Law Portal
Zimbabwe

Welcome To Law Portal

Welcome, Guest!
[Help?]

HH204-10 - BENSON SAMUDZIMU vs DAIRIBORD HOLDINGS LTD

  • View Judgment By Categories
  • View Full Judgment


Procedural Law-viz jurisdiction re subject matter jurisdiction.
Procedural Law-viz jurisdiction re cause of action jurisdiction.
Procedural Law-viz jurisdiction re labour proceedings iro section 89 of the Labour Act [Chapter 28:01].
Procedural Law-viz jurisdiction re jurisdictional curtailment iro section 89 of the Labour Act [Chapter 28:01].
Procedural Law-viz jurisdiction re specialised courts.
Labour Law-viz arbitration re registration of an arbitral award iro section 98 of the Labour Act [Chapter 28:01].
Procedural Law-viz court management re co-hearing of matters.
Procedural Law-viz court management re joint hearing of proceedings.
Procedural Law-viz court management re consolidation of matters.
Procedural Law-viz court management re joinder of actions.
Procedural Law-viz pleadings re counterclaim iro Rule 229 of the High Court Rules.
Procedural Law-viz pleadings re claim in reconvention iro Rule 229A of the High Court Rules.
Procedural Law-viz pleadings re counter application iro Rule 229A of the High Court Rules.
Procedural Law-viz rules of evidence re evidence derived from concurrent litigation.
Procedural Law-viz pleadings re inter-related proceedings iro co-hearing.
Procedural Law-viz pleadings re cross-referencing iro joint hearing.
Procedural Law-viz pleadings re inter-related proceedings iro consolidation of matters.
Procedural Law-viz pleadings re cross referencing iro joinder of actions.

Review re: Labour Proceedings

The legal issue that arises in this chamber application is whether the provisions of the Labour Act [Chapter 20:01] exclude the jurisdiction of the High Court in areas where the Labour Court has jurisdiction.

Section 89(6) of the Labour Act provides:

“No court, other than the Labour Court, shall have jurisdiction in the first instance to hear and determine any application, appeal or matter referred to in subsection (1).”

Section 89 of the Labour Act spells out the functions, powers, and jurisdiction of the Labour Court.

In Tuso v City of Harare 2004 (1) ZLR (H) BHUNU J had occasion to consider the legal import of section 89(6) of the Labour Act. The learned judge concluded…, as follows:

“It is manifestily clear to me, that, the intention of the legislature was to expressly exclude the jurisdiction of all other courts in areas where the Labour Court has jurisdiction in the first instance.”

I am in entire agreement with that conclusion.

It is important to note the historical context in which the Labour Court was created. Its predecessor, the Labour Relations Tribunal, was limited in terms of its powers and jurisdiction. Its decisions were subject to review by the High Court in much the same way as the decisions of any other domestic tribunal would be.

Even then, this court always took the view that a litigant must first exhaust the internal remedies availed to it, in terms of the Labour Act, before approaching it for relief.

The Labour Relations Tribunal was, in 2003, transformed into a court whose powers of review were the same as those of the High Court subject to the provisions of section 89(1) of the Labour Act.

The intention of the legislature clearly was to establish a one stop shop for all labour matters and provide finality in litigation involving labour issues; otherwise, why create a structure that is parallel to the High Court?

However, this exclusive jurisdiction only exists for matters provided for in section 89(1) of the Labour Act.

Pleadings re: Litis Contestatio, Closure of Pleadings, Joinder of Issues and Notice to Discover

The legal issue that arises in this chamber application is whether the provisions of the Labour Act [Chapter 20:01] exclude the jurisdiction of the High Court in areas where the Labour Court has jurisdiction.

Section 89(6) of the Labour Act provides:

“No court, other than the Labour Court, shall have jurisdiction in the first instance to hear and determine any application, appeal or matter referred to in subsection (1).”

Section 89 of the Labour Act spells out the functions, powers, and jurisdiction of the Labour Court.

In Tuso v City of Harare 2004 (1) ZLR (H) BHUNU J had occasion to consider the legal import of section 89(6) of the Labour Act. The learned judge concluded…, as follows:

“It is manifestily clear to me, that, the intention of the legislature was to expressly exclude the jurisdiction of all other courts in areas where the Labour Court has jurisdiction in the first instance.”

I am in entire agreement with that conclusion.

It is important to note the historical context in which the Labour Court was created. Its predecessor, the Labour Relations Tribunal, was limited in terms of its powers and jurisdiction. Its decisions were subject to review by the High Court in much the same way as the decisions of any other domestic tribunal would be.

Even then, this court always took the view that a litigant must first exhaust the internal remedies availed to it, in terms of the Labour Act, before approaching it for relief.

The Labour Relations Tribunal was, in 2003, transformed into a court whose powers of review were the same as those of the High Court subject to the provisions of section 89(1) of the Labour Act.

The intention of the legislature clearly was to establish a one stop shop for all labour matters and provide finality in litigation involving labour issues; otherwise, why create a structure that is parallel to the High Court?

However, this exclusive jurisdiction only exists for matters provided for in section 89(1) of the Labour Act.

In the present application, the applicant seeks to register an arbitral award with this court in terms of section 98(14) of the Labour Act.

The respondent opposes the application on the basis, that, the arbitral award offends public policy in terms of art (s) 34 and 36 of the Arbitration Act.

It has incorporated, by reference, papers it filed under case number HC5560/10, a separate application, and has argued that the present application and that filed under case HC5560/10 be heard together.

I agree with the applicant, that, the correct procedure would have been for the respondent to file a counter chamber application in terms of Rule 229A of the High Court Rules which reads:

“Where a respondent files a notice of opposition and Opposing Affidavit, he may file, together with these documents, a counter application against the applicant, in the form 'mutatis mutandis' of a court application or a chamber application whichever is applicable.”

In any event, it would be improper to join the two applications, because, the time within which the second respondent under case number HC5560/10 (the arbitrator) must file a Notice of Opposition has not expired.

The second respondent's defence in that application is therefore not yet known.

Pleadings re: Inter-related Suits, Cross-Referencing, Record of Proceedings and Off the Record or In Vacuo Submissions

The legal issue that arises in this chamber application is whether the provisions of the Labour Act [Chapter 20:01] exclude the jurisdiction of the High Court in areas where the Labour Court has jurisdiction.

Section 89(6) of the Labour Act provides:

“No court, other than the Labour Court, shall have jurisdiction in the first instance to hear and determine any application, appeal or matter referred to in subsection (1).”

Section 89 of the Labour Act spells out the functions, powers, and jurisdiction of the Labour Court.

In Tuso v City of Harare 2004 (1) ZLR (H) BHUNU J had occasion to consider the legal import of section 89(6) of the Labour Act. The learned judge concluded…, as follows:

“It is manifestily clear to me, that, the intention of the legislature was to expressly exclude the jurisdiction of all other courts in areas where the Labour Court has jurisdiction in the first instance.”

I am in entire agreement with that conclusion.

It is important to note the historical context in which the Labour Court was created. Its predecessor, the Labour Relations Tribunal, was limited in terms of its powers and jurisdiction. Its decisions were subject to review by the High Court in much the same way as the decisions of any other domestic tribunal would be.

Even then, this court always took the view that a litigant must first exhaust the internal remedies availed to it, in terms of the Labour Act, before approaching it for relief.

The Labour Relations Tribunal was, in 2003, transformed into a court whose powers of review were the same as those of the High Court subject to the provisions of section 89(1) of the Labour Act.

The intention of the legislature clearly was to establish a one stop shop for all labour matters and provide finality in litigation involving labour issues; otherwise, why create a structure that is parallel to the High Court?

