of the amounts paid to particular items as and when delivery was effected and the invoices served as delivery notes. However, this was quite clearly a process that was internal to the defendant's accounting system and totally irrelevant to the conclusion of the contract between the parties.

It is quite clear from the foregoing that the contract in casu was concluded unconditionally on the 20th of July 2007 when the defendant accepted the plaintiff's first instalment as part payment towards the entire quotation - including the PC15 cement. The terms and conditions of the contract were that the defendant would deliver the cement in early August against payment by the plaintiff of the full amount of the quotation in instalments. In effect, the parties concluded an unconditional and binding contract for the supply of 1,200 bags of cement to the plaintiff in early August 2007.

Specific Performance and Supervening Impossibility

The defendant avers that at the end of August 2007 it was unable to source PC15 cement from its suppliers because a requisite component (clinker) was not available at that time. It therefore contends that this market factor constituted a supervening event rendering impossible the performance of the contract for the supply of PC15 cement.

It is trite that a party to a binding agreement has the right to demand from the other party, as far as it is possible, performance of his undertaking in terms of the contract where he is in a position to do so. Such specific performance can only be avoided in compelling circumstances. In this respect, the onus lies on the party seeking to avoid the contract to establish the facts and circumstances justifying the court's exercise of its discretion to refuse specific performance. See International Trading (Pvt) Ltd v Nestle Zimbabwe (Pvt) Ltd 1993 (1) ZLR 21 (H)…,.

The general rule in our law is that, if a supervening physical or legal factor renders the performance of a contract impossible, through no fault of the debtor, the obligations of the parties under the contract are thereby extinguished and cannot be enforced. See Beitbridge-Bulawayo Railways (Pvt) Ltd v Commercial Union Insurance Company of Zimbabwe Ltd SC91-07.

However, this general rule does not override the terms of the implications of the contract. The court must have regard to, inter alia, the nature and circumstances of the contract and the nature of the impossibility that is relied upon. If, for instance, it is ascertained that the parties contemplated the situation that gives rise to the impossibility and accepted the risk of the supervening event, the general rule does not apply and the parties are bound to perform their contract. See Beitbridge-Bulawayo Railways (Pvt) Ltd v Commercial Union Insurance Company of Zimbabwe Ltd SC91-07; Bekker N.O. v Duvenhage 1977 (3) SA 884 (ECD)…,.; Bischofberger v Van Eyk 1981 (2) SA 607 (WLD)…,.; CHRISTIE: The Law of Contract in South Africa (3rd ed.)…,.

There is a further situation more pertinent to the facts in casu where the general rule does not override the obligation of the parties to perform their contract. This arises where a party is only temporarily disabled from fulfilling his contractual obligations, in contradistinction to the position where the contract becomes finally and completely impossible of performance. See Field N.O. & Another v Compuserve (Pvt) Ltd 1990 (2) ZLR 253 (HC)…, citing Beretta v Rhodesia Railways Ltd 1947 (2) SA 1075 (R)…., as follows:

The law is clear that when a contract becomes finally and completely impossible of performance by reason of an act of State it is discharged. Peters Flamman & Co v Kokstad Municipality 1919 AD 427. But this does not cover the situation in which one party is temporarily disabled from fulfilling his obligation.

It is nowhere suggested that the immediate effect of such temporary disability is to end the contract, and this is not surprising, for any such suggestion would involve consequences so extreme as to be unthinkable.”

On the evidence before the Court, there is nothing to indicate that the non-availability of clinker on the market was permanent and irreversible. According to Thomas Jongwe's testimony, this non-availability only occurred towards the end of August 2007 when the defendant's suppliers intimated their inability to supply PC15 cement. This would mean that the defendant was merely temporarily unable to source the 1,200 bags of cement and deliver the same to the plaintiff. Certainly, there was no evidence adduced to contradict the plaintiff's testimony that PC15 cement was available on the market from October 2007 onwards. In any event, the shortage of clinker on the market occurred one month after the promised date of delivery, and, therefore, it could not and should not have affected the defendant's undertaking to deliver the cement to the plaintiff in early August 2007.

It follows that the defendant's defence of supervening impossibility cannot be sustained, either at the time when delivery of the cement was to be effected as contemplated by the parties, i.e. in early August 2007, or at any time from October 2007 onwards, when cement was available on the market. It also follows that the defendant has failed to establish any basis for declining specific performance and must therefore be held bound to its undertaking to deliver PC15 cement to the plaintiff.

