Law Portal
Zimbabwe

Welcome To Law Portal

Welcome, Guest!
[Help?]

HH29-10 - PRODUTRADE (PVT) LTD vs CONTINENTAL BAKERIES (PVT) LTD and MUNYUKI ROBERT CHIKWAVIRA

  • View Judgment By Categories
  • View Full Judgment


Law of Contract-viz debt re judgment debt.
Law of Contract-viz debt re debt interest iro judgment interest.
Procedural Law-viz rules of evidence re documentary evidence.
Law of Contract-viz Deed of Settlement re the without prejudice principle.
Procedural Law-viz final orders re correction of a judgment iro Rule 449 of the High Court Rules.
Law of Contract-viz debt re debt interest iro the in duplum rule.
Procedural Law-viz case authorities re the doctrine of stare decisis.

Debt Interest re: In Duplum Rule

On 19 July 2006, the applicant obtained judgment in this Court in Case No. HC2433/2005 in the sum of $485,316,000=. The order provided for interest in the following terms:

Interest is due on the above amount at the prevailing overdraft interest rate as quoted by Stanbic Bank Limited.”

On 10 September 2007, the applicant filed the present application seeking the following relief:

1. That the applicant be and is hereby entitled to levy interest on the capital debt in Case No. HC1929/2005 from 4th February 2005 to date of payment.

2. Costs on the legal practitioner/client scale (sic).”

The material facts giving rise to this application are that the applicants issued summons on 22 April 2005 in case No. HC1929/05 claiming the sum of $485,316,000=, interest at the rate of 115% calculated from 4 February 2005 to the date of payment and costs on a higher scale. The claim arose from an agreement of sale between the applicant and the first respondent in terms of which the applicant was required to deliver flour to the value of $485,316,000= to the first respondent. The flour was duly delivered on 25 January 2005. The first respondent was obliged, under the agreement, to pay the purchase price for the flour by 4 February 2005. The second respondent bound himself as surety and co-principal debtor in respect of the first respondent's liability. The purchase price was not paid on the due date resulting in the claim.

The respondents defended the claim.

On 27 May 2005 the applicant filed an application for summary judgment in case No. HC2433/05. The judgment was duly granted in favour of the applicant on 19 July 2006. The respondent appealed against that judgment on 26 July 2006. However, on 22 March 2007, the respondents tendered payment of $970,632= being the judgment debt plus interest. In a letter dated 13 April 2007, the applicant accepted the payment on a without prejudice basis and reserved their right to claim interest accrued on the sum of $970,632=. Following the payment, the Notice of Appeal was withdrawn on 26 March 2007.

On 18 November 2007, the applicant then filed the present application claiming interest on the capital debt in case No. HC1929/2005 from 4 February to the date of payment.

Before the applicant addressed me on the merits of the application, I queried the nature of relief that the applicant sought and whether or not the applicant had, in view of the judgment in Case No 2433/05, adopted the proper procedure.

Counsel for the applicant submitted that the applicant was seeking a declarator that interest was due from 4 February 2005 to the date of payment. He submitted that the applicant was not seeking a variation of the order in Case No. HC2433/05.

Counsel for the respondent submitted that the matter, and, in particular, the question of interest, had already been adjudicated on in Case No. HC2433/05. He submitted that the applicant was seeking a variation of the order. The applicant could only do so in terms of Rule 449 of the High Court Rules. He further submitted that as the applicant had adopted the wrong procedure, the application should be dismissed with costs.

Despite counsel for the applicant's submissions, it appears to me that counsel for the respondent is correct in stating that the effect of the relief sought by the applicant is a correction of the order granted on 19 July 2006. The question of interest was indeed determined in HC2433/05 and an order was granted by this court. However, it appears to me that there was an apparent omission as to the date when interest was to commence running. The applicant had clearly stated in its prayer in the declaration the date from which interest would commence running. The order is therefore incomplete and inoperative. It is for this reason that I am of the view that I can proceed to determine the matter in terms of Rule 449(1)(b). The Rule provides that:

(1) The court or a judge may, in addition to any other power it or he may have, mero motu or upon the application of any party affected, correct, rescind, or vary any judgment or order —

(a) That was erroneously sought or erroneously granted in the absence of any party affected thereby; or

(b) In which there is an ambiguity or a patent error or omission, but only to the extent of such ambiguity, error or omission; or

(c) That was granted as the result of a mistake common to the parties”…,.

