MATHONSI
JA:
This
is an appeal against the whole judgment of the High Court handed down
on 26 October 2016 dismissing the appellant's application for
specific performance with costs.
The
facts are that the appellant and the second respondent are each the
holders of fifty percent of the issued share capital in the third
respondent, a special joint venture company incorporated in terms of
a joint venture agreement entered into between the appellant and the
second respondent on 21 July 2009.
In
terms of the joint venture agreement the appellant would provide
funding for the business of mining diamonds through the third
respondent. The second respondent undertook to ensure that the mining
rights held under special grants at Marange existed in perpetuity.
The
first respondent, which is the sole shareholder in the second
respondent guaranteed the second respondent's performance of its
obligations under the agreement.
Although
the appellant performed its obligations under the agreement, the
second respondent did not pay the special grants' renewal fees. The
second respondent let the special grants in terms of which the mining
rights existed, expire.
When
that happened, the second respondent did not secure the reinstatement
of the special grants. The first respondent, which had guaranteed the
second respondent's performance of its contractual obligations,
also failed to do anything about that breach of the agreement.
On
30 September 2015, the first respondent addressed a letter to the
Permanent Secretary for Mines and Mining Development which, because
of its centrality in the resolution of this case, is reproduced
hereunder:
“RE:
RENEWAL OF THE MARANGE DIAMOND SPECIAL GRANTS: 4718, 4719, 4720,
4765, 5244, 5247, 5249 & 5769
Reference
is made to the above matter. As per attached table below, ZMDC has
five diamond Special Grants (SG) which expired in October 2013 and
one in December 2010. These are SG Nos. 4718, 4719, 4720, 4765 and
5769.
From
this date the Corporation has to raise the required renewal fees and
in 2014, the Ministry of Mines and Mining Development granted a 12
month exemption on the payment of the renewal fees for the said
grants. Given the fact that ZMDC's financial position has remained
severely constrained, the Corporation is applying for a further
exemption on renewal fees for these SGs, which have currently
expired.
Further,
given the fact that actual mining is now taking place in the first
four of the above SGs, it is necessary for the SGs to be converted
from prospecting to mining SGs, a process that also requires cash
outlay by ZMDC, which funds the Corporation is currently finding
difficult to raise.
In
addition, Marange Resources (Pvt) Ltd, a wholly owned subsidiary of
ZMDC, which is currently mining on Block B under SG4720, has
requested for a valid copy of SG4720, which it requires in its
application for exemption of import duty for an X-Ray Transmography
Machine (XRT machine) that it intends to import. Unfortunately the
Corporation is not able to assist, given the fact that the SG has
expired.
Under
these circumstances therefore, the Corporation is appealing to the
Ministry, for the Ministry to reconsider its earlier position not to
extend the exemption of payment of renewal SG fees, and grant ZMDC an
exemption to update its diamond SGs for a further period of 3 years
to 2016, to allow Marange Resources to process its application for
exemption of import duty.
Sir,
we are kindly requesting for your favourable consideration to our
submission of renewal of the ZMDC held diamond Special Grants Nos
4718, 4719, 4720, 4765, 5244, 5247, 5249 & 5769 and conversion of
SGs Nos. 4718, 4719, 4720 from prospecting to mining.
Yours
faithfully
S.
Simango General Manager.” (The underlining is mine)
It
is clear from the contents of the letter that the special grants, in
terms of which mining operations were to be carried out by the third
respondent, had expired in 2010 and 2013.
The
respondents did not have money to pay renewal fees and were thus
asking for exemptions from the Secretary. They had relied on
exemptions previously to renew the special grants because they again
did not have money. If they were to be granted exemptions from paying
renewal fees, only then would they apply for renewal or revival of
the expired special grants.
The
Secretary of Mines and Mining Development was not impressed. He
rejected the request for exemptions in a letter to the first
respondent dated 22 February 2016. It reads:
“RE:
RENEWAL OF THE MARANGE DIAMOND SPECIAL GRANTS: 4718, 4719, 4720,
4765, 5244, 5247, 5249 AND 5769
The
above matter refers.
We
acknowledge receipt of your letter to our Ministry dated 30 September
2015 contents of which have been noted (copy attached for ease of
reference). As clearly admitted and indicated by yourselves, you have
neglected or failed to renew the Special Grants that were issued to
you, some expired as far back as 2010 and others in 2013. An
exemption had been extended to you but there has been no commitment
on your part to rectify this anomaly which is in contravention of
section 293 of the Mines and Minerals Act [Chapter
21:05].