Quantum of Damages

Assuming that I am wrong in finding that the plaintiff is entitled to claim specific performance on the facts in casu, it is necessary to consider the measure of damages properly due to the plaintiff.

In this regard, the defendant submits that the plaintiff should have accepted the refund that was tendered by the defendant in October 2007. By refusing to accept that refund, so it is argued, the plaintiff has failed to mitigate his damages and must therefore bear the penalty of a commensurate reduction in the quantum of damages to be awarded.

In my view, these submissions are devoid of merit for several reasons.

It cannot be disputed that the plaintiff's entitlement to damages must entail him being placed in the position he would have been in but for the defendant's breach of contract. The plaintiff's unchallenged evidence was that in order to complete his building project he borrowed the requisite cement and presently remains obligated to replace the borrowed cement. More particularly, he rejected the defendant's offer to refund the purchase price originally paid specifically because the amount tendered would not have placed him in the position he was in at the time that the contract was concluded due to the hyper-inflationary economic environment that prevailed at that time. No evidence was adduced on behalf of the defendant to counter the plaintiff's testimony in the above respects.

I accordingly find that the plaintiff did endeavour to mitigate his loss and that his rejection of the refund offered by the defendant was perfectly justifiable at the material time. Moreover, it is common cause that the plaintiff duly performed his contractual obligations and that the defendant has remained in possession and beneficial use of the money paid by the plaintiff for the cement. It also not disputed that the current minimum price for cement is US$9.50 per bag.

In the final analysis, the law requires that the plaintiff be put in a position to purchase the cement that he requires at the current minimum market price in order to meet his obligation to replace the cement that he has borrowed. He is therefore entitled to the measure of damages that he claims in the alternative.

Disposition

Although the plaintiff's claim for damages was originally framed as an alternative in the event of the claim for specific performance being refused, I believe that it would be just and equitable, at this juncture, having regard to the facts of this case and the circumstances of both parties, to grant both an order for specific performance and damages as alternative remedies.

In the result, judgement is hereby entered in favour of the plaintiff as against the defendant for:

(i) The delivery of 1,200 bags of PC15 cement within 7 days of the granting of this order, or, alternatively, the payment of damages for breach of contract in the sum of US$11,400= being the current market value of 1,200 bags of PC15 cement; and

(ii) Costs of suit.

Damages re: Contractual Damages, Damages In Lieu of Specific Performance & Contractual Effects of Breach of Contract

The plaintiff in this case claims the delivery of 1,200 bags of PC15 cement or, in the alternative, damages for breach of contract equivalent to the current market value of the cement, being US$11,400=, and costs of suit.

The defendant resists the claim on several grounds, to wit, that delivery of the cement was conditional on the defendant receiving the same from its supplier, that it was unable to deliver due to supervening impossibility and that it is no longer able to deliver the cement and has offered a refund to the plaintiff in the sum of ZW$336 million.

Evidence for the Plaintiff

Elliot Mutangadura, the plaintiff, testified as follows. In July 2007 he approached the defendant to purchase various building materials. The defendant then submitted a quotation on the 18th of July 2007 listing those materials that it was able to supply - including the cement in question [Exhibit 1]. At that time, PC15 cement was available on the market and also in the defendant's warehouse (though he was not aware of the quantity thereof). This was confirmed by the defendant's Branch Manager (Mavengere) as well as its Sales Manager (Jongwe) without any condition as to having to await delivery from the defendant's suppliers.

The plaintiff then paid the full purchase price for all the materials in six instalments amounting to $3.51 billion, as was confirmed in a letter from Jongwe dated the 30th of August 2007 [Exhibit 2]. In that letter, Jongwe also confirmed that “we had promised delivery early August.” The defendant thereafter delivered all the purchased items - save for the cement.

On the 19th of September 2007, Mavengere wrote a letter stating that the defendant was “unable to supply PC15 cement as per agreement” and offered to supply masonry or other building materials equivalent to the amount paid [Exhibit 3]. The plaintiff rejected the offer as the PC15 cement was specifically required for the building work in question.

On the 21st of September 2007 the plaintiff's lawyers wrote a letter of demand to the defendant [Exhibit 5]. In response, on the 1st of October, the defendant's lawyers offered a refund of the original purchase price of $336 million [Exhibit 4]. The plaintiff rejected this offer through a letter from his lawyers on the 9th of October [Exhibit 6] because the money tendered was insufficient to pay for 1,200 bags of cement at that time.