The court in HC2433/05 did not indicate, in the judgment, why the effective date when interest would run was not included. Had it so indicated, the matter would have been res judicata as contended by counsel for the respondent. It would have been difficult for this court to evoke its powers in terms of Rule 449. The silence in the judgment, and the order itself, appears to me to have been a clear omission.

The next issue for determination is whether or not it is competent for me to correct the order and provide, as requested by the applicant, that interest should have commenced to run from 4 February 2005 to date of payment despite the in duplum rule.

The applicant contended that the in duplum rule does not apply in the present case because proceedings had already been instituted and the delay was attributable to the justice delivery system. In support thereof, the applicant referred me to the case of Standard Bank of South Africa v Oneanate Investments (Pty) Ltd 1998 (1) SA 811 (SCA) and Ehlers v Standard Chartered Bank Zimbabwe Limited 2000 (1) ZLR 136 (H).

Counsel for the applicant contended that the effect of the order sought by the applicant is that interest continues to run until payment in full is made irrespective of the in duplum rule.

The respondent urged me to follow the case of CBZ Limited v MM Builders & Suppliers (Private) Limited & Ors 1996 (2) ZLR 420 (H) and Conforce (Pvt) Ltd v City of Harare 2000 (1) ZLR 445 (H).

The proposition that interest ceases to run when it has reached the capital amount and only commences to run afresh upon judgment is found in CBZ Limited v MM Builders & Suppliers (Private) Limited & Ors 1996 (2) ZLR 420 (H)…, where GILLESPIE J states that:

Upon judgment being given interest on the full amount of the judgment debt commences to run afresh but will once again cease to accrue when it waxes to the amount of the judgment debt, being the capital and interest thereon for which the cause of action was instituted.”

Therefore, the in duplum rule applies where the interest reaches the judgment debt.

It appears to me that the reasoning by MALABA J…, in Ehlers v Standard Chartered Bank Zimbabwe Limited 2000 (1) ZLR 136 (H) does not take into account the fact that the debtor is equally not in control of the process by which interest accumulates. At page 139G-140B he stated:-

The learned judges preferred the view that interest only commences to run anew as from the date of judgment. I must, with respect, express my dissent from the decision in Commercial Bank of Zimbabwe's case supra on the date on which interest commences to run afresh in a case where the in duplum rule applies. This view of the law does not give effect to the policy behind the in duplum rule, nor does it recognize the discretion enjoyed by the court in the matter. In Georgias & Anor v Standard Chartered Finance Zimbabwe Ltd 1998 (2) ZLR 488 (S) at 495D GUBBAY CJ said that the in duplum rule is based upon a public policy designed to protect borrowers from the exploitation of lenders by prohibiting usurious abuse. The principle that interest commences to run afresh from the date of litis contestatio, which, in this case, is the date of service of summons, is based upon the recognition of the fact that from that date the creditor ceases to be in control of the process by which interest accumulates.”

In the present case, the respondent cannot be held accountable for the delays caused by the legal system. It therefore should not be penalised for enforcing its own rights to defend an action particularly, in such a case where there is a divergence of views on the application of the in duplum rule. I do not believe that it would be in the public interest to penalise the debtor.

I am, however, persuaded by the remarks of CHINHENGO J in Conforce (Pvt) Ltd v City of Harare 2000 (1) ZLR 445 (H)…, which seems to reflect the true position regarding the application of the in duplum rule on a judgment debt. At page 458A-F he noted:-

I venture to say that the public interest served by the in duplum rule is not identified with sympathy for the debtor so as to protect him. I view the public interest involved as encompassing a wider spectrum of interests, from the protection of the debtor to securing fiscal discipline on the part of lenders to considerations of justification for charging interest in the first place i.e. to compensate the creditor for deprivation of use of the money due until payment (Mawere v Mukura 1997 (2) ZLR 361 (H) at 364G) and to the interests of commerce generally and perhaps many more interests.

Thus, the public interest cannot be restricted to one or two considerations i.e. the protection of the debtor and the dictates of modern commerce.

But, even if it were so restricted, I cannot see anything incompatible with the rule serving those interests if it were applied in the manner advocated for in MM Builders case. The creditor's claim for interest would be limited to an amount that does not exceed the capital. In my view, the danger in adopting the approach in Oneanate and Ehlers cases supra is that an unscrupulous creditor only has to institute action to defeat the in duplum rule. He may so act as to ensure that the institution of proceedings and the attainment of the double coincide with the result that the rule is rendered in-operative.