However, this exclusive jurisdiction only exists for matters provided for in section 89(1) of the Labour Act.

In the present application, the applicant seeks to register an arbitral award with this court in terms of section 98(14) of the Labour Act.

The respondent opposes the application on the basis, that, the arbitral award offends public policy in terms of art (s) 34 and 36 of the Arbitration Act.

It has incorporated, by reference, papers it filed under case number HC5560/10, a separate application, and has argued that the present application and that filed under case HC5560/10 be heard together.

I agree with the applicant, that, the correct procedure would have been for the respondent to file a counter chamber application in terms of Rule 229A of the High Court Rules which reads:

“Where a respondent files a notice of opposition and Opposing Affidavit, he may file, together with these documents, a counter application against the applicant, in the form 'mutatis mutandis' of a court application or a chamber application whichever is applicable.”

In any event, it would be improper to join the two applications, because, the time within which the second respondent under case number HC5560/10 (the arbitrator) must file a Notice of Opposition has not expired. The second respondent's defence in that application is therefore not yet known.

I have, however, taken the liberty to consider the heads of argument filed by the respondent under case 5560/10 for purposes of determining the present application.

Evidence of Oath, Evidence Derived from Previous, Concurrent or Criminal Litigation and Submissions from the Bar


The legal issue that arises in this chamber application is whether the provisions of the Labour Act [Chapter 20:01] exclude the jurisdiction of the High Court in areas where the Labour Court has jurisdiction.

Section 89(6) of the Labour Act provides:

“No court, other than the Labour Court, shall have jurisdiction in the first instance to hear and determine any application, appeal or matter referred to in subsection (1).”

Section 89 of the Labour Act spells out the functions, powers, and jurisdiction of the Labour Court.

In Tuso v City of Harare 2004 (1) ZLR (H) BHUNU J had occasion to consider the legal import of section 89(6) of the Labour Act. The learned judge concluded…, as follows:

“It is manifestily clear to me, that, the intention of the legislature was to expressly exclude the jurisdiction of all other courts in areas where the Labour Court has jurisdiction in the first instance.”

I am in entire agreement with that conclusion.

It is important to note the historical context in which the Labour Court was created. Its predecessor, the Labour Relations Tribunal, was limited in terms of its powers and jurisdiction. Its decisions were subject to review by the High Court in much the same way as the decisions of any other domestic tribunal would be.

Even then, this court always took the view that a litigant must first exhaust the internal remedies availed to it, in terms of the Labour Act, before approaching it for relief.

The Labour Relations Tribunal was, in 2003, transformed into a court whose powers of review were the same as those of the High Court subject to the provisions of section 89(1) of the Labour Act.

The intention of the legislature clearly was to establish a one stop shop for all labour matters and provide finality in litigation involving labour issues; otherwise, why create a structure that is parallel to the High Court?

However, this exclusive jurisdiction only exists for matters provided for in section 89(1) of the Labour Act.

In the present application, the applicant seeks to register an arbitral award with this court in terms of section 98(14) of the Labour Act.

The respondent opposes the application on the basis, that, the arbitral award offends public policy in terms of art (s) 34 and 36 of the Arbitration Act.

It has incorporated, by reference, papers it filed under case number HC5560/10, a separate application, and has argued that the present application and that filed under case HC5560/10 be heard together.

I agree with the applicant, that, the correct procedure would have been for the respondent to file a counter chamber application in terms of Rule 229A of the High Court Rules which reads:

“Where a respondent files a notice of opposition and Opposing Affidavit, he may file, together with these documents, a counter application against the applicant, in the form 'mutatis mutandis' of a court application or a chamber application whichever is applicable.”

In any event, it would be improper to join the two applications, because, the time within which the second respondent under case number HC5560/10 (the arbitrator) must file a Notice of Opposition has not expired. The second respondent's defence in that application is therefore not yet known.

I have, however, taken the liberty to consider the heads of argument filed by the respondent under case 5560/10 for purposes of determining the present application.

Court Management re: Co-Hearing or Joint Hearing Proceedings

The legal issue that arises in this chamber application is whether the provisions of the Labour Act [Chapter 20:01] exclude the jurisdiction of the High Court in areas where the Labour Court has jurisdiction.

Section 89(6) of the Labour Act provides:

“No court, other than the Labour Court, shall have jurisdiction in the first instance to hear and determine any application, appeal or matter referred to in subsection (1).”

Section 89 of the Labour Act spells out the functions, powers, and jurisdiction of the Labour Court.

In Tuso v City of Harare 2004 (1) ZLR (H) BHUNU J had occasion to consider the legal import of section 89(6) of the Labour Act. The learned judge concluded…, as follows:

“It is manifestily clear to me, that, the intention of the legislature was to expressly exclude the jurisdiction of all other courts in areas where the Labour Court has jurisdiction in the first instance.”

I am in entire agreement with that conclusion.

It is important to note the historical context in which the Labour Court was created. Its predecessor, the Labour Relations Tribunal, was limited in terms of its powers and jurisdiction. Its decisions were subject to review by the High Court in much the same way as the decisions of any other domestic tribunal would be.

Even then, this court always took the view that a litigant must first exhaust the internal remedies availed to it, in terms of the Labour Act, before approaching it for relief.

The Labour Relations Tribunal was, in 2003, transformed into a court whose powers of review were the same as those of the High Court subject to the provisions of section 89(1) of the Labour Act.

The intention of the legislature clearly was to establish a one stop shop for all labour matters and provide finality in litigation involving labour issues; otherwise, why create a structure that is parallel to the High Court?

However, this exclusive jurisdiction only exists for matters provided for in section 89(1) of the Labour Act.

In the present application, the applicant seeks to register an arbitral award with this court in terms of section 98(14) of the Labour Act.

The respondent opposes the application on the basis, that, the arbitral award offends public policy in terms of art (s) 34 and 36 of the Arbitration Act.

It has incorporated, by reference, papers it filed under case number HC5560/10, a separate application, and has argued that the present application and that filed under case HC5560/10 be heard together.

I agree with the applicant, that, the correct procedure would have been for the respondent to file a counter chamber application in terms of Rule 229A of the High Court Rules which reads:

“Where a respondent files a notice of opposition and Opposing Affidavit, he may file, together with these documents, a counter application against the applicant, in the form 'mutatis mutandis' of a court application or a chamber application whichever is applicable.”

In any event, it would be improper to join the two applications, because, the time within which the second respondent under case number HC5560/10 (the arbitrator) must file a Notice of Opposition has not expired. The second respondent's defence in that application is therefore not yet known.

I have, however, taken the liberty to consider the heads of argument filed by the respondent under case 5560/10 for purposes of determining the present application.

Pleadings re: Claims, Counter-Claim, Claim in Reconvention and Counter Application iro Approach


The legal issue that arises in this chamber application is whether the provisions of the Labour Act [Chapter 20:01] exclude the jurisdiction of the High Court in areas where the Labour Court has jurisdiction.

Section 89(6) of the Labour Act provides:

“No court, other than the Labour Court, shall have jurisdiction in the first instance to hear and determine any application, appeal or matter referred to in subsection (1).”

Section 89 of the Labour Act spells out the functions, powers, and jurisdiction of the Labour Court.

In Tuso v City of Harare 2004 (1) ZLR (H) BHUNU J had occasion to consider the legal import of section 89(6) of the Labour Act. The learned judge concluded…, as follows:

“It is manifestily clear to me, that, the intention of the legislature was to expressly exclude the jurisdiction of all other courts in areas where the Labour Court has jurisdiction in the first instance.”

