Law Portal
Zimbabwe

Welcome To Law Portal

Welcome, Guest!
[Help?]

SC37-09 - EDDIES PFUGARI (PVT) LTD vs KNOWE RESIDENTS ASSOCIATION and NORTON TOWN COUNCIL

  • View Judgment By Categories
  • View Full Judgment


Law of Property-viz land development re servicing of Stands.
Company Law-viz voluntary associations.
Company Law-viz unincorporated associations.
Procedural Law-viz locus standi re legal status of a litigating party iro voluntary associations.
Procedural Law-viz locus standi re legal status of litigants iro un-incorporated associations.
Procedural Law-viz appeal re findings of fact made by the primary court.
Procedural Law-viz pleadings re abandoned pleadings.
Procedural Law-viz disputes of fact re material dispute of facts.
Procedural Law-viz dispute of facts re material disputes of fact.
Procedural Law-viz conflict of facts re robust approach.
Procedural Law-viz dispute of facts re common sense approach.
Procedural Law-viz appeal re the exercise of discretion by the trial court.
Procedural Law-viz pleadings re admissions iro confession and avoidance.
Law of Contract-viz specific performance re specific performance ex contractu.
Law of Contract-viz specific performance re time of performance iro debtors mora.
Law of Contract-viz intent re implied contractual provisions.
Law of Contract-viz animus contrahendi re implied contractual provisions.
Procedural Law-viz rules of construction re contractual provisions iro implied contractual provisions.
Procedural Law-viz rules of interpretation re contractual clauses iro implied contractual clauses.
Law of Contract-viz specific performance re time for performance iro debtor's mora.

Locus Standi re: Legal Status of Litigants, Voluntary or Un-incorporated Associations & the Principle of Legal Persona


This is an appeal against the judgment of the High Court directing the appellant to fully service residential stands in Phase 1 of the Knowe Housing Development in Norton.

The facts of this case are these:

The appellant, a private company, is a property developer whilst the respondent is an association of residents of the Knowe Housing Development, who, in 1998, entered into agreements of sale with the appellant in their individual capacities for the purchase of residential Stands.

The association was formed by the residents in order to compel the appellant to carry out its obligations in terms of the various contracts it had entered into with the various individuals who form the association.

Objectives, Vesting of Administrative Powers, Disputes, Derivative Actions and the Proper Plaintiff Rule


This is an appeal against the judgment of the High Court directing the appellant to fully service residential stands in Phase 1 of the Knowe Housing Development in Norton.

The facts of this case are these:

The appellant, a private company, is a property developer whilst the respondent is an association of residents of the Knowe Housing Development, who, in 1998, entered into agreements of sale with the appellant in their individual capacities for the purchase of residential Stands.

The association was formed by the residents in order to compel the appellant to carry out its obligations in terms of the various contracts it had entered into with the various individuals who form the association.

Pleadings re: Abandoned Pleadings


This is an appeal against the judgment of the High Court directing the appellant to fully service residential stands in Phase 1 of the Knowe Housing Development in Norton.

The facts of this case are these:

The appellant, a private company, is a property developer whilst the respondent is an association of residents of the Knowe Housing Development, who, in 1998, entered into agreements of sale with the appellant in their individual capacities for the purchase of residential Stands.

The association was formed by the residents in order to compel the appellant to carry out its obligations in terms of the various contracts it had entered into with the various individuals who form the association.

The High Court found that the appellant had breached the terms of agreement between itself and the residents in regard to Phase 1 of the development. Consequently, the court granted an order directing the appellant to fully service Phase 1 of the housing development within 90 days, and, in particular, to connect to all Stands reticulated water, sanitary systems, tarred roads, and a proper drainage system.

Dissatisfied with that order, the appellant appealed to this Court on the grounds that:

(a) The court a quo had erred in finding that the respondent had locus standi in judicio to institute the proceedings; and

(b) The court a quo had erred in rejecting the appellant's contention that it had complied with its obligations in terms of the relevant Development Permit.

At the hearing of the matter before this Court, counsel for the appellant abandoned the other grounds of appeal and attacked the judgment of the court a quo on the sole basis that there were material disputes of facts which were incapable of resolution on the papers, and, for that reason, the matter should either have been referred to trial or dismissed.

The sole issue for determination before this Court, therefore, is whether the court a quo erred in resolving the disputes raised on the papers without hearing evidence.

Rules of Construction or Interpretation re: Contractual Clauses & Contra Proferentem Rule or Contra Stipulatorem Rule


In reading an implied term into a contract, the court must of course be bound by the principles set out in case law: see Mullin (Pvt) Ltd v Benade Ltd 1952 (1) SA 211.

Employment Contract re: Approach, Pre-employment Formalities and Implied, Inferred, Explicit and Statutory Conditions


In reading an implied term into a contract, the court must of course be bound by the principles set out in case law: see Mullin (Pvt) Ltd v Benade Ltd 1952 (1) SA 211.

Passing of Ownership, Proof of Title and Jus in re Propria re: Subdivisions, Land Developments and Servicing of Stands


This is an appeal against the judgment of the High Court directing the appellant to fully service residential stands in Phase 1 of the Knowe Housing Development in Norton.

The facts of this case are these:

The appellant, a private company, is a property developer whilst the respondent is an association of residents of the Knowe Housing Development, who, in 1998, entered into agreements of sale with the appellant in their individual capacities for the purchase of residential Stands.

The association was formed by the residents in order to compel the appellant to carry out its obligations in terms of the various contracts it had entered into with the various individuals who form the association.

The High Court found that the appellant had breached the terms of agreement between itself and the residents in regard to Phase 1 of the development. Consequently, the court granted an order directing the appellant to fully service Phase 1 of the housing development within 90 days, and, in particular, to connect to all Stands reticulated water, sanitary systems, tarred roads, and a proper drainage system.

Dissatisfied with that order, the appellant appealed to this Court on the grounds that:

(a) The court a quo had erred in finding that the respondent had locus standi in judicio to institute the proceedings; and

(b) The court a quo had erred in rejecting the appellant's contention that it had complied with its obligations in terms of the relevant Development Permit.

At the hearing of the matter before this Court, counsel for the appellant abandoned the other grounds of appeal and attacked the judgment of the court a quo on the sole basis that there were material disputes of facts which were incapable of resolution on the papers, and, for that reason, the matter should either have been referred to trial or dismissed.

The sole issue for determination before this Court, therefore, is whether the court a quo erred in resolving the disputes raised on the papers without hearing evidence.

In terms of condition 27 of the Development Permit issued to the appellant by the second respondent, the appellant was obliged, at his own expense, to: “provide all infrastructural services viz roads, electricity, water mains, and sewerage disposal, to the specification approved by and to the satisfaction of Norton Town Council and all such services shall be handed over to Council at a date to be agreed upon by the two parties involved.”

In its founding papers before the High Court, the first respondent alleged that the appellant had breached the contract in various respects.

The first respondent alleged that although the appellant had tarred the roads in Phase 1, it had done so in a substandard manner; that no proper drainage system had been constructed; and tapped water was not available at all the Stands. The first respondent further alleged that no street lighting had been put in place and social amenities, such as schools and clinics, were still to be constructed.