Subsequently, from October 2007 to June 2008, the plaintiff sourced 1,200 bags of cement, on loan, from his uncle's hardware business. The return of the cement borrowed is now overdue. The requisite PC15 cement is currently available on the market at US$9.50 to US$10 per bag.

Evidence for the Defendant

Thomas Jongwe was the Sales Manager of the defendant's Harare branch at the relevant time. His evidence was as follows.

Before giving the original quotation to the plaintiff, on the 18th of July 2007, he made enquiries with the defendant's suppliers and told the plaintiff that PC15 cement was available for supply to the plaintiff. However, before the first payment was received, on the 20th of July, he verbally informed the plaintiff that the cement was not immediately available and would be sourced from Unichem, a supplier in Bulawayo. He then placed an order for 1,200 bags with Unichem on the 31st of July [Exhibit 7]. Unichem did not have any clinker, a critical raw material in cement, and he verbally informed the plaintiff of that fact.

The plaintiff made six payments in all, from the 20th of July to the 16th of August 2007, as shown on the receipts therefor [Exhibit 8]. There was no indication on the receipts as to the specific items paid for. The payments were made towards the total quotation amount, with appropriation in respect of each item being made at the time of invoicing. No invoice was raised for the cement as it was not in stock to deliver. In accordance with the defendant's internal accounting system, an invoice is raised after payment is received and is given to the customer at the delivery point as a delivery note.

Under cross-examination, Thomas Jongwe accepted that by the date of the last payment, on the 16th of August 2007, the plaintiff had discharged his obligation under the contract. He also conceded that he made enquiries with the defendant's suppliers and made certain that the cement was available before issuing the quotation to the plaintiff. He further confirmed that PC15 cement is presently available on the market.

Issues for Determination

The agreed issues for determination herein are as follows:

(a) What terms and conditions were agreed to or can be implied from the contract concluded between the parties?

(b) Whether the defendant is liable for specific performance in terms of the contract.

(c) What amount of compensation, if any, is the defendant liable to pay to the plaintiff?

Terms and Conditions of Contract

The evidence before the Court shows that after the plaintiff initially approached the defendant, its Sales Manager, Thomas Jongwe, made enquiries with the defendant's suppliers and received positive confirmation as to the availability of PC15 cement. Jongwe then made out the quotation [Exhibit 1] and upon handing it to the plaintiff on the 18th of July 2007 gave a firm assurance that the cement would be delivered in early August.

At that time, the defendant did not, as it contends, stipulate any condition as to the fulfilment of the contract being subject to delivery from its suppliers. Thereafter, the plaintiff paid the full amount of the quotation in six instalments, beginning on the 20th of July and finishing on the 16th of August 2007. The defendant only raised the non-availability of PC15 cement from its suppliers over one month after full payment had been made and received.

All the payments made by the plaintiff were towards the total quotation and not towards any specific materials thereon. The defendant's invoicing process involved the appropriation of the amounts paid to particular items as and when delivery was effected and the invoices served as delivery notes. However, this was quite clearly a process that was internal to the defendant's accounting system and totally irrelevant to the conclusion of the contract between the parties.

It is quite clear from the foregoing that the contract in casu was concluded unconditionally on the 20th of July 2007 when the defendant accepted the plaintiff's first instalment as part payment towards the entire quotation - including the PC15 cement. The terms and conditions of the contract were that the defendant would deliver the cement in early August against payment by the plaintiff of the full amount of the quotation in instalments. In effect, the parties concluded an unconditional and binding contract for the supply of 1,200 bags of cement to the plaintiff in early August 2007.

Specific Performance and Supervening Impossibility

The defendant avers that at the end of August 2007 it was unable to source PC15 cement from its suppliers because a requisite component (clinker) was not available at that time. It therefore contends that this market factor constituted a supervening event rendering impossible the performance of the contract for the supply of PC15 cement.

It is trite that a party to a binding agreement has the right to demand from the other party, as far as it is possible, performance of his undertaking in terms of the contract where he is in a position to do so. Such specific performance can only be avoided in compelling circumstances. In this respect, the onus lies on the party seeking to avoid the contract to establish the facts and circumstances justifying the court's exercise of its discretion to refuse specific performance. See International Trading (Pvt) Ltd v Nestle Zimbabwe (Pvt) Ltd 1993 (1) ZLR 21 (H)…,.