I am in entire agreement with that conclusion.

It is important to note the historical context in which the Labour Court was created. Its predecessor, the Labour Relations Tribunal, was limited in terms of its powers and jurisdiction. Its decisions were subject to review by the High Court in much the same way as the decisions of any other domestic tribunal would be.

Even then, this court always took the view that a litigant must first exhaust the internal remedies availed to it, in terms of the Labour Act, before approaching it for relief.

The Labour Relations Tribunal was, in 2003, transformed into a court whose powers of review were the same as those of the High Court subject to the provisions of section 89(1) of the Labour Act.

The intention of the legislature clearly was to establish a one stop shop for all labour matters and provide finality in litigation involving labour issues; otherwise, why create a structure that is parallel to the High Court?

However, this exclusive jurisdiction only exists for matters provided for in section 89(1) of the Labour Act.

In the present application, the applicant seeks to register an arbitral award with this court in terms of section 98(14) of the Labour Act.

The respondent opposes the application on the basis, that, the arbitral award offends public policy in terms of art (s) 34 and 36 of the Arbitration Act.

It has incorporated, by reference, papers it filed under case number HC5560/10, a separate application, and has argued that the present application and that filed under case HC5560/10 be heard together.

I agree with the applicant, that, the correct procedure would have been for the respondent to file a counter chamber application in terms of Rule 229A of the High Court Rules which reads:

“Where a respondent files a notice of opposition and Opposing Affidavit, he may file, together with these documents, a counter application against the applicant, in the form 'mutatis mutandis' of a court application or a chamber application whichever is applicable.”

In any event, it would be improper to join the two applications, because, the time within which the second respondent under case number HC5560/10 (the arbitrator) must file a Notice of Opposition has not expired. The second respondent's defence in that application is therefore not yet known.

I have, however, taken the liberty to consider the heads of argument filed by the respondent under case 5560/10 for purposes of determining the present application.

Court Management re: Consolidation of Matters, Joinder of Actions, Fragmantation of Disputes and the Consolidation Order


The legal issue that arises in this chamber application is whether the provisions of the Labour Act [Chapter 20:01] exclude the jurisdiction of the High Court in areas where the Labour Court has jurisdiction.

Section 89(6) of the Labour Act provides:

“No court, other than the Labour Court, shall have jurisdiction in the first instance to hear and determine any application, appeal or matter referred to in subsection (1).”

Section 89 of the Labour Act spells out the functions, powers, and jurisdiction of the Labour Court.

In Tuso v City of Harare 2004 (1) ZLR (H) BHUNU J had occasion to consider the legal import of section 89(6) of the Labour Act. The learned judge concluded…, as follows:

“It is manifestily clear to me, that, the intention of the legislature was to expressly exclude the jurisdiction of all other courts in areas where the Labour Court has jurisdiction in the first instance.”

I am in entire agreement with that conclusion.

It is important to note the historical context in which the Labour Court was created. Its predecessor, the Labour Relations Tribunal, was limited in terms of its powers and jurisdiction. Its decisions were subject to review by the High Court in much the same way as the decisions of any other domestic tribunal would be.

Even then, this court always took the view that a litigant must first exhaust the internal remedies availed to it, in terms of the Labour Act, before approaching it for relief.

The Labour Relations Tribunal was, in 2003, transformed into a court whose powers of review were the same as those of the High Court subject to the provisions of section 89(1) of the Labour Act.

The intention of the legislature clearly was to establish a one stop shop for all labour matters and provide finality in litigation involving labour issues; otherwise, why create a structure that is parallel to the High Court?

However, this exclusive jurisdiction only exists for matters provided for in section 89(1) of the Labour Act.

In the present application, the applicant seeks to register an arbitral award with this court in terms of section 98(14) of the Labour Act.

The respondent opposes the application on the basis, that, the arbitral award offends public policy in terms of art (s) 34 and 36 of the Arbitration Act.

It has incorporated, by reference, papers it filed under case number HC5560/10, a separate application, and has argued that the present application and that filed under case HC5560/10 be heard together.

I agree with the applicant, that, the correct procedure would have been for the respondent to file a counter chamber application in terms of Rule 229A of the High Court Rules which reads:

“Where a respondent files a notice of opposition and Opposing Affidavit, he may file, together with these documents, a counter application against the applicant, in the form 'mutatis mutandis' of a court application or a chamber application whichever is applicable.”

In any event, it would be improper to join the two applications, because, the time within which the second respondent under case number HC5560/10 (the arbitrator) must file a Notice of Opposition has not expired.

The second respondent's defence in that application is therefore not yet known.

Rules of Construction or Interpretation re: Approach


The legal issue that arises in this chamber application is whether the provisions of the Labour Act [Chapter 20:01] exclude the jurisdiction of the High Court in areas where the Labour Court has jurisdiction.

Section 89(6) of the Labour Act provides:

“No court, other than the Labour Court, shall have jurisdiction in the first instance to hear and determine any application, appeal or matter referred to in subsection (1).”

Section 89 of the Labour Act spells out the functions, powers, and jurisdiction of the Labour Court.

In Tuso v City of Harare 2004 (1) ZLR (H) BHUNU J had occasion to consider the legal import of section 89(6) of the Labour Act. The learned judge concluded…, as follows:

“It is manifestily clear to me, that, the intention of the legislature was to expressly exclude the jurisdiction of all other courts in areas where the Labour Court has jurisdiction in the first instance.”

I am in entire agreement with that conclusion.

It is important to note the historical context in which the Labour Court was created. Its predecessor, the Labour Relations Tribunal, was limited in terms of its powers and jurisdiction. Its decisions were subject to review by the High Court in much the same way as the decisions of any other domestic tribunal would be.

Even then, this court always took the view that a litigant must first exhaust the internal remedies availed to it, in terms of the Labour Act, before approaching it for relief.

The Labour Relations Tribunal was, in 2003, transformed into a court whose powers of review were the same as those of the High Court subject to the provisions of section 89(1) of the Labour Act.

The intention of the legislature clearly was to establish a one stop shop for all labour matters and provide finality in litigation involving labour issues; otherwise, why create a structure that is parallel to the High Court?

However, this exclusive jurisdiction only exists for matters provided for in section 89(1) of the Labour Act.

In the present application, the applicant seeks to register an arbitral award with this court in terms of section 98(14) of the Labour Act.

The respondent opposes the application on the basis, that, the arbitral award offends public policy in terms of art (s) 34 and 36 of the Arbitration Act.

It has incorporated, by reference, papers it filed under case number HC5560/10, a separate application, and has argued that the present application and that filed under case HC5560/10 be heard together.

I agree with the applicant, that, the correct procedure would have been for the respondent to file a counter chamber application in terms of Rule 229A of the High Court Rules which reads:

“Where a respondent files a notice of opposition and Opposing Affidavit, he may file, together with these documents, a counter application against the applicant, in the form 'mutatis mutandis' of a court application or a chamber application whichever is applicable.”

In any event, it would be improper to join the two applications, because, the time within which the second respondent under case number HC5560/10 (the arbitrator) must file a Notice of Opposition has not expired. The second respondent's defence in that application is therefore not yet known.

I have, however, taken the liberty to consider the heads of argument filed by the respondent under case 5560/10 for purposes of determining the present application.

I agree with the applicant, that, the extent to which the provisions of the Arbitration Act are applicable in labour matters is governed by section 98 of the Labour Act, subsection 2 of which provides:

“Subject to this section, the Arbitration Act [Cap 7:15] shall apply to a dispute referred to compulsory arbitration.”