In its opposing affidavit, the appellant asserted, that, it had done its best to carry out its obligations under the difficult economic conditions prevailing in Zimbabwe, and that it was on course to completing its obligations.

It further stated, that, although there were no tarred roads in Phases 1 and 2, it had acquired state of the art equipment in order to carry out this task.

The appellant further stated, that, the roads had not been tarred because of the scarcity of diesel and unavailability of tar in Zimbabwe.

However, the appellant also stated, that, the road network in Phase 1 had been done satisfactorily by a Chinese sub-contractor.

The appellant further remarked, that, no drainage system had been put in place because the tarring of the roads had to be completed first. Culverts too were to be constructed after the roads had been tarred. The drainage was not as bad as suggested by the first respondent.

The appellant also stated, that, water mains had been installed and what remained was for the individual Stand holders to apply for connections.

As regards street lighting, the appellant submitted, that, this could only be attended to once the roads had been tarred.

Lastly, the appellant remarked, that, it had not deliberately avoided fully servicing the area but had been constrained by factors beyond its control, and, that, if given three months, it would ensure that the roads are completed.

In its opposing papers, the second respondent highlighted the fact that the appellant had not successfully completed Phase 1, and, therefore, should not have embarked on Phases 2 and 3 of the development project.

In determining that the appellant was in breach of its contractual obligations, the court a quo remarked, at page 6 of the cyclostyled judgment:

“It was quite apparent, from the papers before me, that the first respondent was indeed in breach of the terms of his contract in regard to Phase One of the development.

The applicant, through its members, has complied with their part of the contract and paid for the Stands in full. In my view, they may properly seek an order for specific performance.

In its opposition, the first respondent argued that the court should not exercise its discretion in favour of the applicant as the obligation was too onerous for it to perform. The excuses made by the first respondent, relating to unavailability of diesel and tar, were, in my view, merely an excuse as the applicant could carry out its obligations if it was diligent in its efforts. Whilst the court takes judicial notice of the socio-economic hardships complained of, it also notes that other successful developments have continued in spite of these challenges.

The second issue raised by the first respondent was that there was no timeframe for performance in the permit and they were therefore still in the process of completing the task.

This, in my view, was no defence to the order sought by the applicants.

Whilst it is noted that the permit does not indeed give a time frame within which the infrastructural development must be carried out, it is an implied term of the contract that performance must be conducted within a reasonable time.

In reading an implied term into a contract, the court must of course be bound by the principles set out in case law: see Mullin (Pvt) Ltd v Benade Ltd 1952 (1) SA 211.

The applicants in this case entered into the contracts with the first respondent in 1998. This application was filed on 22 June 2005. Clearly, the time lapse between the time of entering into the contract and time for performance exceeds, by any stretch of the imagination, the definition of a reasonable time.

In my view, a period in excess of six years is no longer a reasonable time - even in these challenging times.”

On the facts of this case, I am in no doubt that the court a quo was correct in determining the dispute on the papers.

The appellant had obligations which it had failed to discharge - even at the time of the hearing of the matter before the High Court in November 2006. The second respondent had still not issued the appellant with a Certificate of Compliance.

The appellant does not dispute, in its papers, that it had not discharged all its obligations in terms of the permit. Instead, the appellant states that it did the best in the prevailing socio economic situation and that it was on course to discharging its obligations under the contract.

The second respondent, in its papers, states that the servicing of Phase 1 had not been completed.

The remark by the appellant, that the drainage is not as bad as portrayed, is an admission that the work was not complete. Indeed, the appellant admitted that work was still to be done in tarring the roads, constructing a drainage system, and providing amenities.

The dispute, on the facts, could be resolved without hearing evidence. The position is now well established that:

“In motion proceedings, a court should endeavour to resolve the dispute raised in affidavits without the hearing of evidence. It must take a robust and common sense approach and not an over fastidious one; always provided that it is convinced that there is no real possibility of any resolution doing an injustice to the other party concerned.”

See Zimbabwe Bonded Fibreglass (Pvt) Ltd v Peech 1987 (2) ZLR 338 (SC)…,.

I agree with the submission by the respondent that the dispute was not so much on the substance but rather on the extent of non-compliance. I find no basis upon which the approach taken by the court a quo can be impugned.

The appeal is without merit. It is accordingly dismissed with costs.

Specific Performance re: Approach, Impossibility of Performance and the Exceptio Non Adimpleti Contractus


This is an appeal against the judgment of the High Court directing the appellant to fully service residential stands in Phase 1 of the Knowe Housing Development in Norton.

The facts of this case are these:

The appellant, a private company, is a property developer whilst the respondent is an association of residents of the Knowe Housing Development, who, in 1998, entered into agreements of sale with the appellant in their individual capacities for the purchase of residential Stands.

The association was formed by the residents in order to compel the appellant to carry out its obligations in terms of the various contracts it had entered into with the various individuals who form the association.

The High Court found that the appellant had breached the terms of agreement between itself and the residents in regard to Phase 1 of the development. Consequently, the court granted an order directing the appellant to fully service Phase 1 of the housing development within 90 days, and, in particular, to connect to all Stands reticulated water, sanitary systems, tarred roads, and a proper drainage system.

Dissatisfied with that order, the appellant appealed to this Court on the grounds that:

(a) The court a quo had erred in finding that the respondent had locus standi in judicio to institute the proceedings; and

(b) The court a quo had erred in rejecting the appellant's contention that it had complied with its obligations in terms of the relevant Development Permit.

At the hearing of the matter before this Court, counsel for the appellant abandoned the other grounds of appeal and attacked the judgment of the court a quo on the sole basis that there were material disputes of facts which were incapable of resolution on the papers, and, for that reason, the matter should either have been referred to trial or dismissed.

The sole issue for determination before this Court, therefore, is whether the court a quo erred in resolving the disputes raised on the papers without hearing evidence.

In terms of condition 27 of the Development Permit issued to the appellant by the second respondent, the appellant was obliged, at his own expense, to: “provide all infrastructural services viz roads, electricity, water mains, and sewerage disposal, to the specification approved by and to the satisfaction of Norton Town Council and all such services shall be handed over to Council at a date to be agreed upon by the two parties involved.”

In its founding papers before the High Court, the first respondent alleged that the appellant had breached the contract in various respects.

The first respondent alleged that although the appellant had tarred the roads in Phase 1, it had done so in a substandard manner; that no proper drainage system had been constructed; and tapped water was not available at all the Stands. The first respondent further alleged that no street lighting had been put in place and social amenities, such as schools and clinics, were still to be constructed.

In its opposing affidavit, the appellant asserted, that, it had done its best to carry out its obligations under the difficult economic conditions prevailing in Zimbabwe, and that it was on course to completing its obligations.

It further stated, that, although there were no tarred roads in Phases 1 and 2, it had acquired state of the art equipment in order to carry out this task.

The appellant further stated, that, the roads had not been tarred because of the scarcity of diesel and unavailability of tar in Zimbabwe.

However, the appellant also stated, that, the road network in Phase 1 had been done satisfactorily by a Chinese sub-contractor.