The general rule in our law is that, if a supervening physical or legal factor renders the performance of a contract impossible, through no fault of the debtor, the obligations of the parties under the contract are thereby extinguished and cannot be enforced. See Beitbridge-Bulawayo Railways (Pvt) Ltd v Commercial Union Insurance Company of Zimbabwe Ltd SC91-07.

However, this general rule does not override the terms of the implications of the contract. The court must have regard to, inter alia, the nature and circumstances of the contract and the nature of the impossibility that is relied upon. If, for instance, it is ascertained that the parties contemplated the situation that gives rise to the impossibility and accepted the risk of the supervening event, the general rule does not apply and the parties are bound to perform their contract. See Beitbridge-Bulawayo Railways (Pvt) Ltd v Commercial Union Insurance Company of Zimbabwe Ltd SC91-07; Bekker N.O. v Duvenhage 1977 (3) SA 884 (ECD)…,.; Bischofberger v Van Eyk 1981 (2) SA 607 (WLD)…,.; CHRISTIE: The Law of Contract in South Africa (3rd ed.)…,.

There is a further situation more pertinent to the facts in casu where the general rule does not override the obligation of the parties to perform their contract. This arises where a party is only temporarily disabled from fulfilling his contractual obligations, in contradistinction to the position where the contract becomes finally and completely impossible of performance. See Field N.O. & Another v Compuserve (Pvt) Ltd 1990 (2) ZLR 253 (HC)…, citing Beretta v Rhodesia Railways Ltd 1947 (2) SA 1075 (R)…., as follows:

The law is clear that when a contract becomes finally and completely impossible of performance by reason of an act of State it is discharged. Peters Flamman & Co v Kokstad Municipality 1919 AD 427. But this does not cover the situation in which one party is temporarily disabled from fulfilling his obligation.

It is nowhere suggested that the immediate effect of such temporary disability is to end the contract, and this is not surprising, for any such suggestion would involve consequences so extreme as to be unthinkable.”

On the evidence before the Court, there is nothing to indicate that the non-availability of clinker on the market was permanent and irreversible. According to Thomas Jongwe's testimony, this non-availability only occurred towards the end of August 2007 when the defendant's suppliers intimated their inability to supply PC15 cement. This would mean that the defendant was merely temporarily unable to source the 1,200 bags of cement and deliver the same to the plaintiff. Certainly, there was no evidence adduced to contradict the plaintiff's testimony that PC15 cement was available on the market from October 2007 onwards. In any event, the shortage of clinker on the market occurred one month after the promised date of delivery, and, therefore, it could not and should not have affected the defendant's undertaking to deliver the cement to the plaintiff in early August 2007.

It follows that the defendant's defence of supervening impossibility cannot be sustained, either at the time when delivery of the cement was to be effected as contemplated by the parties, i.e. in early August 2007, or at any time from October 2007 onwards, when cement was available on the market. It also follows that the defendant has failed to establish any basis for declining specific performance and must therefore be held bound to its undertaking to deliver PC15 cement to the plaintiff.

Quantum of Damages

Assuming that I am wrong in finding that the plaintiff is entitled to claim specific performance on the facts in casu, it is necessary to consider the measure of damages properly due to the plaintiff.

In this regard, the defendant submits that the plaintiff should have accepted the refund that was tendered by the defendant in October 2007. By refusing to accept that refund, so it is argued, the plaintiff has failed to mitigate his damages and must therefore bear the penalty of a commensurate reduction in the quantum of damages to be awarded.

In my view, these submissions are devoid of merit for several reasons.

It cannot be disputed that the plaintiff's entitlement to damages must entail him being placed in the position he would have been in but for the defendant's breach of contract. The plaintiff's unchallenged evidence was that in order to complete his building project he borrowed the requisite cement and presently remains obligated to replace the borrowed cement. More particularly, he rejected the defendant's offer to refund the purchase price originally paid specifically because the amount tendered would not have placed him in the position he was in at the time that the contract was concluded due to the hyper-inflationary economic environment that prevailed at that time. No evidence was adduced on behalf of the defendant to counter the plaintiff's testimony in the above respects.