Section 98 of the Labour Act provides for, inter alia, the referral of matters to compulsory arbitration, the appointment of arbitrators, appeals against decisions of arbitrators, reviews, and other remedies.

These provisions are detailed and comprehensive.

Clearly, it could not have been the intention of the legislature, that, parties aggrieved by the decision of an arbitrator, in a labour dispute, seek remedy in terms of section 34 or 36 of the Arbitration Act.

I agree with the applicant, that, the correct interpretation would be that, with regards the law, the Labour Act takes precedence over the Arbitration Act and any other enactment.

The intention of the legislature was to have all labour matters initiated and resolved to finality in terms of the Labour Act. Equally, the legislature must have intended that such matters be dealt with by the Labour Court to the exclusion of any other court.

Sections 34 and 36 of the Arbitration Act are not applicable in cases where the award sought to be challenged relates to a labour dispute.

The mechanisms for challenging such awards are provided for in the Labour Act and may be accessed through the medium of the Labour Court. No other court has jurisdiction to entertain such matters.

Appeal, Leave to Appeal, Leave to Execute Pending Appeal re: Suspension of Orders Pending Appeal iro Labour Proceedings


The legal issue that arises in this chamber application is whether the provisions of the Labour Act [Chapter 20:01] exclude the jurisdiction of the High Court in areas where the Labour Court has jurisdiction.

Section 89(6) of the Labour Act provides:

“No court, other than the Labour Court, shall have jurisdiction in the first instance to hear and determine any application, appeal or matter referred to in subsection (1).”

Section 89 of the Labour Act spells out the functions, powers, and jurisdiction of the Labour Court.

In Tuso v City of Harare 2004 (1) ZLR (H) BHUNU J had occasion to consider the legal import of section 89(6) of the Labour Act. The learned judge concluded…, as follows:

“It is manifestily clear to me, that, the intention of the legislature was to expressly exclude the jurisdiction of all other courts in areas where the Labour Court has jurisdiction in the first instance.”

I am in entire agreement with that conclusion.

It is important to note the historical context in which the Labour Court was created. Its predecessor, the Labour Relations Tribunal, was limited in terms of its powers and jurisdiction. Its decisions were subject to review by the High Court in much the same way as the decisions of any other domestic tribunal would be.

Even then, this court always took the view that a litigant must first exhaust the internal remedies availed to it, in terms of the Labour Act, before approaching it for relief.

The Labour Relations Tribunal was, in 2003, transformed into a court whose powers of review were the same as those of the High Court subject to the provisions of section 89(1) of the Labour Act.

The intention of the legislature clearly was to establish a one stop shop for all labour matters and provide finality in litigation involving labour issues; otherwise, why create a structure that is parallel to the High Court?

However, this exclusive jurisdiction only exists for matters provided for in section 89(1) of the Labour Act.

In the present application, the applicant seeks to register an arbitral award with this court in terms of section 98(14) of the Labour Act.

The respondent opposes the application on the basis, that, the arbitral award offends public policy in terms of art (s) 34 and 36 of the Arbitration Act.

It has incorporated, by reference, papers it filed under case number HC5560/10, a separate application, and has argued that the present application and that filed under case HC5560/10 be heard together.

I agree with the applicant, that, the correct procedure would have been for the respondent to file a counter chamber application in terms of Rule 229A of the High Court Rules which reads:

“Where a respondent files a notice of opposition and Opposing Affidavit, he may file, together with these documents, a counter application against the applicant, in the form 'mutatis mutandis' of a court application or a chamber application whichever is applicable.”

In any event, it would be improper to join the two applications, because, the time within which the second respondent under case number HC5560/10 (the arbitrator) must file a Notice of Opposition has not expired. The second respondent's defence in that application is therefore not yet known.

I have, however, taken the liberty to consider the heads of argument filed by the respondent under case 5560/10 for purposes of determining the present application.

I agree with the applicant, that, the extent to which the provisions of the Arbitration Act are applicable in labour matters is governed by section 98 of the Labour Act, subsection 2 of which provides:

“Subject to this section, the Arbitration Act [Cap 7:15] shall apply to a dispute referred to compulsory arbitration.”

Section 98 of the Labour Act provides for, inter alia, the referral of matters to compulsory arbitration, the appointment of arbitrators, appeals against decisions of arbitrators, reviews, and other remedies.

These provisions are detailed and comprehensive.

Clearly, it could not have been the intention of the legislature, that, parties aggrieved by the decision of an arbitrator, in a labour dispute, seek remedy in terms of section 34 or 36 of the Arbitration Act.

I agree with the applicant, that, the correct interpretation would be that, with regards the law, the Labour Act takes precedence over the Arbitration Act and any other enactment.

The intention of the legislature was to have all labour matters initiated and resolved to finality in terms of the Labour Act. Equally, the legislature must have intended that such matters be dealt with by the Labour Court to the exclusion of any other court.

Sections 34 and 36 of the Arbitration Act are not applicable in cases where the award sought to be challenged relates to a labour dispute. The mechanisms for challenging such awards are provided for in the Labour Act and may be accessed through the medium of the Labour Court. No other court has jurisdiction to entertain such matters.

In the present case, the respondent has lodged an appeal with the Labour Court. The appeal is still pending. Should the respondent wish to have the arbitrator's determination suspended pending appeal or dealt with in any other interim way, it is to that court that it must direct its application.

Accordingly, for as long as the arbitral award has not been suspended or set aside on review or appeal, in terms of the Labour Act, there is no basis upon which this court may decline registration of the same.

Jurisdiction re: Approach, Concurrent Jurisdiction, Statutory, Procedural and Contractual Jurisdictional Curtailment


The legal issue that arises in this chamber application is whether the provisions of the Labour Act [Chapter 20:01] exclude the jurisdiction of the High Court in areas where the Labour Court has jurisdiction.

Section 89(6) of the Labour Act provides:

“No court, other than the Labour Court, shall have jurisdiction in the first instance to hear and determine any application, appeal or matter referred to in subsection (1).”

Section 89 of the Labour Act spells out the functions, powers, and jurisdiction of the Labour Court.

In Tuso v City of Harare 2004 (1) ZLR (H) BHUNU J had occasion to consider the legal import of section 89(6) of the Labour Act. The learned judge concluded…, as follows:

“It is manifestily clear to me, that, the intention of the legislature was to expressly exclude the jurisdiction of all other courts in areas where the Labour Court has jurisdiction in the first instance.”

I am in entire agreement with that conclusion.

It is important to note the historical context in which the Labour Court was created. Its predecessor, the Labour Relations Tribunal, was limited in terms of its powers and jurisdiction. Its decisions were subject to review by the High Court in much the same way as the decisions of any other domestic tribunal would be.

Even then, this court always took the view that a litigant must first exhaust the internal remedies availed to it, in terms of the Labour Act, before approaching it for relief.

The Labour Relations Tribunal was, in 2003, transformed into a court whose powers of review were the same as those of the High Court subject to the provisions of section 89(1) of the Labour Act.

The intention of the legislature clearly was to establish a one stop shop for all labour matters and provide finality in litigation involving labour issues; otherwise, why create a structure that is parallel to the High Court?

However, this exclusive jurisdiction only exists for matters provided for in section 89(1) of the Labour Act.

In the present application, the applicant seeks to register an arbitral award with this court in terms of section 98(14) of the Labour Act.

The respondent opposes the application on the basis, that, the arbitral award offends public policy in terms of art (s) 34 and 36 of the Arbitration Act.

It has incorporated, by reference, papers it filed under case number HC5560/10, a separate application, and has argued that the present application and that filed under case HC5560/10 be heard together.