The appellant further remarked, that, no drainage system had been put in place because the tarring of the roads had to be completed first. Culverts too were to be constructed after the roads had been tarred. The drainage was not as bad as suggested by the first respondent.

The appellant also stated, that, water mains had been installed and what remained was for the individual Stand holders to apply for connections.

As regards street lighting, the appellant submitted, that, this could only be attended to once the roads had been tarred.

Lastly, the appellant remarked, that, it had not deliberately avoided fully servicing the area but had been constrained by factors beyond its control, and, that, if given three months, it would ensure that the roads are completed.

In its opposing papers, the second respondent highlighted the fact that the appellant had not successfully completed Phase 1, and, therefore, should not have embarked on Phases 2 and 3 of the development project.

In determining that the appellant was in breach of its contractual obligations, the court a quo remarked, at page 6 of the cyclostyled judgment:

“It was quite apparent, from the papers before me, that the first respondent was indeed in breach of the terms of his contract in regard to Phase One of the development.

The applicant, through its members, has complied with their part of the contract and paid for the Stands in full. In my view, they may properly seek an order for specific performance.

In its opposition, the first respondent argued that the court should not exercise its discretion in favour of the applicant as the obligation was too onerous for it to perform. The excuses made by the first respondent, relating to unavailability of diesel and tar, were, in my view, merely an excuse as the applicant could carry out its obligations if it was diligent in its efforts. Whilst the court takes judicial notice of the socio-economic hardships complained of, it also notes that other successful developments have continued in spite of these challenges.

The second issue raised by the first respondent was that there was no timeframe for performance in the permit and they were therefore still in the process of completing the task.

This, in my view, was no defence to the order sought by the applicants.

Whilst it is noted that the permit does not indeed give a time frame within which the infrastructural development must be carried out, it is an implied term of the contract that performance must be conducted within a reasonable time.

In reading an implied term into a contract, the court must of course be bound by the principles set out in case law: see Mullin (Pvt) Ltd v Benade Ltd 1952 (1) SA 211.

The applicants in this case entered into the contracts with the first respondent in 1998. This application was filed on 22 June 2005. Clearly, the time lapse between the time of entering into the contract and time for performance exceeds, by any stretch of the imagination, the definition of a reasonable time.

In my view, a period in excess of six years is no longer a reasonable time - even in these challenging times.”

On the facts of this case, I am in no doubt that the court a quo was correct in determining the dispute on the papers.

The appellant had obligations which it had failed to discharge - even at the time of the hearing of the matter before the High Court in November 2006. The second respondent had still not issued the appellant with a Certificate of Compliance.

The appellant does not dispute, in its papers, that it had not discharged all its obligations in terms of the permit. Instead, the appellant states that it did the best in the prevailing socio economic situation and that it was on course to discharging its obligations under the contract.

The second respondent, in its papers, states that the servicing of Phase 1 had not been completed.

The remark by the appellant, that the drainage is not as bad as portrayed, is an admission that the work was not complete. Indeed, the appellant admitted that work was still to be done in tarring the roads, constructing a drainage system, and providing amenities.

The dispute, on the facts, could be resolved without hearing evidence. The position is now well established that:

“In motion proceedings, a court should endeavour to resolve the dispute raised in affidavits without the hearing of evidence. It must take a robust and common sense approach and not an over fastidious one; always provided that it is convinced that there is no real possibility of any resolution doing an injustice to the other party concerned.”

See Zimbabwe Bonded Fibreglass (Pvt) Ltd v Peech 1987 (2) ZLR 338 (SC)…,.

I agree with the submission by the respondent that the dispute was not so much on the substance but rather on the extent of non-compliance. I find no basis upon which the approach taken by the court a quo can be impugned.

The appeal is without merit. It is accordingly dismissed with costs.

Disputes of Fact or Conflict of Facts re: Approach, Factual, Non-Factual, Questions of Law and Material Resolutions


This is an appeal against the judgment of the High Court directing the appellant to fully service residential stands in Phase 1 of the Knowe Housing Development in Norton.

The facts of this case are these:

The appellant, a private company, is a property developer whilst the respondent is an association of residents of the Knowe Housing Development, who, in 1998, entered into agreements of sale with the appellant in their individual capacities for the purchase of residential Stands.

The association was formed by the residents in order to compel the appellant to carry out its obligations in terms of the various contracts it had entered into with the various individuals who form the association.

The High Court found that the appellant had breached the terms of agreement between itself and the residents in regard to Phase 1 of the development. Consequently, the court granted an order directing the appellant to fully service Phase 1 of the housing development within 90 days, and, in particular, to connect to all Stands reticulated water, sanitary systems, tarred roads, and a proper drainage system.

Dissatisfied with that order, the appellant appealed to this Court on the grounds that:

(a) The court a quo had erred in finding that the respondent had locus standi in judicio to institute the proceedings; and

(b) The court a quo had erred in rejecting the appellant's contention that it had complied with its obligations in terms of the relevant Development Permit.

At the hearing of the matter before this Court, counsel for the appellant abandoned the other grounds of appeal and attacked the judgment of the court a quo on the sole basis that there were material disputes of facts which were incapable of resolution on the papers, and, for that reason, the matter should either have been referred to trial or dismissed.

The sole issue for determination before this Court, therefore, is whether the court a quo erred in resolving the disputes raised on the papers without hearing evidence.

In terms of condition 27 of the Development Permit issued to the appellant by the second respondent, the appellant was obliged, at his own expense, to: “provide all infrastructural services viz roads, electricity, water mains, and sewerage disposal, to the specification approved by and to the satisfaction of Norton Town Council and all such services shall be handed over to Council at a date to be agreed upon by the two parties involved.”

In its founding papers before the High Court, the first respondent alleged that the appellant had breached the contract in various respects.

The first respondent alleged that although the appellant had tarred the roads in Phase 1, it had done so in a substandard manner; that no proper drainage system had been constructed; and tapped water was not available at all the Stands. The first respondent further alleged that no street lighting had been put in place and social amenities, such as schools and clinics, were still to be constructed.

In its opposing affidavit, the appellant asserted, that, it had done its best to carry out its obligations under the difficult economic conditions prevailing in Zimbabwe, and that it was on course to completing its obligations.

It further stated, that, although there were no tarred roads in Phases 1 and 2, it had acquired state of the art equipment in order to carry out this task.

The appellant further stated, that, the roads had not been tarred because of the scarcity of diesel and unavailability of tar in Zimbabwe.

However, the appellant also stated, that, the road network in Phase 1 had been done satisfactorily by a Chinese sub-contractor.

The appellant further remarked, that, no drainage system had been put in place because the tarring of the roads had to be completed first. Culverts too were to be constructed after the roads had been tarred. The drainage was not as bad as suggested by the first respondent.

The appellant also stated, that, water mains had been installed and what remained was for the individual Stand holders to apply for connections.

As regards street lighting, the appellant submitted, that, this could only be attended to once the roads had been tarred.

Lastly, the appellant remarked, that, it had not deliberately avoided fully servicing the area but had been constrained by factors beyond its control, and, that, if given three months, it would ensure that the roads are completed.

In its opposing papers, the second respondent highlighted the fact that the appellant had not successfully completed Phase 1, and, therefore, should not have embarked on Phases 2 and 3 of the development project.