I accordingly find that the plaintiff did endeavour to mitigate his loss and that his rejection of the refund offered by the defendant was perfectly justifiable at the material time. Moreover, it is common cause that the plaintiff duly performed his contractual obligations and that the defendant has remained in possession and beneficial use of the money paid by the plaintiff for the cement. It also not disputed that the current minimum price for cement is US$9.50 per bag.

In the final analysis, the law requires that the plaintiff be put in a position to purchase the cement that he requires at the current minimum market price in order to meet his obligation to replace the cement that he has borrowed. He is therefore entitled to the measure of damages that he claims in the alternative.

Disposition

Although the plaintiff's claim for damages was originally framed as an alternative in the event of the claim for specific performance being refused, I believe that it would be just and equitable, at this juncture, having regard to the facts of this case and the circumstances of both parties, to grant both an order for specific performance and damages as alternative remedies.

In the result, judgement is hereby entered in favour of the plaintiff as against the defendant for:

(i) The delivery of 1,200 bags of PC15 cement within 7 days of the granting of this order, or, alternatively, the payment of damages for breach of contract in the sum of US$11,400= being the current market value of 1,200 bags of PC15 cement; and

(ii) Costs of suit.

Specific Performance re: Triable Issues

The agreed issues for determination herein are as follows:

(a) What terms and conditions were agreed to or can be implied from the contract concluded between the parties?

(b) Whether the defendant is liable for specific performance in terms of the contract.

(c) What amount of compensation, if any, is the defendant liable to pay to the plaintiff?


PATEL J: The plaintiff in this case claims the delivery of 1200 bags of PC 15 cement or, in the alternative, damages for breach of contract equivalent to the current market value of the cement, being US$11,400.00, and costs of suit.

The defendant resists the claim on several grounds, to wit, that delivery of the cement was conditional on the defendant receiving the same from its supplier, that it was unable to deliver due to supervening impossibility and that it is no longer able to deliver the cement and has offered a refund to the plaintiff in the sum of ZW$336 million.

Evidence for the Plaintiff

Elliot Mutangadura, the plaintiff, testified as follows. In July 2007 he approached the defendant to purchase various building materials. The defendant then submitted a quotation on the 18th of July 2007 listing those materials that it was able to supply, including the cement in question [Exhibit 1]. At that time, PC 15 cement was available on the market and also in defendant's warehouse (though he was not aware of the quantity thereof).

This was confirmed by the defendant's Branch Manager (Mavengere) as well as its Sales Manager (Jongwe) without any condition as to having to await delivery from the defendant's suppliers.

The plaintiff then paid the full purchase price for all the materials in six instalments amounting to $3.51 billion, as was confirmed in a letter from Jongwe dated the 30th of August 2007 [Exhibit 2]. In that letter, Jongwe also confirmed that “we had promised delivery early August”. The defendant thereafter delivered all the purchased items, save for the cement.

On the 19th of September 2007 Mavengere wrote a letter stating that the defendant was “unable to supply PC 15 Cement as per agreement” and offered to supply masonry or other building materials equivalent to the amount paid [Exhibit 3]. The plaintiff rejected the offer as the PC 15 cement was specifically required for the building work in question.

On the 21st of September 2007 the plaintiff's lawyers wrote a letter of demand to the defendant [Exhibit 5]. In response, on the 1st of October, the defendant's lawyers offered a refund of the original purchase price of $336 million [Exhibit 4]. The plaintiff rejected this offer through a letter from his lawyers on the 9th of October [Exhibit 6] because the money tendered was insufficient to pay for 1200 bags of cement at that time.

Subsequently, from October 2007 to June 2008, the plaintiff sourced 1200 bags of cement on loan from his uncle's hardware business. The return of the cement borrowed is now overdue. The requisite PC 15 cement is currently available on the market at US$9.50 to US$10 per bag.

Evidence for the Defendant

Thomas Jongwe was the Sales Manager of the defendant's Harare branch at the relevant time. His evidence was as follows.

Before giving the original quotation to the plaintiff on the 18th of July 2007, he made enquiries with the defendant's suppliers and told the plaintiff that PC 15 cement was available for supply to the plaintiff. However, before the first payment was received on the 20th of July, he verbally informed the plaintiff that the cement was not immediately available and would be sourced from Unichem, a supplier in Bulawayo. He then placed an order for 1200 bags with Unichem on the 31st of July [Exhibit 7]. Unichem did not have any clinker, a critical raw material in cement, and he verbally informed the plaintiff of that fact.