I agree with the applicant, that, the correct procedure would have been for the respondent to file a counter chamber application in terms of Rule 229A of the High Court Rules which reads:

“Where a respondent files a notice of opposition and Opposing Affidavit, he may file, together with these documents, a counter application against the applicant, in the form 'mutatis mutandis' of a court application or a chamber application whichever is applicable.”

In any event, it would be improper to join the two applications, because, the time within which the second respondent under case number HC5560/10 (the arbitrator) must file a Notice of Opposition has not expired. The second respondent's defence in that application is therefore not yet known.

I have, however, taken the liberty to consider the heads of argument filed by the respondent under case 5560/10 for purposes of determining the present application.

I agree with the applicant, that, the extent to which the provisions of the Arbitration Act are applicable in labour matters is governed by section 98 of the Labour Act, subsection 2 of which provides:

“Subject to this section, the Arbitration Act [Cap 7:15] shall apply to a dispute referred to compulsory arbitration.”

Section 98 of the Labour Act provides for, inter alia, the referral of matters to compulsory arbitration, the appointment of arbitrators, appeals against decisions of arbitrators, reviews, and other remedies.

These provisions are detailed and comprehensive.

Clearly, it could not have been the intention of the legislature, that, parties aggrieved by the decision of an arbitrator, in a labour dispute, seek remedy in terms of section 34 or 36 of the Arbitration Act.

I agree with the applicant, that, the correct interpretation would be that, with regards the law, the Labour Act takes precedence over the Arbitration Act and any other enactment.

The intention of the legislature was to have all labour matters initiated and resolved to finality in terms of the Labour Act. Equally, the legislature must have intended that such matters be dealt with by the Labour Court to the exclusion of any other court.

Sections 34 and 36 of the Arbitration Act are not applicable in cases where the award sought to be challenged relates to a labour dispute. The mechanisms for challenging such awards are provided for in the Labour Act and may be accessed through the medium of the Labour Court. No other court has jurisdiction to entertain such matters.

In the present case, the respondent has lodged an appeal with the Labour Court. The appeal is still pending. Should the respondent wish to have the arbitrator's determination suspended pending appeal or dealt with in any other interim way, it is to that court that it must direct its application.

Accordingly, for as long as the arbitral award has not been suspended or set aside on review or appeal, in terms of the Labour Act, there is no basis upon which this court may decline registration of the same.

It is therefore ordered as follows:

1. The arbitral award issued by Mr A.J. Manase, an independent arbitrator, be and is hereby registered in terms of section 98(14) of the Labour Act [Chapter 28:01].

2. In terms of the said arbitral award, the respondent shall pay the applicant an amount of US$287,491.

3. The respondent is to pay the costs of this application.

Jurisdiction re: Labour Proceedings


The legal issue that arises in this chamber application is whether the provisions of the Labour Act [Chapter 20:01] exclude the jurisdiction of the High Court in areas where the Labour Court has jurisdiction.

Section 89(6) of the Labour Act provides:

“No court, other than the Labour Court, shall have jurisdiction in the first instance to hear and determine any application, appeal or matter referred to in subsection (1).”

Section 89 of the Labour Act spells out the functions, powers, and jurisdiction of the Labour Court.

In Tuso v City of Harare 2004 (1) ZLR (H) BHUNU J had occasion to consider the legal import of section 89(6) of the Labour Act. The learned judge concluded…, as follows:

“It is manifestily clear to me, that, the intention of the legislature was to expressly exclude the jurisdiction of all other courts in areas where the Labour Court has jurisdiction in the first instance.”

I am in entire agreement with that conclusion.

It is important to note the historical context in which the Labour Court was created. Its predecessor, the Labour Relations Tribunal, was limited in terms of its powers and jurisdiction. Its decisions were subject to review by the High Court in much the same way as the decisions of any other domestic tribunal would be.

Even then, this court always took the view that a litigant must first exhaust the internal remedies availed to it, in terms of the Labour Act, before approaching it for relief.

The Labour Relations Tribunal was, in 2003, transformed into a court whose powers of review were the same as those of the High Court subject to the provisions of section 89(1) of the Labour Act.

The intention of the legislature clearly was to establish a one stop shop for all labour matters and provide finality in litigation involving labour issues; otherwise, why create a structure that is parallel to the High Court?

However, this exclusive jurisdiction only exists for matters provided for in section 89(1) of the Labour Act.

In the present application, the applicant seeks to register an arbitral award with this court in terms of section 98(14) of the Labour Act.

The respondent opposes the application on the basis, that, the arbitral award offends public policy in terms of art (s) 34 and 36 of the Arbitration Act.

It has incorporated, by reference, papers it filed under case number HC5560/10, a separate application, and has argued that the present application and that filed under case HC5560/10 be heard together.

I agree with the applicant, that, the correct procedure would have been for the respondent to file a counter chamber application in terms of Rule 229A of the High Court Rules which reads:

“Where a respondent files a notice of opposition and Opposing Affidavit, he may file, together with these documents, a counter application against the applicant, in the form 'mutatis mutandis' of a court application or a chamber application whichever is applicable.”

In any event, it would be improper to join the two applications, because, the time within which the second respondent under case number HC5560/10 (the arbitrator) must file a Notice of Opposition has not expired. The second respondent's defence in that application is therefore not yet known.

I have, however, taken the liberty to consider the heads of argument filed by the respondent under case 5560/10 for purposes of determining the present application.

I agree with the applicant, that, the extent to which the provisions of the Arbitration Act are applicable in labour matters is governed by section 98 of the Labour Act, subsection 2 of which provides:

“Subject to this section, the Arbitration Act [Cap 7:15] shall apply to a dispute referred to compulsory arbitration.”

Section 98 of the Labour Act provides for, inter alia, the referral of matters to compulsory arbitration, the appointment of arbitrators, appeals against decisions of arbitrators, reviews, and other remedies.

These provisions are detailed and comprehensive.

Clearly, it could not have been the intention of the legislature, that, parties aggrieved by the decision of an arbitrator, in a labour dispute, seek remedy in terms of section 34 or 36 of the Arbitration Act.

I agree with the applicant, that, the correct interpretation would be that, with regards the law, the Labour Act takes precedence over the Arbitration Act and any other enactment.

The intention of the legislature was to have all labour matters initiated and resolved to finality in terms of the Labour Act. Equally, the legislature must have intended that such matters be dealt with by the Labour Court to the exclusion of any other court.

Sections 34 and 36 of the Arbitration Act are not applicable in cases where the award sought to be challenged relates to a labour dispute. The mechanisms for challenging such awards are provided for in the Labour Act and may be accessed through the medium of the Labour Court. No other court has jurisdiction to entertain such matters.

In the present case, the respondent has lodged an appeal with the Labour Court. The appeal is still pending. Should the respondent wish to have the arbitrator's determination suspended pending appeal or dealt with in any other interim way, it is to that court that it must direct its application.

Accordingly, for as long as the arbitral award has not been suspended or set aside on review or appeal, in terms of the Labour Act, there is no basis upon which this court may decline registration of the same.

It is therefore ordered as follows:

1. The arbitral award issued by Mr A.J. Manase, an independent arbitrator, be and is hereby registered in terms of section 98(14) of the Labour Act [Chapter 28:01].

2. In terms of the said arbitral award, the respondent shall pay the applicant an amount of US$287,491.

3. The respondent is to pay the costs of this application.

Jurisdiction re: Monetary, Cause of Action or Subject Matter


The legal issue that arises in this chamber application is whether the provisions of the Labour Act [Chapter 20:01] exclude the jurisdiction of the High Court in areas where the Labour Court has jurisdiction.