In determining that the appellant was in breach of its contractual obligations, the court a quo remarked, at page 6 of the cyclostyled judgment:

“It was quite apparent, from the papers before me, that the first respondent was indeed in breach of the terms of his contract in regard to Phase One of the development.

The applicant, through its members, has complied with their part of the contract and paid for the Stands in full. In my view, they may properly seek an order for specific performance.

In its opposition, the first respondent argued that the court should not exercise its discretion in favour of the applicant as the obligation was too onerous for it to perform. The excuses made by the first respondent, relating to unavailability of diesel and tar, were, in my view, merely an excuse as the applicant could carry out its obligations if it was diligent in its efforts. Whilst the court takes judicial notice of the socio-economic hardships complained of, it also notes that other successful developments have continued in spite of these challenges.

The second issue raised by the first respondent was that there was no timeframe for performance in the permit and they were therefore still in the process of completing the task.

This, in my view, was no defence to the order sought by the applicants.

Whilst it is noted that the permit does not indeed give a time frame within which the infrastructural development must be carried out, it is an implied term of the contract that performance must be conducted within a reasonable time.

In reading an implied term into a contract, the court must of course be bound by the principles set out in case law: see Mullin (Pvt) Ltd v Benade Ltd 1952 (1) SA 211.

The applicants in this case entered into the contracts with the first respondent in 1998. This application was filed on 22 June 2005. Clearly, the time lapse between the time of entering into the contract and time for performance exceeds, by any stretch of the imagination, the definition of a reasonable time.

In my view, a period in excess of six years is no longer a reasonable time - even in these challenging times.”

On the facts of this case, I am in no doubt that the court a quo was correct in determining the dispute on the papers.

The appellant had obligations which it had failed to discharge - even at the time of the hearing of the matter before the High Court in November 2006. The second respondent had still not issued the appellant with a Certificate of Compliance.

The appellant does not dispute, in its papers, that it had not discharged all its obligations in terms of the permit. Instead, the appellant states that it did the best in the prevailing socio economic situation and that it was on course to discharging its obligations under the contract.

The second respondent, in its papers, states that the servicing of Phase 1 had not been completed.

The remark by the appellant, that the drainage is not as bad as portrayed, is an admission that the work was not complete. Indeed, the appellant admitted that work was still to be done in tarring the roads, constructing a drainage system, and providing amenities.

The dispute, on the facts, could be resolved without hearing evidence. The position is now well established that:

“In motion proceedings, a court should endeavour to resolve the dispute raised in affidavits without the hearing of evidence. It must take a robust and common sense approach and not an over fastidious one; always provided that it is convinced that there is no real possibility of any resolution doing an injustice to the other party concerned.”

See Zimbabwe Bonded Fibreglass (Pvt) Ltd v Peech 1987 (2) ZLR 338 (SC)…,.

I agree with the submission by the respondent that the dispute was not so much on the substance but rather on the extent of non-compliance. I find no basis upon which the approach taken by the court a quo can be impugned.

The appeal is without merit. It is accordingly dismissed with costs.

Pleadings re: Admissions or Undisputed Facts iro Confessionaries, Confession and Avoidance & Concession and Avoidance


This is an appeal against the judgment of the High Court directing the appellant to fully service residential stands in Phase 1 of the Knowe Housing Development in Norton.

The facts of this case are these:

The appellant, a private company, is a property developer whilst the respondent is an association of residents of the Knowe Housing Development, who, in 1998, entered into agreements of sale with the appellant in their individual capacities for the purchase of residential Stands.

The association was formed by the residents in order to compel the appellant to carry out its obligations in terms of the various contracts it had entered into with the various individuals who form the association.

The High Court found that the appellant had breached the terms of agreement between itself and the residents in regard to Phase 1 of the development. Consequently, the court granted an order directing the appellant to fully service Phase 1 of the housing development within 90 days, and, in particular, to connect to all Stands reticulated water, sanitary systems, tarred roads, and a proper drainage system.

Dissatisfied with that order, the appellant appealed to this Court on the grounds that:

(a) The court a quo had erred in finding that the respondent had locus standi in judicio to institute the proceedings; and

(b) The court a quo had erred in rejecting the appellant's contention that it had complied with its obligations in terms of the relevant Development Permit.

At the hearing of the matter before this Court, counsel for the appellant abandoned the other grounds of appeal and attacked the judgment of the court a quo on the sole basis that there were material disputes of facts which were incapable of resolution on the papers, and, for that reason, the matter should either have been referred to trial or dismissed.

The sole issue for determination before this Court, therefore, is whether the court a quo erred in resolving the disputes raised on the papers without hearing evidence.

In terms of condition 27 of the Development Permit issued to the appellant by the second respondent, the appellant was obliged, at his own expense, to: “provide all infrastructural services viz roads, electricity, water mains, and sewerage disposal, to the specification approved by and to the satisfaction of Norton Town Council and all such services shall be handed over to Council at a date to be agreed upon by the two parties involved.”

In its founding papers before the High Court, the first respondent alleged that the appellant had breached the contract in various respects.

The first respondent alleged that although the appellant had tarred the roads in Phase 1, it had done so in a substandard manner; that no proper drainage system had been constructed; and tapped water was not available at all the Stands. The first respondent further alleged that no street lighting had been put in place and social amenities, such as schools and clinics, were still to be constructed.

In its opposing affidavit, the appellant asserted, that, it had done its best to carry out its obligations under the difficult economic conditions prevailing in Zimbabwe, and that it was on course to completing its obligations.

It further stated, that, although there were no tarred roads in Phases 1 and 2, it had acquired state of the art equipment in order to carry out this task.

The appellant further stated, that, the roads had not been tarred because of the scarcity of diesel and unavailability of tar in Zimbabwe.

However, the appellant also stated, that, the road network in Phase 1 had been done satisfactorily by a Chinese sub-contractor.

The appellant further remarked, that, no drainage system had been put in place because the tarring of the roads had to be completed first. Culverts too were to be constructed after the roads had been tarred. The drainage was not as bad as suggested by the first respondent.

The appellant also stated, that, water mains had been installed and what remained was for the individual Stand holders to apply for connections.

As regards street lighting, the appellant submitted, that, this could only be attended to once the roads had been tarred.

Lastly, the appellant remarked, that, it had not deliberately avoided fully servicing the area but had been constrained by factors beyond its control, and, that, if given three months, it would ensure that the roads are completed.

In its opposing papers, the second respondent highlighted the fact that the appellant had not successfully completed Phase 1, and, therefore, should not have embarked on Phases 2 and 3 of the development project.

In determining that the appellant was in breach of its contractual obligations, the court a quo remarked, at page 6 of the cyclostyled judgment:

“It was quite apparent, from the papers before me, that the first respondent was indeed in breach of the terms of his contract in regard to Phase One of the development.

The applicant, through its members, has complied with their part of the contract and paid for the Stands in full. In my view, they may properly seek an order for specific performance.