I do not see anything that is against the public interest, or the interest of modern finance, if the in duplum rule operates in the manner outlined by GILLESPIE J and the old Roman Dutch authorities which espouse the view that once the double has been reached, interest must stop to run regardless of the institution of proceedings or that the stage of litis contestatio has been reached. Where, in particular, the double has not been reached, I find no relevance at all of the event of institution of proceedings. Interest must continue to run until it equates to the capital amount soon after or long after the institution of proceedings, but that is immaterial. I am therefore un-persuaded by the conclusion reached on this point in Oneanate and Ehlers cases. I must respectfully express my dissent from those judgments.”

As rightly submitted by counsel for the respondent, the decision in Standard Bank of South Africa v Oneanate Investments (Pty) Ltd 1998 (1) SA 811 (SCA) is merely persuasive. The decision in CBZ Limited v MM Builders & Suppliers (Private) Limited & Ors 1996 (2) ZLR 420 (H) was decided by a full bench of the High Court and is therefore binding on me.

In the result, it is ordered that:

1. The application be and is hereby granted.

2. The order granted in HC1929/05, on 19 July 2006, be and is hereby amended by the deletion of paragraph 2 and substitution with:

Interest is due on the above amount at the prevailing overdraft interest rate as quoted by Stanbic Bank Limited with effect from 4th February 2005 to date of payment.”

3. The respondent shall pay the costs of the application.

Final Orders re: Composition of Bench iro Judicial Precedents, Effect of Ex Post Facto Statutes and Judicial Lag


The material facts giving rise to this application are that the applicants issued summons on 22 April 2005 in case No. HC1929/05 claiming the sum of $485,316,000=, interest at the rate of 115% calculated from 4 February 2005 to the date of payment and costs on a higher scale.

The claim arose from an agreement of sale between the applicant and the first respondent in terms of which the applicant was required to deliver flour to the value of $485,316,000= to the first respondent. The flour was duly delivered on 25 January 2005. The first respondent was obliged, under the agreement, to pay the purchase price for the flour by 4 February 2005. The second respondent bound himself as surety and co-principal debtor in respect of the first respondent's liability. The purchase price was not paid on the due date resulting in the claim.

The respondents defended the claim.

On 27 May 2005 the applicant filed an application for summary judgment in case No. HC2433/05. The judgment was duly granted in favour of the applicant on 19 July 2006. The respondent appealed against that judgment on 26 July 2006. However, on 22 March 2007, the respondents tendered payment of $970,632= being the judgment debt plus interest. In a letter dated 13 April 2007, the applicant accepted the payment on a without prejudice basis and reserved their right to claim interest accrued on the sum of $970,632=. Following the payment, the Notice of Appeal was withdrawn on 26 March 2007.

On 18 November 2007, the applicant then filed the present application claiming interest on the capital debt in case No. HC1929/2005 from 4 February to the date of payment….,.

The applicant contended that the in duplum rule does not apply in the present case because proceedings had already been instituted and the delay was attributable to the justice delivery system. In support thereof, the applicant referred me to the case of Standard Bank of South Africa v Oneanate Investments (Pty) Ltd 1998 (1) SA 811 (SCA) and Ehlers v Standard Chartered Bank Zimbabwe Limited 2000 (1) ZLR 136 (H).

Counsel for the applicant contended that the effect of the order sought by the applicant is that interest continues to run until payment in full is made irrespective of the in duplum rule.

The respondent urged me to follow the case of CBZ Limited v MM Builders & Suppliers (Private) Limited & Ors 1996 (2) ZLR 420 (H) and Conforce (Pvt) Ltd v City of Harare 2000 (1) ZLR 445 (H).

The proposition that interest ceases to run when it has reached the capital amount and only commences to run afresh upon judgment is found in CBZ Limited v MM Builders & Suppliers (Private) Limited & Ors 1996 (2) ZLR 420 (H)…,.

As rightly submitted by counsel for the respondent, the decision in Standard Bank of South Africa v Oneanate Investments (Pty) Ltd 1998 (1) SA 811 (SCA) is merely persuasive. The decision in CBZ Limited v MM Builders & Suppliers (Private) Limited & Ors 1996 (2) ZLR 420 (H) was decided by a full bench of the High Court and is therefore binding on me.