The plaintiff made six payments in all, from the 20th of July to the 16th of August 2007, as shown on the receipts therefor [Exhibit 8]. There was no indication on the receipts as to the specific items paid for. The payments were made towards the total quotation amount, with appropriation in respect of each item being made at the time of invoicing. No invoice was raised for the cement as it was not in stock to deliver. In accordance with the defendant's internal accounting system, an invoice is raised after payment is received and is given to the customer at the delivery point as a delivery note.

Under cross-examination, Jongwe accepted that by the date of the last payment on the 18th of July 2007 the plaintiff had discharged his obligation under the contract. He also conceded that he made enquiries with the defendant's suppliers and made certain that the cement was available before issuing the quotation to the plaintiff. He further confirmed that PC 15 cement is presently available on the market.

Issues for Determination

The agreed issues for determination herein are as follows:

(a) What terms and conditions were agreed to or can be implied from the contract concluded between the parties?

(b) Whether the defendant is liable for specific performance in terms of the contract.

(c) What amount of compensation, if any, is the defendant liable to pay to the plaintiff?

Terms and Conditions of Contract

The evidence before the Court shows that after the plaintiff initially approached the defendant, its Sales Manager, Thomas Jongwe, made enquiries with the defendant's suppliers and received positive confirmation as to the availability of PC 15 cement. Jongwe then made out the quotation [Exhibit 1] and upon handing it to the plaintiff on the 18th of July 2007 gave a firm assurance that the cement would be delivered in early August.

At that time, the defendant did not, as it contends, stipulate any condition as to the fulfilment of the contract being subject to delivery from its suppliers. Thereafter, the plaintiff paid the full amount of the quotation in six instalments, beginning on the 20th of July and finishing on the 16th of August 2007. The defendant only raised the non-availability of PC 15 cement from its suppliers over one month after full payment had been made and received.

All the payments made by the plaintiff were towards the total quotation and not towards any specific materials thereon. The defendant's invoicing process involved the appropriation of the amounts paid to particular items as and when delivery was effected and the invoices served as delivery notes. However, this was quite clearly a process that was internal to the defendant's accounting system and totally irrelevant to the conclusion of the contract between the parties.

It is quite clear from the foregoing that the contract in casu was concluded unconditionally on the 20th of July 2007 when the defendant accepted the plaintiff's first instalment as part payment towards the entire quotation, including the PC 15 cement. The terms and conditions of the contract were that the defendant would deliver the cement in early August against payment by the plaintiff of the full amount of the quotation in instalments. In effect, the parties concluded an unconditional and binding contract for the supply of 1200 bags of cement to the plaintiff in early August 2007.

Specific Performance and Supervening Impossibility

The defendant avers that at the end of August 2007 it was unable to source PC 15 cement from its suppliers because a requisite component (clinker) was not available at that time. It therefore contends that this market factor constituted a supervening event rendering impossible the performance of the contract for the supply of PC 15 cement.

It is trite that a party to a binding agreement has the right to demand from the other party, as far as it is possible, performance of his undertaking in terms of the contract where he is in a position to do so. Such specific performance can only be avoided in compelling circumstances. In this respect, the onus lies on the party seeking to avoid the contract to establish the facts and circumstances justifying the court's exercise of its discretion to refuse specific performance. See International Trading (Pvt) Ltd v Nestle Zimbabwe (Pvt) Ltd 1993 (1) ZLR 21 (H) at 28.

The general rule in our law is that, if a supervening physical or legal factor renders the performance of a contract impossible through no fault of the debtor, the obligations of the parties under the contract are thereby extinguished and cannot be enforced. See Beitbridge-Bulawayo Railways (Pvt) Ltd v Commercial Union Insurance Company of Zimbabwe Ltd SC 91-2007.

However, this general rule does not override the terms of the implications of the contract. The court must have regard to, inter alia, the nature and circumstances of the contract and the nature of the impossibility that is relied upon. If, for instance, it is ascertained that the parties contemplated the situation that gives rise to the impossibility and accepted the risk of the supervening event, the general rule does not apply and the parties are bound to perform their contract. See Beitbridge-Bulawayo Railways case, supra; Bekker N.O. v Duvenhage 1977 (3) SA 884 (ECD) at 888; Bischofberger v Van Eyk 1981 (2) SA 607 (WLD) at 610-611; Christie: The Law of Contract in South Africa (3rd ed.) at 527.