In its opposition, the first respondent argued that the court should not exercise its discretion in favour of the applicant as the obligation was too onerous for it to perform. The excuses made by the first respondent, relating to unavailability of diesel and tar, were, in my view, merely an excuse as the applicant could carry out its obligations if it was diligent in its efforts. Whilst the court takes judicial notice of the socio-economic hardships complained of, it also notes that other successful developments have continued in spite of these challenges.

The second issue raised by the first respondent was that there was no timeframe for performance in the permit and they were therefore still in the process of completing the task.

This, in my view, was no defence to the order sought by the applicants.

Whilst it is noted that the permit does not indeed give a time frame within which the infrastructural development must be carried out, it is an implied term of the contract that performance must be conducted within a reasonable time.

In reading an implied term into a contract, the court must of course be bound by the principles set out in case law: see Mullin (Pvt) Ltd v Benade Ltd 1952 (1) SA 211.

The applicants in this case entered into the contracts with the first respondent in 1998. This application was filed on 22 June 2005. Clearly, the time lapse between the time of entering into the contract and time for performance exceeds, by any stretch of the imagination, the definition of a reasonable time.

In my view, a period in excess of six years is no longer a reasonable time - even in these challenging times.”

On the facts of this case, I am in no doubt that the court a quo was correct in determining the dispute on the papers.

The appellant had obligations which it had failed to discharge - even at the time of the hearing of the matter before the High Court in November 2006. The second respondent had still not issued the appellant with a Certificate of Compliance.

The appellant does not dispute, in its papers, that it had not discharged all its obligations in terms of the permit. Instead, the appellant states that it did the best in the prevailing socio economic situation and that it was on course to discharging its obligations under the contract.

The second respondent, in its papers, states that the servicing of Phase 1 had not been completed.

The remark by the appellant, that the drainage is not as bad as portrayed, is an admission that the work was not complete. Indeed, the appellant admitted that work was still to be done in tarring the roads, constructing a drainage system, and providing amenities.

The dispute, on the facts, could be resolved without hearing evidence. The position is now well established that:

“In motion proceedings, a court should endeavour to resolve the dispute raised in affidavits without the hearing of evidence. It must take a robust and common sense approach and not an over fastidious one; always provided that it is convinced that there is no real possibility of any resolution doing an injustice to the other party concerned.”

See Zimbabwe Bonded Fibreglass (Pvt) Ltd v Peech 1987 (2) ZLR 338 (SC)…,.

I agree with the submission by the respondent that the dispute was not so much on the substance but rather on the extent of non-compliance. I find no basis upon which the approach taken by the court a quo can be impugned.

The appeal is without merit. It is accordingly dismissed with costs.

Specific Performance re: Time of Performance iro Debtors Mora, Mora Ex Re, Mora Ex Persona, Interpellatio & Time of Essence


This is an appeal against the judgment of the High Court directing the appellant to fully service residential stands in Phase 1 of the Knowe Housing Development in Norton.

The facts of this case are these:

The appellant, a private company, is a property developer whilst the respondent is an association of residents of the Knowe Housing Development, who, in 1998, entered into agreements of sale with the appellant in their individual capacities for the purchase of residential Stands.

The association was formed by the residents in order to compel the appellant to carry out its obligations in terms of the various contracts it had entered into with the various individuals who form the association.

The High Court found that the appellant had breached the terms of agreement between itself and the residents in regard to Phase 1 of the development. Consequently, the court granted an order directing the appellant to fully service Phase 1 of the housing development within 90 days, and, in particular, to connect to all Stands reticulated water, sanitary systems, tarred roads, and a proper drainage system.

Dissatisfied with that order, the appellant appealed to this Court on the grounds that:

(a) The court a quo had erred in finding that the respondent had locus standi in judicio to institute the proceedings; and

(b) The court a quo had erred in rejecting the appellant's contention that it had complied with its obligations in terms of the relevant Development Permit.

At the hearing of the matter before this Court, counsel for the appellant abandoned the other grounds of appeal and attacked the judgment of the court a quo on the sole basis that there were material disputes of facts which were incapable of resolution on the papers, and, for that reason, the matter should either have been referred to trial or dismissed.

The sole issue for determination before this Court, therefore, is whether the court a quo erred in resolving the disputes raised on the papers without hearing evidence.

In terms of condition 27 of the Development Permit issued to the appellant by the second respondent, the appellant was obliged, at his own expense, to: “provide all infrastructural services viz roads, electricity, water mains, and sewerage disposal, to the specification approved by and to the satisfaction of Norton Town Council and all such services shall be handed over to Council at a date to be agreed upon by the two parties involved.”

In its founding papers before the High Court, the first respondent alleged that the appellant had breached the contract in various respects.

The first respondent alleged that although the appellant had tarred the roads in Phase 1, it had done so in a substandard manner; that no proper drainage system had been constructed; and tapped water was not available at all the Stands. The first respondent further alleged that no street lighting had been put in place and social amenities, such as schools and clinics, were still to be constructed.

In its opposing affidavit, the appellant asserted, that, it had done its best to carry out its obligations under the difficult economic conditions prevailing in Zimbabwe, and that it was on course to completing its obligations.

It further stated, that, although there were no tarred roads in Phases 1 and 2, it had acquired state of the art equipment in order to carry out this task.

The appellant further stated, that, the roads had not been tarred because of the scarcity of diesel and unavailability of tar in Zimbabwe.

However, the appellant also stated, that, the road network in Phase 1 had been done satisfactorily by a Chinese sub-contractor.

The appellant further remarked, that, no drainage system had been put in place because the tarring of the roads had to be completed first. Culverts too were to be constructed after the roads had been tarred. The drainage was not as bad as suggested by the first respondent.

The appellant also stated, that, water mains had been installed and what remained was for the individual Stand holders to apply for connections.

As regards street lighting, the appellant submitted, that, this could only be attended to once the roads had been tarred.

Lastly, the appellant remarked, that, it had not deliberately avoided fully servicing the area but had been constrained by factors beyond its control, and, that, if given three months, it would ensure that the roads are completed.

In its opposing papers, the second respondent highlighted the fact that the appellant had not successfully completed Phase 1, and, therefore, should not have embarked on Phases 2 and 3 of the development project.

In determining that the appellant was in breach of its contractual obligations, the court a quo remarked, at page 6 of the cyclostyled judgment:

“It was quite apparent, from the papers before me, that the first respondent was indeed in breach of the terms of his contract in regard to Phase One of the development.

The applicant, through its members, has complied with their part of the contract and paid for the Stands in full. In my view, they may properly seek an order for specific performance.

In its opposition, the first respondent argued that the court should not exercise its discretion in favour of the applicant as the obligation was too onerous for it to perform. The excuses made by the first respondent, relating to unavailability of diesel and tar, were, in my view, merely an excuse as the applicant could carry out its obligations if it was diligent in its efforts. Whilst the court takes judicial notice of the socio-economic hardships complained of, it also notes that other successful developments have continued in spite of these challenges.

The second issue raised by the first respondent was that there was no timeframe for performance in the permit and they were therefore still in the process of completing the task.

This, in my view, was no defence to the order sought by the applicants.

Whilst it is noted that the permit does not indeed give a time frame within which the infrastructural development must be carried out, it is an implied term of the contract that performance must be conducted within a reasonable time.