Final Orders re: Nature, Amendment, Variation, Rescission iro Corrections and Orders Erroneously Sought or Granted

On 19 July 2006, the applicant obtained judgment in this Court in Case No. HC2433/2005 in the sum of $485,316,000=. The order provided for interest in the following terms:

Interest is due on the above amount at the prevailing overdraft interest rate as quoted by Stanbic Bank Limited.”

On 10 September 2007, the applicant filed the present application seeking the following relief:

1. That the applicant be and is hereby entitled to levy interest on the capital debt in Case No. HC1929/2005 from 4th February 2005 to date of payment.

2. Costs on the legal practitioner/client scale (sic).”…,.

Before the applicant addressed me on the merits of the application, I queried the nature of relief that the applicant sought and whether or not the applicant had, in view of the judgment in Case No 2433/05, adopted the proper procedure.

Counsel for the applicant submitted that the applicant was seeking a declarator that interest was due from 4 February 2005 to the date of payment. He submitted that the applicant was not seeking a variation of the order in Case No. HC2433/05.

Counsel for the respondent submitted that the matter, and, in particular, the question of interest, had already been adjudicated on in Case No. HC2433/05. He submitted that the applicant was seeking a variation of the order. The applicant could only do so in terms of Rule 449 of the High Court Rules. He further submitted that as the applicant had adopted the wrong procedure, the application should be dismissed with costs.

Despite counsel for the applicant's submissions, it appears to me that counsel for the respondent is correct in stating that the effect of the relief sought by the applicant is a correction of the order granted on 19 July 2006. The question of interest was indeed determined in HC2433/05 and an order was granted by this court. However, it appears to me that there was an apparent omission as to the date when interest was to commence running. The applicant had clearly stated in its prayer, in the declaration, the date from which interest would commence running. The order is therefore incomplete and in-operative. It is for this reason that I am of the view that I can proceed to determine the matter in terms of Rule 449(1)(b). The Rule provides that:

(1) The court or a judge may, in addition to any other power it or he may have, mero motu or upon the application of any party affected, correct, rescind, or vary any judgment or order —

(a) That was erroneously sought or erroneously granted in the absence of any party affected thereby; or

(b) In which there is an ambiguity or a patent error or omission, but only to the extent of such ambiguity, error or omission; or

(c) That was granted as the result of a mistake common to the parties”…,.

The court in HC2433/05 did not indicate, in the judgment, why the effective date when interest would run was not included. Had it so indicated, the matter would have been res judicata as contended by counsel for the respondent. It would have been difficult for this court to evoke its powers in terms of Rule 449. The silence in the judgment, and the order itself, appears to me to have been a clear omission.

Variation of Contracts re: Deed of Settlement, Compromise Agreement iro Without Prejudice Negotiations

The material facts giving rise to this application are that the applicants issued summons on 22 April 2005 in case No. HC1929/05 claiming the sum of $485,316,000=, interest at the rate of 115% calculated from 4 February 2005 to the date of payment and costs on a higher scale.

The claim arose from an agreement of sale between the applicant and the first respondent in terms of which the applicant was required to deliver flour, to the value of $485,316,000=, to the first respondent. The flour was duly delivered on 25 January 2005. The first respondent was obliged, under the agreement, to pay the purchase price for the flour by 4 February 2005. The second respondent bound himself as surety and co-principal debtor in respect of the first respondent's liability. The purchase price was not paid on the due date resulting in the claim.

The respondents defended the claim.

On 27 May 2005 the applicant filed an application for summary judgment in case No. HC2433/05. The judgment was duly granted in favour of the applicant on 19 July 2006. The respondent appealed against that judgment on 26 July 2006. However, on 22 March 2007, the respondents tendered payment of $970,632= being the judgment debt plus interest. In a letter dated 13 April 2007, the applicant accepted the payment on a without prejudice basis and reserved their right to claim interest accrued on the sum of $970,632=. Following the payment, the Notice of Appeal was withdrawn on 26 March 2007.

On 18 November 2007, the applicant then filed the present application claiming interest on the capital debt in case No. HC1929/2005 from 4 February to the date of payment….,.


CHATUKUTA J: On 19 July 2006, the applicant obtained judgment in this Court in Case No. HC2433/2005 in the sum of $485,316,000. The order provided for interest in the following terms:

Interest is due on the above amount at the prevailing overdraft interest rate as quoted by Stanbic Bank Limited.”

On 10 September 2007, the applicant filed the present application seeking the following relief:

1. That the applicant be and is hereby entitled to levy interest on the capital debt in Case No. HC1929/2005 from 4th February 2005 to date of payment.