Section 89(6) of the Labour Act provides:

“No court, other than the Labour Court, shall have jurisdiction in the first instance to hear and determine any application, appeal or matter referred to in subsection (1).”

Section 89 of the Labour Act spells out the functions, powers, and jurisdiction of the Labour Court.

In Tuso v City of Harare 2004 (1) ZLR (H) BHUNU J had occasion to consider the legal import of section 89(6) of the Labour Act. The learned judge concluded…, as follows:

“It is manifestily clear to me, that, the intention of the legislature was to expressly exclude the jurisdiction of all other courts in areas where the Labour Court has jurisdiction in the first instance.”

I am in entire agreement with that conclusion.

It is important to note the historical context in which the Labour Court was created. Its predecessor, the Labour Relations Tribunal, was limited in terms of its powers and jurisdiction. Its decisions were subject to review by the High Court in much the same way as the decisions of any other domestic tribunal would be.

Even then, this court always took the view that a litigant must first exhaust the internal remedies availed to it, in terms of the Labour Act, before approaching it for relief.

The Labour Relations Tribunal was, in 2003, transformed into a court whose powers of review were the same as those of the High Court subject to the provisions of section 89(1) of the Labour Act.

The intention of the legislature clearly was to establish a one stop shop for all labour matters and provide finality in litigation involving labour issues; otherwise, why create a structure that is parallel to the High Court?

However, this exclusive jurisdiction only exists for matters provided for in section 89(1) of the Labour Act.

In the present application, the applicant seeks to register an arbitral award with this court in terms of section 98(14) of the Labour Act.

The respondent opposes the application on the basis, that, the arbitral award offends public policy in terms of art (s) 34 and 36 of the Arbitration Act.

It has incorporated, by reference, papers it filed under case number HC5560/10, a separate application, and has argued that the present application and that filed under case HC5560/10 be heard together.

I agree with the applicant, that, the correct procedure would have been for the respondent to file a counter chamber application in terms of Rule 229A of the High Court Rules which reads:

“Where a respondent files a notice of opposition and Opposing Affidavit, he may file, together with these documents, a counter application against the applicant, in the form 'mutatis mutandis' of a court application or a chamber application whichever is applicable.”

In any event, it would be improper to join the two applications, because, the time within which the second respondent under case number HC5560/10 (the arbitrator) must file a Notice of Opposition has not expired. The second respondent's defence in that application is therefore not yet known.

I have, however, taken the liberty to consider the heads of argument filed by the respondent under case 5560/10 for purposes of determining the present application.

I agree with the applicant, that, the extent to which the provisions of the Arbitration Act are applicable in labour matters is governed by section 98 of the Labour Act, subsection 2 of which provides:

“Subject to this section, the Arbitration Act [Cap 7:15] shall apply to a dispute referred to compulsory arbitration.”

Section 98 of the Labour Act provides for, inter alia, the referral of matters to compulsory arbitration, the appointment of arbitrators, appeals against decisions of arbitrators, reviews, and other remedies.

These provisions are detailed and comprehensive.

Clearly, it could not have been the intention of the legislature, that, parties aggrieved by the decision of an arbitrator, in a labour dispute, seek remedy in terms of section 34 or 36 of the Arbitration Act.

I agree with the applicant, that, the correct interpretation would be that, with regards the law, the Labour Act takes precedence over the Arbitration Act and any other enactment.

The intention of the legislature was to have all labour matters initiated and resolved to finality in terms of the Labour Act. Equally, the legislature must have intended that such matters be dealt with by the Labour Court to the exclusion of any other court.

Sections 34 and 36 of the Arbitration Act are not applicable in cases where the award sought to be challenged relates to a labour dispute. The mechanisms for challenging such awards are provided for in the Labour Act and may be accessed through the medium of the Labour Court. No other court has jurisdiction to entertain such matters.

In the present case, the respondent has lodged an appeal with the Labour Court. The appeal is still pending. Should the respondent wish to have the arbitrator's determination suspended pending appeal or dealt with in any other interim way, it is to that court that it must direct its application.

Accordingly, for as long as the arbitral award has not been suspended or set aside on review or appeal, in terms of the Labour Act, there is no basis upon which this court may decline registration of the same.

It is therefore ordered as follows:

1. The arbitral award issued by Mr A.J. Manase, an independent arbitrator, be and is hereby registered in terms of section 98(14) of the Labour Act [Chapter 28:01].

2. In terms of the said arbitral award, the respondent shall pay the applicant an amount of US$287,491.

3. The respondent is to pay the costs of this application.

Jurisdiction re: Judicial Deference iro Specialised Courts and Tribunals


The legal issue that arises in this chamber application is whether the provisions of the Labour Act [Chapter 20:01] exclude the jurisdiction of the High Court in areas where the Labour Court has jurisdiction.

Section 89(6) of the Labour Act provides:

“No court, other than the Labour Court, shall have jurisdiction in the first instance to hear and determine any application, appeal or matter referred to in subsection (1).”

Section 89 of the Labour Act spells out the functions, powers, and jurisdiction of the Labour Court.

In Tuso v City of Harare 2004 (1) ZLR (H) BHUNU J had occasion to consider the legal import of section 89(6) of the Labour Act. The learned judge concluded…, as follows:

“It is manifestily clear to me, that, the intention of the legislature was to expressly exclude the jurisdiction of all other courts in areas where the Labour Court has jurisdiction in the first instance.”

I am in entire agreement with that conclusion.

It is important to note the historical context in which the Labour Court was created. Its predecessor, the Labour Relations Tribunal, was limited in terms of its powers and jurisdiction. Its decisions were subject to review by the High Court in much the same way as the decisions of any other domestic tribunal would be.

Even then, this court always took the view that a litigant must first exhaust the internal remedies availed to it, in terms of the Labour Act, before approaching it for relief.

The Labour Relations Tribunal was, in 2003, transformed into a court whose powers of review were the same as those of the High Court subject to the provisions of section 89(1) of the Labour Act.

The intention of the legislature clearly was to establish a one stop shop for all labour matters and provide finality in litigation involving labour issues; otherwise, why create a structure that is parallel to the High Court?

However, this exclusive jurisdiction only exists for matters provided for in section 89(1) of the Labour Act.

In the present application, the applicant seeks to register an arbitral award with this court in terms of section 98(14) of the Labour Act.

The respondent opposes the application on the basis, that, the arbitral award offends public policy in terms of art (s) 34 and 36 of the Arbitration Act.

It has incorporated, by reference, papers it filed under case number HC5560/10, a separate application, and has argued that the present application and that filed under case HC5560/10 be heard together.

I agree with the applicant, that, the correct procedure would have been for the respondent to file a counter chamber application in terms of Rule 229A of the High Court Rules which reads:

“Where a respondent files a notice of opposition and Opposing Affidavit, he may file, together with these documents, a counter application against the applicant, in the form 'mutatis mutandis' of a court application or a chamber application whichever is applicable.”

In any event, it would be improper to join the two applications, because, the time within which the second respondent under case number HC5560/10 (the arbitrator) must file a Notice of Opposition has not expired. The second respondent's defence in that application is therefore not yet known.

I have, however, taken the liberty to consider the heads of argument filed by the respondent under case 5560/10 for purposes of determining the present application.

I agree with the applicant, that, the extent to which the provisions of the Arbitration Act are applicable in labour matters is governed by section 98 of the Labour Act, subsection 2 of which provides:

“Subject to this section, the Arbitration Act [Cap 7:15] shall apply to a dispute referred to compulsory arbitration.”