In reading an implied term into a contract, the court must of course be bound by the principles set out in case law: see Mullin (Pvt) Ltd v Benade Ltd 1952 (1) SA 211.

The applicants in this case entered into the contracts with the first respondent in 1998. This application was filed on 22 June 2005. Clearly, the time lapse between the time of entering into the contract and time for performance exceeds, by any stretch of the imagination, the definition of a reasonable time.

In my view, a period in excess of six years is no longer a reasonable time - even in these challenging times.”

On the facts of this case, I am in no doubt that the court a quo was correct in determining the dispute on the papers.

The appellant had obligations which it had failed to discharge - even at the time of the hearing of the matter before the High Court in November 2006. The second respondent had still not issued the appellant with a Certificate of Compliance.

The appellant does not dispute, in its papers, that it had not discharged all its obligations in terms of the permit. Instead, the appellant states that it did the best in the prevailing socio economic situation and that it was on course to discharging its obligations under the contract.

The second respondent, in its papers, states that the servicing of Phase 1 had not been completed.

The remark by the appellant, that the drainage is not as bad as portrayed, is an admission that the work was not complete. Indeed, the appellant admitted that work was still to be done in tarring the roads, constructing a drainage system, and providing amenities.

The dispute, on the facts, could be resolved without hearing evidence. The position is now well established that:

“In motion proceedings, a court should endeavour to resolve the dispute raised in affidavits without the hearing of evidence. It must take a robust and common sense approach and not an over fastidious one; always provided that it is convinced that there is no real possibility of any resolution doing an injustice to the other party concerned.”

See Zimbabwe Bonded Fibreglass (Pvt) Ltd v Peech 1987 (2) ZLR 338 (SC)…,.

I agree with the submission by the respondent that the dispute was not so much on the substance but rather on the extent of non-compliance. I find no basis upon which the approach taken by the court a quo can be impugned.

The appeal is without merit. It is accordingly dismissed with costs.

Intent or Animus Contrahendi re: Deemed, Implied, Tacit, Unsigned Agreements or Informal Contracts


This is an appeal against the judgment of the High Court directing the appellant to fully service residential stands in Phase 1 of the Knowe Housing Development in Norton.

The facts of this case are these:

The appellant, a private company, is a property developer whilst the respondent is an association of residents of the Knowe Housing Development, who, in 1998, entered into agreements of sale with the appellant in their individual capacities for the purchase of residential Stands.

The association was formed by the residents in order to compel the appellant to carry out its obligations in terms of the various contracts it had entered into with the various individuals who form the association.

The High Court found that the appellant had breached the terms of agreement between itself and the residents in regard to Phase 1 of the development. Consequently, the court granted an order directing the appellant to fully service Phase 1 of the housing development within 90 days, and, in particular, to connect to all Stands reticulated water, sanitary systems, tarred roads, and a proper drainage system.

Dissatisfied with that order, the appellant appealed to this Court on the grounds that:

(a) The court a quo had erred in finding that the respondent had locus standi in judicio to institute the proceedings; and

(b) The court a quo had erred in rejecting the appellant's contention that it had complied with its obligations in terms of the relevant Development Permit.

At the hearing of the matter before this Court, counsel for the appellant abandoned the other grounds of appeal and attacked the judgment of the court a quo on the sole basis that there were material disputes of facts which were incapable of resolution on the papers, and, for that reason, the matter should either have been referred to trial or dismissed.

The sole issue for determination before this Court, therefore, is whether the court a quo erred in resolving the disputes raised on the papers without hearing evidence.

In terms of condition 27 of the Development Permit issued to the appellant by the second respondent, the appellant was obliged, at his own expense, to: “provide all infrastructural services viz roads, electricity, water mains, and sewerage disposal, to the specification approved by and to the satisfaction of Norton Town Council and all such services shall be handed over to Council at a date to be agreed upon by the two parties involved.”

In its founding papers before the High Court, the first respondent alleged that the appellant had breached the contract in various respects.

The first respondent alleged that although the appellant had tarred the roads in Phase 1, it had done so in a substandard manner; that no proper drainage system had been constructed; and tapped water was not available at all the Stands. The first respondent further alleged that no street lighting had been put in place and social amenities, such as schools and clinics, were still to be constructed.

In its opposing affidavit, the appellant asserted, that, it had done its best to carry out its obligations under the difficult economic conditions prevailing in Zimbabwe, and that it was on course to completing its obligations.

It further stated, that, although there were no tarred roads in Phases 1 and 2, it had acquired state of the art equipment in order to carry out this task.

The appellant further stated, that, the roads had not been tarred because of the scarcity of diesel and unavailability of tar in Zimbabwe.

However, the appellant also stated, that, the road network in Phase 1 had been done satisfactorily by a Chinese sub-contractor.

The appellant further remarked, that, no drainage system had been put in place because the tarring of the roads had to be completed first. Culverts too were to be constructed after the roads had been tarred. The drainage was not as bad as suggested by the first respondent.

The appellant also stated, that, water mains had been installed and what remained was for the individual Stand holders to apply for connections.

As regards street lighting, the appellant submitted, that, this could only be attended to once the roads had been tarred.

Lastly, the appellant remarked, that, it had not deliberately avoided fully servicing the area but had been constrained by factors beyond its control, and, that, if given three months, it would ensure that the roads are completed.

In its opposing papers, the second respondent highlighted the fact that the appellant had not successfully completed Phase 1, and, therefore, should not have embarked on Phases 2 and 3 of the development project.

In determining that the appellant was in breach of its contractual obligations, the court a quo remarked, at page 6 of the cyclostyled judgment:

“It was quite apparent, from the papers before me, that the first respondent was indeed in breach of the terms of his contract in regard to Phase One of the development.

The applicant, through its members, has complied with their part of the contract and paid for the Stands in full. In my view, they may properly seek an order for specific performance.

In its opposition, the first respondent argued that the court should not exercise its discretion in favour of the applicant as the obligation was too onerous for it to perform. The excuses made by the first respondent, relating to unavailability of diesel and tar, were, in my view, merely an excuse as the applicant could carry out its obligations if it was diligent in its efforts. Whilst the court takes judicial notice of the socio-economic hardships complained of, it also notes that other successful developments have continued in spite of these challenges.

The second issue raised by the first respondent was that there was no timeframe for performance in the permit and they were therefore still in the process of completing the task.

This, in my view, was no defence to the order sought by the applicants.

Whilst it is noted that the permit does not indeed give a time frame within which the infrastructural development must be carried out, it is an implied term of the contract that performance must be conducted within a reasonable time.

In reading an implied term into a contract, the court must of course be bound by the principles set out in case law: see Mullin (Pvt) Ltd v Benade Ltd 1952 (1) SA 211.

The applicants in this case entered into the contracts with the first respondent in 1998. This application was filed on 22 June 2005. Clearly, the time lapse between the time of entering into the contract and time for performance exceeds, by any stretch of the imagination, the definition of a reasonable time.

In my view, a period in excess of six years is no longer a reasonable time - even in these challenging times.”

On the facts of this case, I am in no doubt that the court a quo was correct in determining the dispute on the papers.