Instead
you are requesting for a further exemption.
It
has also come to our attention that there are some Special Grants
that are purported not to have a duration period.
It
is trite law that a Special Grant is issued upon application and its
issuance is done in terms of section 291 of the Mines and Minerals
Act [Chapter 21:05] which demands that, a period for the subsistence
of the Special Grant shall be specified failure of which renders the
Special Grant void. In light of this, these Special Grants shall be
deemed to have been granted for the period which the applicant had
requested in its application.
After
serious consideration of this matter, we do hereby notify you that
the Ministry is not in a position to give any further exemptions for
the renewal of all Special Grants namely 4718, 4719, 4720, 4765,
5244, 5247, 5249 and 5769 that were issued to you and neither are we
renewing the same.
Prof.
P.F. Gudyanga
Secretary
for Mines and Mining Development.” (The underlining is mine)
After
the rejection of the request for exemptions, it is common cause that
the respondents did not do anything. They did not challenge the
Secretary's decision. Neither did they raise money to pay for the
renewal or revival of the expired Special Grants.
The
appellant then launched an application in the High Court seeking
an order directing the respondents to pay renewal fees for the
Special Grants and to file renewal applications among other ancillary
relief. The application was prompted by the third respondent's
inability to carry out mining operations without regularisation of
the special mining grants. The application was premised on the
respondents' breach of the joint venture agreement.
The
first and second respondents opposed the application.
They
denied breaching the agreement asserting that they applied for both
exemption to pay renewal fees and the renewal of the Special grants
to the Secretary for Mines.
It
therefore became an issue for determination by the court a quo
whether the first and second respondents breached the terms of the
joint venture agreement by failing to perform specific acts in
pursuance of their contractual obligations.
The
court a quo held that the first respondent's letter of 30 September
2015 is indeed an application for renewal of the Special Grants. The
court a quo found that the response to the application by the
Secretary for Mines dealt with the issues of exemption and renewal of
the Special Grants which had expired. The court a quo held that the
Secretary for Mines had made a decision not to renew the Special
Grants. It would therefore be incompetent, so the court a quo
reasoned, for the court to order the Secretary to review his own
decision by granting an order for specific
performance.
This
appeal is the fruit of the appellant's grief with that judgment of
the court a quo. The grounds of appeal are that:
1.
The court a quo erred and grossly misdirected itself in finding that
an application for renewal of the Special mining grants had been
filed by the first and second respondents in discharge of their
contractual obligations to the appellant;
2.
The court a quo erred and grossly misdirected itself in limiting the
first and second respondents' contractual obligations to filing an
application for renewal of the special mining grants whereas their
obligation was to do all that was necessary to ensure the existence
in perpetuity of the special mining rights.
Whether
or not the court a quo correctly held the letter of the first
respondent to the Secretary for Mines as an act of specific
performance in terms of the parties' agreement.
Generally
the policy of the law is to give effect to the contracts of the
parties because it is salutary in our jurisdiction to uphold the
freedom of the parties to contract lawfully. This notion is embodied
in the principle of sanctity of contract.
Once
the parties have contracted, it is not open to the courts to rewrite
the contract they have entered into. In addition, the court will not
excuse any of the parties from the consequences of the contract that
they freely and voluntarily entered into with their eyes wide open.
This is so even if the consequences are onerous or oppressive. See
Magodora & Ors v Care International Zimbabwe 2014 (1) ZLR 397 (S)
at 403 C-D.
As
to the remedy of specific performance in the law of contract, it is
accepted that it is aimed at upholding the contract and obtaining the
performance of the terms of the contract as agreed. Indeed, specific
performance is the primary or default remedy for breach of contract
and is usually claimable.
According
to the learned author I Maja, The Law of Contract in Zimbabwe, 2015,
The Maja Foundation, at p126:
“The
general rule under Roman Dutch Law is that an innocent party has a
right – in every case of breach of contract – to a remedy of
specific performance unless there are exceptional circumstances which
justify refusal of an order for specific performance.
According
to Farmers Co-operative Society (Reg) v Berry 1912 AD 343 at 350:
'Prima
facie, every party to a binding agreement who is ready to carry out
his own obligation under it has a right to demand from the other
party, so far as it is possible, a performance of his undertaking in
terms of the contract. As remarked by KOTZE CJ in Thompson v
Pullinger the right of the plaintiff to the specific performance of a
contract where the defendant is in a position to do so is beyond all
doubt.'”