Section 98 of the Labour Act provides for, inter alia, the referral of matters to compulsory arbitration, the appointment of arbitrators, appeals against decisions of arbitrators, reviews, and other remedies.

These provisions are detailed and comprehensive.

Clearly, it could not have been the intention of the legislature, that, parties aggrieved by the decision of an arbitrator, in a labour dispute, seek remedy in terms of section 34 or 36 of the Arbitration Act.

I agree with the applicant, that, the correct interpretation would be that, with regards the law, the Labour Act takes precedence over the Arbitration Act and any other enactment.

The intention of the legislature was to have all labour matters initiated and resolved to finality in terms of the Labour Act. Equally, the legislature must have intended that such matters be dealt with by the Labour Court to the exclusion of any other court.

Sections 34 and 36 of the Arbitration Act are not applicable in cases where the award sought to be challenged relates to a labour dispute. The mechanisms for challenging such awards are provided for in the Labour Act and may be accessed through the medium of the Labour Court. No other court has jurisdiction to entertain such matters.

In the present case, the respondent has lodged an appeal with the Labour Court. The appeal is still pending. Should the respondent wish to have the arbitrator's determination suspended pending appeal or dealt with in any other interim way, it is to that court that it must direct its application.

Accordingly, for as long as the arbitral award has not been suspended or set aside on review or appeal, in terms of the Labour Act, there is no basis upon which this court may decline registration of the same.

It is therefore ordered as follows:

1. The arbitral award issued by Mr A.J. Manase, an independent arbitrator, be and is hereby registered in terms of section 98(14) of the Labour Act [Chapter 28:01].

2. In terms of the said arbitral award, the respondent shall pay the applicant an amount of US$287,491.

3. The respondent is to pay the costs of this application.

Lis Alibi Pendens or Pending Litigation re: Administrative and Quasi Judicial Proceedings


The legal issue that arises in this chamber application is whether the provisions of the Labour Act [Chapter 20:01] exclude the jurisdiction of the High Court in areas where the Labour Court has jurisdiction.

Section 89(6) of the Labour Act provides:

“No court, other than the Labour Court, shall have jurisdiction in the first instance to hear and determine any application, appeal or matter referred to in subsection (1).”

Section 89 of the Labour Act spells out the functions, powers, and jurisdiction of the Labour Court.

In Tuso v City of Harare 2004 (1) ZLR (H) BHUNU J had occasion to consider the legal import of section 89(6) of the Labour Act. The learned judge concluded…, as follows:

“It is manifestily clear to me, that, the intention of the legislature was to expressly exclude the jurisdiction of all other courts in areas where the Labour Court has jurisdiction in the first instance.”

I am in entire agreement with that conclusion.

It is important to note the historical context in which the Labour Court was created. Its predecessor, the Labour Relations Tribunal, was limited in terms of its powers and jurisdiction. Its decisions were subject to review by the High Court in much the same way as the decisions of any other domestic tribunal would be.

Even then, this court always took the view that a litigant must first exhaust the internal remedies availed to it, in terms of the Labour Act, before approaching it for relief.

The Labour Relations Tribunal was, in 2003, transformed into a court whose powers of review were the same as those of the High Court subject to the provisions of section 89(1) of the Labour Act.

The intention of the legislature clearly was to establish a one stop shop for all labour matters and provide finality in litigation involving labour issues; otherwise, why create a structure that is parallel to the High Court?

However, this exclusive jurisdiction only exists for matters provided for in section 89(1) of the Labour Act.

In the present application, the applicant seeks to register an arbitral award with this court in terms of section 98(14) of the Labour Act.

The respondent opposes the application on the basis, that, the arbitral award offends public policy in terms of art (s) 34 and 36 of the Arbitration Act.

It has incorporated, by reference, papers it filed under case number HC5560/10, a separate application, and has argued that the present application and that filed under case HC5560/10 be heard together.

I agree with the applicant, that, the correct procedure would have been for the respondent to file a counter chamber application in terms of Rule 229A of the High Court Rules which reads:

“Where a respondent files a notice of opposition and Opposing Affidavit, he may file, together with these documents, a counter application against the applicant, in the form 'mutatis mutandis' of a court application or a chamber application whichever is applicable.”

In any event, it would be improper to join the two applications, because, the time within which the second respondent under case number HC5560/10 (the arbitrator) must file a Notice of Opposition has not expired. The second respondent's defence in that application is therefore not yet known.

I have, however, taken the liberty to consider the heads of argument filed by the respondent under case 5560/10 for purposes of determining the present application.

I agree with the applicant, that, the extent to which the provisions of the Arbitration Act are applicable in labour matters is governed by section 98 of the Labour Act, subsection 2 of which provides:

“Subject to this section, the Arbitration Act [Cap 7:15] shall apply to a dispute referred to compulsory arbitration.”

Section 98 of the Labour Act provides for, inter alia, the referral of matters to compulsory arbitration, the appointment of arbitrators, appeals against decisions of arbitrators, reviews, and other remedies.

These provisions are detailed and comprehensive.

Clearly, it could not have been the intention of the legislature, that, parties aggrieved by the decision of an arbitrator, in a labour dispute, seek remedy in terms of section 34 or 36 of the Arbitration Act.

I agree with the applicant, that, the correct interpretation would be that, with regards the law, the Labour Act takes precedence over the Arbitration Act and any other enactment.

The intention of the legislature was to have all labour matters initiated and resolved to finality in terms of the Labour Act. Equally, the legislature must have intended that such matters be dealt with by the Labour Court to the exclusion of any other court.

Sections 34 and 36 of the Arbitration Act are not applicable in cases where the award sought to be challenged relates to a labour dispute. The mechanisms for challenging such awards are provided for in the Labour Act and may be accessed through the medium of the Labour Court. No other court has jurisdiction to entertain such matters.

In the present case, the respondent has lodged an appeal with the Labour Court. The appeal is still pending. Should the respondent wish to have the arbitrator's determination suspended pending appeal or dealt with in any other interim way, it is to that court that it must direct its application.

Accordingly, for as long as the arbitral award has not been suspended or set aside on review or appeal, in terms of the Labour Act, there is no basis upon which this court may decline registration of the same.

It is therefore ordered as follows:

1. The arbitral award issued by Mr A.J. Manase, an independent arbitrator, be and is hereby registered in terms of section 98(14) of the Labour Act [Chapter 28:01].

2. In terms of the said arbitral award, the respondent shall pay the applicant an amount of US$287,491.

3. The respondent is to pay the costs of this application.

Arbitration re: Approach, Proceedings Before an Arbitrator and Registration and Execution of Arbitral Awards


The legal issue that arises in this chamber application is whether the provisions of the Labour Act [Chapter 20:01] exclude the jurisdiction of the High Court in areas where the Labour Court has jurisdiction.

Section 89(6) of the Labour Act provides:

“No court, other than the Labour Court, shall have jurisdiction in the first instance to hear and determine any application, appeal or matter referred to in subsection (1).”

Section 89 of the Labour Act spells out the functions, powers, and jurisdiction of the Labour Court.

In Tuso v City of Harare 2004 (1) ZLR (H) BHUNU J had occasion to consider the legal import of section 89(6) of the Labour Act. The learned judge concluded…, as follows:

“It is manifestily clear to me, that, the intention of the legislature was to expressly exclude the jurisdiction of all other courts in areas where the Labour Court has jurisdiction in the first instance.”

I am in entire agreement with that conclusion.

It is important to note the historical context in which the Labour Court was created. Its predecessor, the Labour Relations Tribunal, was limited in terms of its powers and jurisdiction. Its decisions were subject to review by the High Court in much the same way as the decisions of any other domestic tribunal would be.