The appellant had obligations which it had failed to discharge - even at the time of the hearing of the matter before the High Court in November 2006. The second respondent had still not issued the appellant with a Certificate of Compliance.

The appellant does not dispute, in its papers, that it had not discharged all its obligations in terms of the permit. Instead, the appellant states that it did the best in the prevailing socio economic situation and that it was on course to discharging its obligations under the contract.

The second respondent, in its papers, states that the servicing of Phase 1 had not been completed.

The remark by the appellant, that the drainage is not as bad as portrayed, is an admission that the work was not complete. Indeed, the appellant admitted that work was still to be done in tarring the roads, constructing a drainage system, and providing amenities.

The dispute, on the facts, could be resolved without hearing evidence. The position is now well established that:

“In motion proceedings, a court should endeavour to resolve the dispute raised in affidavits without the hearing of evidence. It must take a robust and common sense approach and not an over fastidious one; always provided that it is convinced that there is no real possibility of any resolution doing an injustice to the other party concerned.”

See Zimbabwe Bonded Fibreglass (Pvt) Ltd v Peech 1987 (2) ZLR 338 (SC)…,.

I agree with the submission by the respondent that the dispute was not so much on the substance but rather on the extent of non-compliance. I find no basis upon which the approach taken by the court a quo can be impugned.

The appeal is without merit. It is accordingly dismissed with costs.

Appeal re: Findings of Fact or Exercise of Discretion Made by Lower Court iro Terminated or Complete Proceedings


This is an appeal against the judgment of the High Court directing the appellant to fully service residential stands in Phase 1 of the Knowe Housing Development in Norton.

The facts of this case are these:

The appellant, a private company, is a property developer whilst the respondent is an association of residents of the Knowe Housing Development, who, in 1998, entered into agreements of sale with the appellant in their individual capacities for the purchase of residential Stands.

The association was formed by the residents in order to compel the appellant to carry out its obligations in terms of the various contracts it had entered into with the various individuals who form the association.

The High Court found that the appellant had breached the terms of agreement between itself and the residents in regard to Phase 1 of the development. Consequently, the court granted an order directing the appellant to fully service Phase 1 of the housing development within 90 days, and, in particular, to connect to all Stands reticulated water, sanitary systems, tarred roads, and a proper drainage system.

Dissatisfied with that order, the appellant appealed to this Court on the grounds that:

(a) The court a quo had erred in finding that the respondent had locus standi in judicio to institute the proceedings; and

(b) The court a quo had erred in rejecting the appellant's contention that it had complied with its obligations in terms of the relevant Development Permit.

At the hearing of the matter before this Court, counsel for the appellant abandoned the other grounds of appeal and attacked the judgment of the court a quo on the sole basis that there were material disputes of facts which were incapable of resolution on the papers, and, for that reason, the matter should either have been referred to trial or dismissed.

The sole issue for determination before this Court, therefore, is whether the court a quo erred in resolving the disputes raised on the papers without hearing evidence.

In terms of condition 27 of the Development Permit issued to the appellant by the second respondent, the appellant was obliged, at his own expense, to: “provide all infrastructural services viz roads, electricity, water mains, and sewerage disposal, to the specification approved by and to the satisfaction of Norton Town Council and all such services shall be handed over to Council at a date to be agreed upon by the two parties involved.”

In its founding papers before the High Court, the first respondent alleged that the appellant had breached the contract in various respects.

The first respondent alleged that although the appellant had tarred the roads in Phase 1, it had done so in a substandard manner; that no proper drainage system had been constructed; and tapped water was not available at all the Stands. The first respondent further alleged that no street lighting had been put in place and social amenities, such as schools and clinics, were still to be constructed.

In its opposing affidavit, the appellant asserted, that, it had done its best to carry out its obligations under the difficult economic conditions prevailing in Zimbabwe, and that it was on course to completing its obligations.

It further stated, that, although there were no tarred roads in Phases 1 and 2, it had acquired state of the art equipment in order to carry out this task.

The appellant further stated, that, the roads had not been tarred because of the scarcity of diesel and unavailability of tar in Zimbabwe.

However, the appellant also stated, that, the road network in Phase 1 had been done satisfactorily by a Chinese sub-contractor.

The appellant further remarked, that, no drainage system had been put in place because the tarring of the roads had to be completed first. Culverts too were to be constructed after the roads had been tarred. The drainage was not as bad as suggested by the first respondent.

The appellant also stated, that, water mains had been installed and what remained was for the individual Stand holders to apply for connections.

As regards street lighting, the appellant submitted, that, this could only be attended to once the roads had been tarred.

Lastly, the appellant remarked, that, it had not deliberately avoided fully servicing the area but had been constrained by factors beyond its control, and, that, if given three months, it would ensure that the roads are completed.

In its opposing papers, the second respondent highlighted the fact that the appellant had not successfully completed Phase 1, and, therefore, should not have embarked on Phases 2 and 3 of the development project.

In determining that the appellant was in breach of its contractual obligations, the court a quo remarked, at page 6 of the cyclostyled judgment:

“It was quite apparent, from the papers before me, that the first respondent was indeed in breach of the terms of his contract in regard to Phase One of the development.

The applicant, through its members, has complied with their part of the contract and paid for the Stands in full. In my view, they may properly seek an order for specific performance.

In its opposition, the first respondent argued that the court should not exercise its discretion in favour of the applicant as the obligation was too onerous for it to perform. The excuses made by the first respondent, relating to unavailability of diesel and tar, were, in my view, merely an excuse as the applicant could carry out its obligations if it was diligent in its efforts. Whilst the court takes judicial notice of the socio-economic hardships complained of, it also notes that other successful developments have continued in spite of these challenges.

The second issue raised by the first respondent was that there was no timeframe for performance in the permit and they were therefore still in the process of completing the task.

This, in my view, was no defence to the order sought by the applicants.

Whilst it is noted that the permit does not indeed give a time frame within which the infrastructural development must be carried out, it is an implied term of the contract that performance must be conducted within a reasonable time.

In reading an implied term into a contract, the court must of course be bound by the principles set out in case law: see Mullin (Pvt) Ltd v Benade Ltd 1952 (1) SA 211.

The applicants in this case entered into the contracts with the first respondent in 1998. This application was filed on 22 June 2005. Clearly, the time lapse between the time of entering into the contract and time for performance exceeds, by any stretch of the imagination, the definition of a reasonable time.

In my view, a period in excess of six years is no longer a reasonable time - even in these challenging times.”

On the facts of this case, I am in no doubt that the court a quo was correct in determining the dispute on the papers.

The appellant had obligations which it had failed to discharge - even at the time of the hearing of the matter before the High Court in November 2006. The second respondent had still not issued the appellant with a Certificate of Compliance.

The appellant does not dispute, in its papers, that it had not discharged all its obligations in terms of the permit. Instead, the appellant states that it did the best in the prevailing socio economic situation and that it was on course to discharging its obligations under the contract.

The second respondent, in its papers, states that the servicing of Phase 1 had not been completed.

The remark by the appellant, that the drainage is not as bad as portrayed, is an admission that the work was not complete. Indeed, the appellant admitted that work was still to be done in tarring the roads, constructing a drainage system, and providing amenities.