See
also Smith & Ors v ZESA 2003 (1) ZLR 158 (H) at p165 A-B; Savanhu
v Marere N.O. & Ors 2009 (1) ZLR 320 (S).
However,
the right to claim specific performance is predicated on the concept
that the party claiming it must first show that he or she has
performed all his or her obligations under the contract or is ready,
willing and able to perform his or her side of the bargain.
Even
then, the court has a discretion, which should be exercised
judicially, to grant or refuse a decree of specific performance. It
follows therefore that the court's discretion should not be
exercised arbitrarily or capriciously. See Minister of Public
Construction & National Housing v Zescon (Pvt) Ltd 1989 (2) ZLR
311 (S), where at 318 G, this Court stated:
“The
law is clear. This is a remedy to which a party is entitled as of
right. It cannot be withheld arbitrarily or capriciously.”
It
is important to consider the specific terms of the contract entered
into between the parties which the appellant wishes to enforce.
Clause
6.3 of the Joint Venture Agreement provides:
“6.3
Marange undertakes that it shall forthwith after the signature date
and thereafter for the duration of this Agreement –
6.3.1
pay all necessary fees and make application for the renewal and/or
continued existence and do all that may be necessary so as to ensure
that the special grants and rights thereunder are in good standing
and remain valid for the duration of this Agreement allowing Marange
to mine and prospect the concession area in perpetuity ……”
The
appellant's case is that the respondents breached that provision by
failing to pay the necessary fees and to make the requisite
application for the renewal of the Special Grants. As a result the
Special Grants lapsed.
The
respondents submitted that the letter written by the first respondent
to the Secretary of Mines on 30 September 2015 constituted a valid
application for the renewal of the Special Grants which application
was rejected by the Secretary for Mines. They therefore fulfilled
their part of the bargain.
It
is common cause that the appellant fulfilled its own obligations in
terms of the contract and was therefore entitled to demand specific
performance. The court a quo found that the letter of 30 September
2015 was “an application for renewal” and that its heading was
very clear needing no further explanation. The court said at p7 of
the cyclostyled judgment:
“What
is clear from the above is that it is an application for renewal. The
heading is very clear and needs no further explanation. The first
paragraph makes reference to the heading and therefore the renewal of
the special grants.
The
second paragraph relates to an exemption to pay renewal fees.
Paragraphs 3 and 4 are not relevant to the determination of the issue
at hand. Paragraph 4, again, relates to exemptions. The last
paragraph puts paid to any doubt what the letter relates to. It talks
about renewal.
I
agree with Mr Tsivama that there is no procedure or format laid down
in JVA as to how the application for renewal is to be submitted.”
With
respect, the court a quo took a very simplistic, if not pedestrian,
approach to the letter in question.
Clause
6.3.1 of the Joint Venture Agreement required the respondents first
and foremost, to pay all necessary fees for the renewal of the
special grants. It also required them to make the necessary
application for such renewal. It recognised the reality that the
payment of fees was a pre-requisite for a valid and successful
application for renewal. Such a situation is not what was obtaining
on the ground and as such the letter of 30 September 2015 cannot, by
any stretch of the imagination, be regarded as a fulfilment of the
respondents' obligations under Clause 6.3.1 of the Joint Venture
Agreement.
Clearly
it was not a valid or competent application for renewal.
It
is clear from the provisions of section
293 of the Mines and Minerals Act [Chapter 21:05] that the payment of
renewal fees is central to the validity of an application for
renewal. Section 293 provides:
“The
person to whom a special grant is issued shall pay the prescribed fee
in respect of the issue of a special grant or any renewal thereof.”
It
is common cause that the respondents did not pay renewal fees. In
fact all the relevant special grants were allowed to expire years
before the letter of 30 September 2015 was written. The contents of
that letter are clear that the first respondent was seeking an
exemption from paying renewal fees because of an incongruent
financial position. Without the payment of renewal fees the renewal
could only be done by the benevolence of the Secretary.
The
respondents could not possibly be said to have performed their
obligations of ensuring the mining rights existed in perpetuity. The
rights had expired.
The
court a quo fell into error in that aspect. The letter of 30
September 2015 did not constitute specific performance of the
respondents' obligations in terms of the contract.