2. Costs on the legal practitioner/client scale (sic).”

The material facts giving rise to this application are that the applicants issued summons on 22 April 2005 in case No. HC1929/05 claiming the sum of $485,316,000, interest at the rate of 115% calculated from 4 February 2005 to the date of payment and costs on a higher scale. The claim arose from an agreement of sale between the applicant and the 1st respondent in terms of which the applicant was required to deliver flour to the value of $485,316,000 to the 1st respondent. The flour was duly delivered on 25 January 2005. The 1st respondent was obliged under the agreement to pay the purchase price for the flour by 4 February 2005. The 2nd respondent bound himself as surety and co-principal debtor in respect of the 1st respondent's liability. The purchase price was not paid on the due date resulting in the claim.

The respondents defended the claim.

On 27 May 2005 the applicant filed an application for summary judgment in case No. HC2433/05. The judgment was duly granted in favour of the applicant on 19 July 2006. The respondent appealed against that judgment on 26 July 2006. However, on 22 March 2007, the respondents tendered payment of $970,632,00 being the judgment debt, plus interest. In a letter dated 13 April 2007, the applicant accepted the payment on a without prejudice basis, and reserved their right to claim interest accrued on the sum of $970,632. Following the payment, the notice of appeal was withdrawn on 26 March 2007.

On 18 November 2007, the applicant then filed the present application claiming interest on the capital debt in case No. HC1929/2005 from 4 February to the date of payment. Before the applicant addressed me on the merits of the application, I queried the nature of relief that the applicant sought and whether or not the applicant had, in view of the judgment in Case No 2433/05, adopted the proper procedure.

Mr Venturas, for the applicant, submitted that the applicant was seeking a declarator that interest was due from 4 February 2005 to the date of payment. He submitted that the applicant was not seeking a variation of the order in Case No. HC2433/05.

Mr Mutero, for the respondent, submitted that the matter, and in particular the question of interest, had already been adjudicated on in Case No. HC2433/05. He submitted that the applicant was seeking a variation of the order. The applicant could only do so in terms of Rule 449 of the High Court Rules. He further submitted that as the applicant had adopted the wrong procedure, the application should be dismissed with costs.

Despite Mr Venturas' submissions, it appears to me that Mr Mutero is correct in stating that the effect of the relief sought by the applicant is a correction of the order granted on 19 July 2006. The question of interest was indeed determined in the HC2433/05 and an order was granted by this court. However, it appears to me that there was an apparent omission as to the date when interest was to commence running. The applicant had clearly stated in its prayer in the declaration the date from which interest would commence running. The order is therefore incomplete and inoperative. It is for this reason that I am of the view that I can proceed to determine the matter in terms of Rule 449(1)(b). The Rule provides that:

(1) The court or a judge may, in addition to any other power it or he may have, mero motu or upon the application of any party affected, correct, rescind, or vary any judgment or order —

(a) that was erroneously sought or erroneously granted in the absence of any party affected thereby; or

(b) in which there is an ambiguity or a patent error or omission, but only to the extent of such ambiguity, error or omission; or

(c) that was granted as the result of a mistake common to the parties” (own emphasis)

The court in HC2433/05 did not indicate in the judgment why the effective date when interest would run was not included. Had it so indicated, the matter would have been res judicata as contended by Mr Mutero. It would have been difficult for this court to evoke its powers in terms of Rule 449. The silence in the judgment and the order itself appears to me to have been a clear omission.

The next issue for determination is whether or not it is competent for me to correct the order and provide as requested by the applicant that interest should have commenced to run from 4 February 2005 to date of payment despite the in duplum rule.

The applicant contended that the in duplum rule does not apply in the present case because proceedings had already been instituted and the delay was attributable to the justice delivery system. In support thereof, the applicant referred me to the case of Standard Bank of South Africa v Oneanate Investments (Pty) Ltd 1998 (1) SA 811 (SCA) and Ehlers v Standard Chartered Bank Zimbabwe Limited 2000 (1) ZLR 136 (H). Mr Venturas contended that the effect of the order sought by the applicant is that interest continues to run until payment in full is made irrespective of the in duplum rule.

The respondent urged me to follow the case of CBZ Limited v MM Builders & Suppliers (Private) Limited & Ors 1996 (2) ZLR 420 (H) and Conforce (Pvt) Ltd v City of Harare 2000 (1) ZLR 445 (H).