The dispute, on the facts, could be resolved without hearing evidence. The position is now well established that:

“In motion proceedings, a court should endeavour to resolve the dispute raised in affidavits without the hearing of evidence. It must take a robust and common sense approach and not an over fastidious one; always provided that it is convinced that there is no real possibility of any resolution doing an injustice to the other party concerned.”

See Zimbabwe Bonded Fibreglass (Pvt) Ltd v Peech 1987 (2) ZLR 338 (SC)…,.

I agree with the submission by the respondent that the dispute was not so much on the substance but rather on the extent of non-compliance. I find no basis upon which the approach taken by the court a quo can be impugned.

The appeal is without merit. It is accordingly dismissed with costs.

GARWE JA: This is an appeal against the judgment of the High Court directing the appellant to fully service residential stands in Phase 1 of the Knowe Housing Development in Norton.

The facts of this case are these.

The appellant, a private company, is a property developer whilst the respondent is an association of residents of the Knowe Housing Development who in 1998 entered into agreements of sale with the appellant in their individual capacities for the purchase of residential stands.

The association was formed by the residents in order to compel the appellant to carry out its obligations in terms of the various contracts it had entered into with the various individuals who form the association.

The High Court found that the appellant had breached the terms of agreement between itself and the residents in regard to Phase 1 of the development. Consequently the court granted an order directing the appellant to fully service phase 1 of the Housing Development within 90 days and in particular to connect to all stands reticulated water, sanitary systems, tarred roads and a proper drainage system.

Dissatisfied with that order, the appellant appealed to this Court on the grounds that:

(a) the court a quo had erred in finding that the respondent had locus standi in judicio to institute the proceedings; and

(b) the court a quo had erred in rejecting the appellant's contention that it had complied with its obligations in terms of the relevant development permit.

At the hearing of the matter before this Court Mr Mazonde for the appellant abandoned the other grounds of appeal and attacked the judgment of the court a quo on the sole basis that there were material disputes of facts which were incapable of resolution on the papers and for that reason the matter should either have been referred to trial or dismissed.

The sole issue for determination before this Court therefore is whether the court a quo erred in resolving the disputes raised on the papers without hearing evidence.

In terms of condition 27 of the development permit issued to the appellant by the second respondent, the appellant was obliged at his own expense to: “provide all infrastructural services viz roads, electricity, water mains and sewerage disposal, to the specification approved by and to the satisfaction of Norton Town Council and all such services shall be handed over to council at a date to be agreed upon by the two parties involved.”

In its founding papers before the High court the first respondent alleged that the appellant had breached the contract in various respects.

The first respondent alleged that although the appellant had tarred the roads in phase 1 it had done so in a substandard manner, that no proper drainage system had been constructed and tapped water was not available at all the stands. The first respondent further alleged that no street lighting had been put in place and social amenities such as schools and clinics were still to be constructed.

In its opposing affidavit the appellant asserted that it had done its best to carry out its obligations under the difficult economic conditions prevailing in Zimbabwe and that it was on course to completing its obligations.

It further stated that although there were no tarred roads in phases 1 and 2, it had acquired state of the art equipment in order to carry out this task.

The appellant further stated that the roads had not been tarred because of the scarcity of diesel and unavailability of tar in Zimbabwe.

However the appellant also stated that the road network in phase 1 had been done satisfactorily by a Chinese Sub-contractor.

The appellant further remarked that no drainage system had been put in place because the tarring of the roads had to be completed first. Culverts too were to be constructed after the roads had been tarred. The drainage was not as bad as suggested by the first respondent.

The appellant also stated that water mains had been installed and what remained was for the individual stand holders to apply for connections.

As regards street lighting the appellant submitted that this could only be attended to once the roads had been tarred.

Lastly the appellant remarked that it had not deliberately avoided fully servicing the area but had been constrained by factors beyond its control and that if given three months it would ensure that the roads are completed.

In its opposing papers the second respondent highlighted the fact that the appellant had not successfully completed phase 1 and therefore should not have embarked on phases 2 and 3 of the development project.

In determining that the appellant was in breach of its contractual obligations the court a quo remarked at page 6 of the cyclostyled judgment:

It was quite apparent from the papers before me that the first respondent was indeed in breach of the terms of his contract in regard to phase one of the development. The applicant through its members has complied with their part of the contract and paid for the stands in full. In my view they may properly seek an order for specific performance. In its opposition the first respondent argued that the court should not exercise its discretion in favour of the applicant as the obligation was too onerous for it to perform. The excuses made by the first respondent relating to unavailability of diesel and tar were in my view merely an excuse as the applicant could carry out its obligations if it was diligent in its efforts. Whilst the court takes judicial notice of the socio-economic hardships complained of it also notes that other successful developments have continued in spite of these challenges.

The second issue raised by the first respondent was that there was no time frame for performance in the permit and they were therefore still in the process of completing the task.

This in my view was no defence to the order sought by the applicants.

Whilst it is noted that the permit does not indeed give a time frame within which the infrastructural development must be carried out, it is an implied term of the contract that performance must be conducted within a reasonable time.

In reading an implied term into a contract the court must of course be bound by the principles set out in case law. (See Mullin (Pvt) Ltd v Benade Ltd 1952 (1) SA 211).

The applicants in this case entered into the contracts with the first respondent in 1998. This application was filed on 22 June 2005. Clearly the time lapse between the time of entering into the contract and time for performance exceeds by any stretch of the imagination the definition of a reasonable time.

In my view a period in excess of six years is no longer a reasonable time even in these challenging times.”

On the facts of this case, I am in no doubt that the court a quo was correct in determining the disputes on the papers.

The appellant had obligations which it had failed to discharge even at the time of the hearing of the matter before the High Court in November 2006. The second respondent had still not issued the appellant with a certificate of compliance.

The appellant does not dispute in its papers that it had not discharged all its obligations in terms of the permit. Instead the appellant states that it did the best in the prevailing socioeconomic situation and that it was on course to discharging its obligations under the contract.

The second respondent in its papers states that the servicing of phase 1 had not been completed.

The remark by the appellant that the drainage is not as bad as portrayed is an admission that the work was not complete. Indeed the appellant admitted that work was still to be done in tarring the roads, constructing a drainage system and providing amenities.

The dispute on the facts could be resolved without hearing evidence. The position is now well established that:

in motion proceedings a court should endeavour to resolve the dispute raised in affidavits without the hearing of evidence. It must take a robust and common sense approach and not an over fastidious one; always provided that it is convinced that there is no real possibility of any resolution doing an injustice to the other party concerned.”

See Zimbabwe Bonded Fibreglass (Pvt) Ltd v Peech 1987 (2) ZLR 338 (SC) at 339 C-D.

I agree with the submission by the respondent that the dispute was not so much on the substance but rather on the extent of non-compliance. I find no basis upon which the approach taken by the court a quo can be impugned.

The appeal is without merit. It is accordingly dismissed with costs.

SANDURA JA: I agree

ZIYAMBI JA: I agree









Scanlen & Holderness, appellant's legal practitioners

Lofty & Fraser, first respondent's legal practitioners

Muskwe & Associates, second respondent's legal practitioners

Back Main menu

Categories

Back to top