Whether
the respondents did all that was necessary to ensure the Special
Mining rights existed in perpetuity
Mr
Magwaliba for the appellant submitted that the obligations of the
respondents set out in the contract were much broader than merely
submitting an application for renewal of the Special Grants. They
were required, so the argument goes, to ensure that the mining rights
existed in perpetuity. They failed to perform to such an extent that
the special grants expired in 2010 and 2013 long before the
respondents even submitted the letter they relied on.
I
agree.
In
fact once it is accepted that the respondents did not pay renewal
fees and that they allowed the grants to expire, it cannot be said at
the same time that the respondents did all that was necessary to
ensure the existence of the special mining rights in perpetuity. They
could only so exist if there was full compliance with renewal
requirements including the timeous payment of renewal fees and
submission of the necessary applications.
Repeated
requests for exemptions from payment would never ensure perpetuity as
that left everything in the hands of the Secretary for Mines.
Whether
the court should exercise its discretion in favour of granting
specific performance.
Mr
Tsivama for the respondents submitted that the Secretary for Mines
made a decision not to renew the Special Grants which decision is
contained in his letter of 22 February 2016 quoted above. He
submitted that the court a quo cannot be faulted for concluding that
it would be incompetent for the court to direct him to review his own
decision by granting specific performance.
Mr
Magwaliba on the other hand sharply differed with that assertion.
In
his view there was no application for renewal placed before the
Secretary for Mines. He could not grant an application which was not
made and his response clearly showed his disquiet about the
respondents' repeated failure to pay renewal fees.
I
have said that the court has a discretion whether to grant specific
performance but that discretion should be exercised judicially and
not arbitrarily or capriciously. This is because specific performance
is a remedy to which a party is entitled to as of right. See Minister
of Public Construction & National Housing v Zescon (Pvt) Ltd,
Supra.
The
court a quo did not consider the circumstances that are relevant in
deciding whether to grant a decree of specific performance or not. In
its view that was unnecessary because it had come to the conclusion
that the respondent's letter to the Secretary for Mines amounted to
specific performance. I therefore do not agree with Mr Tsivama that
the court a quo exercised judicial discretion and refused specific
performance, which discretion can only be interfered with if
exercised capriciously or upon a wrong principle.
The
discretion was simply not exercised by the court a quo for obvious
reasons, namely its finding that specific performance had occurred.
There
is no doubt that the Secretary for Mines was called upon to decide
whether or not to grant the respondents exemption from paying renewal
fees. He refused to do so because, according to him, an exemption had
been granted previously but the respondents showed no commitment to
rectify the anomalies. The respondents were not entitled to further
exemptions.
What
is significant to note is that the respondents' obligations in
terms of the contract are not to apply for exemptions but to pay
renewal fees.
It
is clear from the letter of the Secretary for Mines dated 22 February
2016 that if renewal fees are paid the application will be favourably
considered.
In
light of that I perceive no ground whatsoever for exercising the
discretion reposed upon the court against the granting of specific
performance. After all it is the primary remedy for breach of
contract. The appellant has shown that the respondents breached the
contract. Specific performance is possible and as such it should be
granted.
In
the result, it is ordered that:
1.
The appeal succeeds with costs.
2.
The judgment of the court a quo is set aside and substituted with the
following order:
“2.1.
The application be and is hereby granted.
2.2.
The 1st and 2nd respondents be and are hereby directed to pay renewal
fees in respect of the special grants constituting the concession on
which the 3rd respondent was carrying out mining operations and which
mining grants are referred to in the Joint Venture Agreement and the
Shareholders Agreement attached to the application.
2.3.
Thereafter the 1st and 2nd respondents be and are hereby directed to
file a renewal application in respect of the said special grants and
to provide the renewing statutory authority with all that is required
to enable the said authority to process the renewal application
including a detailed written motivation to ensure urgent renewal of
the special grants.
2.4.
The 1st and 2nd respondents shall provide the applicant with copies
of the renewal application together with proof of payment of fees.
2.5.
The 1st and 2nd respondents shall pay the costs of this application
jointly and severally the one paying the other to be absolved.
GWAUNZA
DCJ: I agree
MAVANGIRA
JA: I agree
Scanlen
& Holderness, legal practitioners for the appellant
Sawyer
& Mkushi, 1st and 2nd respondents' legal practitioners