The proposition that interest ceases to run when it has reached the capital amount and only commences to run afresh upon judgment is found in the CBZ Limited v MM Builders case (supra) at 441E-F where GILLESPIE J states that:

Upon judgment being given interest on the full amount of the judgment debt commences to run afresh but will once again cease to accrue when it waxes to the amount of the judgment debt, being the capital and interest thereon for which the cause of action was instituted.”

Therefore the in duplum rule applies where the interest reaches the judgment debt.

It appears to me that the reasoning by MALABA J (as he then was) in Ehlers case does not take into account the fact that the debtor is equally not in control of the process by which interest accumulates. At page 139G-140B he stated:-

The learned judges preferred the view that interest only commences to run anew as from the date of judgment. I must, with respect, express my dissent from the decision in Commercial Bank of Zimbabwe's Case supra on the date on which interest commences to run afresh in a case where the in duplum rule applies. This view of the law does not give effect to the policy behind the in duplum rule, nor does it recognize the discretion enjoyed by the court in the matter. In Georgias & Anor v Standard Chartered Finance Zimbabwe Ltd 1998 (2) ZLR 488 (S) at 495D GUBBAY CJ said that the in duplum rule is based upon a public policy designed to protect borrowers from the exploitation of lenders by prohibiting usurious abuse. The principle that interest commence to run afresh from the date of litis contestatio, which in this case is the date of service of summons is based upon the recognition of the fact that from that date the creditor ceases to be in control of the process by which interest accumulates.”

In the present case, the respondent cannot be held accountable for the delays caused by the legal system. It therefore should not be penalised for enforcing its own rights to defend an action particularly, in such a case where there is a divergence of views on the application of the in duplum rule. I do not believe that it would be in the public interest to penalise the debtor.

I am however, persuaded by the remarks of CHINHENGO J in the Conforce case, (supra) at 457B-D which seems to reflect the true position regarding the application of the in duplum rule on a judgment debt. At page 458A-F he noted:-

I venture to say that the public interest served by the in duplum rule is not identified with sympathy for the debtor, so as to protect him. I view the public interest involved as encompassing a wider spectrum of interests, from the protection of the debtor to securing fiscal discipline on the part of lenders to considerations of justification for charging interest in the first place i.e. to compensate the creditor for deprivation of use of the money due until payment (Mawere v Mukura 1997 (2) ZLR 361 (H) at 364G) and to the interests of commerce generally and perhaps many more interests. Thus the public interest cannot be restricted to one or two considerations i.e. the protection of the debtor and the dictates of modern commerce. But even if it were so restricted, I cannot see anything incompatible with the rule serving those interests if it were applied in the manner advocated for in MM Builders case. The creditor's claim for interest would be limited to an amount that does exceed the capital. In my view, the danger in adopting the approach in Oneanate and Ehlers cases supra is that an unscrupulous creditor only has to institute action to defeat the in duplum rule. He may so act as to ensure that the institution of proceedings and the attainment of the double coincide with the result that the rule is rendered inoperative. I do not see anything that is against the public interest or the interest of modern finance, if the in duplum rule operates in the manner outlined by GILLESPIE J and the old Roman Dutch authorities which espouse the view that once the double has been reached, interest must stop to run regardless of the institution of proceedings or that the stage of litis contestatio has been reached. Where in particular the double has not been reached, I find no relevance at all of the event of institution of proceedings. Interest must continue to run until it equates to the capital amount soon after or long after the institution of proceedings, but that is immaterial. I am therefore unpersuaded by the conclusion reached on this point in Oneanate and Ehlers cases. I must respectfully express my dissent from those judgments.”

As rightly submitted by Mr. Mutero, the decision in Oneanate's case is merely persuasive. The decision in the CBZ Limited v MM Builders was decided by a full bench of the High Court and is therefore binding on me.

In the result, it is ordered that:

1. The application be and is hereby granted.

2. The order granted in HC1929/05 on 19 July 2006 be and is hereby amended by the deletion of paragraph 2 and substitution with:

Interest is due on the above amount at the prevailing overdraft interest rate as quoted by Stanbic Bank Limited with effect from 4th February 2005 to date of payment.”

3. The respondent shall pay the costs of the application.



Messrs Byron Venturas & Partners, applicant's legal practitioners

Messrs Sawyer & Mkushi, respondents' legal practitioners

Back Main menu

Categories

Back to top