There is a further situation, more pertinent to the facts in casu, where the general rule does not override the obligation of the parties to perform their contract. This arises where a party is only temporarily disabled from fulfilling his contractual obligations, in contradistinction to the position where the contract becomes finally and completely impossible of performance. See Field N.O. & Another v Compuserve (Pvt) Ltd 1990 (2) ZLR 253 (HC) at 260, citing Beretta v Rhodesia Railways Ltd 1947 (2) SA 1075 (R) at 1078 as follows:

The law is clear that when a contract becomes finally and completely impossible of performance by reason of an act of State it is discharged. Peters Flamman & Co v Kokstad Municipality 1919 AD 427. But this does not cover the situation in which one party is temporarily disabled from fulfilling his obligation.

It is nowhere suggested that the immediate effect of such temporary disability is to end the contract, and this is not surprising, for any such suggestion would involve consequences so extreme as to be unthinkable.”


On the evidence before the Court, there is nothing to indicate that the non-availability of clinker on the market was permanent and irreversible. According to Jongwe's testimony, this non-availability only occurred towards the end of August 2007 when the defendant's suppliers intimated their inability to supply PC 15 cement. This would mean that the defendant was merely temporarily unable to source the 1200 bags of cement and deliver the same to the plaintiff. Certainly, there was no evidence adduced to contradict the plaintiff's testimony that PC 15 cement was available on the market from October 2007 onwards. In any event, the shortage of clinker on the market occurred one month after the promised date of delivery and, therefore, it could not and should not have affected the defendant's undertaking to deliver the cement to the plaintiff in early August 2007.

It follows that the defendant's defence of supervening impossibility cannot be sustained, either at the time when delivery of the cement was to be effected as contemplated by the parties, i.e. in early August 2007, or at any time from October 2007 onwards, when cement was available on the market. It also follows that the defendant has failed to establish any basis for declining specific performance and must therefore be held bound to its undertaking to deliver PC 15 cement to the plaintiff.

Quantum of Damages

Assuming that I am wrong in finding that the plaintiff is entitled to claim specific performance on the facts in casu, it is necessary to consider the measure of damages properly due to the plaintiff.

In this regard, the defendant submits that the plaintiff should have accepted the refund that was tendered by the defendant in October 2007. By refusing to accept that refund, so it is argued, the plaintiff has failed to mitigate his damages and must therefore bear the penalty of a commensurate reduction in the quantum of damages to be awarded.

In my view, these submissions are devoid of merit for several reasons.

It cannot be disputed that the plaintiff's entitlement to damages must entail him being placed in the position he would have been in but for the defendant's breach of contract. The plaintiff's unchallenged evidence was that in order to complete his building project he borrowed the requisite cement and presently remains obligated to replace the borrowed cement. More particularly, he rejected the defendant's offer to refund the purchase price originally paid specifically because the amount tendered would not have placed him in the position he was in at the time that the contract was concluded due to the hyperinflationary economic environment that prevailed at that time. No evidence was adduced on behalf of the defendant to counter the plaintiff's testimony in the above respects.

I accordingly find that the plaintiff did endeavour to mitigate his loss and that his rejection of the refund offered by the defendant was perfectly justifiable at the material time. Moreover, it is common cause that the plaintiff duly performed his contractual obligations and that the defendant has remained in possession and beneficial use of the money paid by the plaintiff for the cement. It also not disputed that the current minimum price for cement is US$9.50 per bag.

In the final analysis, the law requires that the plaintiff be put in a position to purchase the cement that he requires at the current minimum market price in order to meet his obligation to replace the cement that he has borrowed. He is therefore entitled to the measure of damages that he claims in the alternative.

Disposition

Although the plaintiff's claim for damages was originally framed as an alternative in the event of the claim for specific performance being refused, I believe that it would be just and equitable at this juncture, having regard to the facts of this case and the circumstances of both parties, to grant both an order for specific performance and damages as alternative remedies.

In the result, judgement is hereby entered in favour of the plaintiff as against the defendant for:

(i) the delivery of 1200 bags of PC 15 cement within 7 days of the granting of this order or, alternatively, the payment of damages for breach of contract in the sum of US$11,400.00 being the current market value of 1200 bags of PC 15 cement; and

(ii) costs of suit.








Chirimuuta & Associates, plaintiff's legal practitioners

Wintertons, defendant's legal practitioners

Back Main menu

Categories

Back to top