Even then, this court always took the view that a litigant must first exhaust the internal remedies availed to it, in terms of the Labour Act, before approaching it for relief.

The Labour Relations Tribunal was, in 2003, transformed into a court whose powers of review were the same as those of the High Court subject to the provisions of section 89(1) of the Labour Act.

The intention of the legislature clearly was to establish a one stop shop for all labour matters and provide finality in litigation involving labour issues; otherwise, why create a structure that is parallel to the High Court?

However, this exclusive jurisdiction only exists for matters provided for in section 89(1) of the Labour Act.

In the present application, the applicant seeks to register an arbitral award with this court in terms of section 98(14) of the Labour Act.

The respondent opposes the application on the basis, that, the arbitral award offends public policy in terms of art (s) 34 and 36 of the Arbitration Act.

It has incorporated, by reference, papers it filed under case number HC5560/10, a separate application, and has argued that the present application and that filed under case HC5560/10 be heard together.

I agree with the applicant, that, the correct procedure would have been for the respondent to file a counter chamber application in terms of Rule 229A of the High Court Rules which reads:

“Where a respondent files a notice of opposition and Opposing Affidavit, he may file, together with these documents, a counter application against the applicant, in the form 'mutatis mutandis' of a court application or a chamber application whichever is applicable.”

In any event, it would be improper to join the two applications, because, the time within which the second respondent under case number HC5560/10 (the arbitrator) must file a Notice of Opposition has not expired. The second respondent's defence in that application is therefore not yet known.

I have, however, taken the liberty to consider the heads of argument filed by the respondent under case 5560/10 for purposes of determining the present application.

I agree with the applicant, that, the extent to which the provisions of the Arbitration Act are applicable in labour matters is governed by section 98 of the Labour Act, subsection 2 of which provides:

“Subject to this section, the Arbitration Act [Cap 7:15] shall apply to a dispute referred to compulsory arbitration.”

Section 98 of the Labour Act provides for, inter alia, the referral of matters to compulsory arbitration, the appointment of arbitrators, appeals against decisions of arbitrators, reviews, and other remedies.

These provisions are detailed and comprehensive.

Clearly, it could not have been the intention of the legislature, that, parties aggrieved by the decision of an arbitrator, in a labour dispute, seek remedy in terms of section 34 or 36 of the Arbitration Act.

I agree with the applicant, that, the correct interpretation would be that, with regards the law, the Labour Act takes precedence over the Arbitration Act and any other enactment.

The intention of the legislature was to have all labour matters initiated and resolved to finality in terms of the Labour Act. Equally, the legislature must have intended that such matters be dealt with by the Labour Court to the exclusion of any other court.

Sections 34 and 36 of the Arbitration Act are not applicable in cases where the award sought to be challenged relates to a labour dispute. The mechanisms for challenging such awards are provided for in the Labour Act and may be accessed through the medium of the Labour Court. No other court has jurisdiction to entertain such matters.

In the present case, the respondent has lodged an appeal with the Labour Court. The appeal is still pending. Should the respondent wish to have the arbitrator's determination suspended pending appeal or dealt with in any other interim way, it is to that court that it must direct its application.

Accordingly, for as long as the arbitral award has not been suspended or set aside on review or appeal, in terms of the Labour Act, there is no basis upon which this court may decline registration of the same.

It is therefore ordered as follows:

1. The arbitral award issued by Mr A.J. Manase, an independent arbitrator, be and is hereby registered in terms of section 98(14) of the Labour Act [Chapter 28:01].

2. In terms of the said arbitral award, the respondent shall pay the applicant an amount of US$287,491.

3. The respondent is to pay the costs of this application.

Cause of Action and Draft Orders re: Approach iro Labour Proceedings


The legal issue that arises in this chamber application is whether the provisions of the Labour Act [Chapter 20:01] exclude the jurisdiction of the High Court in areas where the Labour Court has jurisdiction.

Section 89(6) of the Labour Act provides:

“No court, other than the Labour Court, shall have jurisdiction in the first instance to hear and determine any application, appeal or matter referred to in subsection (1).”

Section 89 of the Labour Act spells out the functions, powers, and jurisdiction of the Labour Court.

In Tuso v City of Harare 2004 (1) ZLR (H) BHUNU J had occasion to consider the legal import of section 89(6) of the Labour Act. The learned judge concluded…, as follows:

“It is manifestily clear to me, that, the intention of the legislature was to expressly exclude the jurisdiction of all other courts in areas where the Labour Court has jurisdiction in the first instance.”

I am in entire agreement with that conclusion.

It is important to note the historical context in which the Labour Court was created. Its predecessor, the Labour Relations Tribunal, was limited in terms of its powers and jurisdiction. Its decisions were subject to review by the High Court in much the same way as the decisions of any other domestic tribunal would be.

Even then, this court always took the view that a litigant must first exhaust the internal remedies availed to it, in terms of the Labour Act, before approaching it for relief.

The Labour Relations Tribunal was, in 2003, transformed into a court whose powers of review were the same as those of the High Court subject to the provisions of section 89(1) of the Labour Act.

The intention of the legislature clearly was to establish a one stop shop for all labour matters and provide finality in litigation involving labour issues; otherwise, why create a structure that is parallel to the High Court?

However, this exclusive jurisdiction only exists for matters provided for in section 89(1) of the Labour Act.

In the present application, the applicant seeks to register an arbitral award with this court in terms of section 98(14) of the Labour Act.

The respondent opposes the application on the basis, that, the arbitral award offends public policy in terms of art (s) 34 and 36 of the Arbitration Act.

It has incorporated, by reference, papers it filed under case number HC5560/10, a separate application, and has argued that the present application and that filed under case HC5560/10 be heard together.

I agree with the applicant, that, the correct procedure would have been for the respondent to file a counter chamber application in terms of Rule 229A of the High Court Rules which reads:

“Where a respondent files a notice of opposition and Opposing Affidavit, he may file, together with these documents, a counter application against the applicant, in the form 'mutatis mutandis' of a court application or a chamber application whichever is applicable.”

In any event, it would be improper to join the two applications, because, the time within which the second respondent under case number HC5560/10 (the arbitrator) must file a Notice of Opposition has not expired. The second respondent's defence in that application is therefore not yet known.

I have, however, taken the liberty to consider the heads of argument filed by the respondent under case 5560/10 for purposes of determining the present application.

I agree with the applicant, that, the extent to which the provisions of the Arbitration Act are applicable in labour matters is governed by section 98 of the Labour Act, subsection 2 of which provides:

“Subject to this section, the Arbitration Act [Cap 7:15] shall apply to a dispute referred to compulsory arbitration.”

Section 98 of the Labour Act provides for, inter alia, the referral of matters to compulsory arbitration, the appointment of arbitrators, appeals against decisions of arbitrators, reviews, and other remedies.

These provisions are detailed and comprehensive.

Clearly, it could not have been the intention of the legislature, that, parties aggrieved by the decision of an arbitrator, in a labour dispute, seek remedy in terms of section 34 or 36 of the Arbitration Act.

I agree with the applicant, that, the correct interpretation would be that, with regards the law, the Labour Act takes precedence over the Arbitration Act and any other enactment.

The intention of the legislature was to have all labour matters initiated and resolved to finality in terms of the Labour Act. Equally, the legislature must have intended that such matters be dealt with by the Labour Court to the exclusion of any other court.

Sections 34 and 36 of the Arbitration Act are not applicable in cases where the award sought to be challenged relates to a labour dispute. The mechanisms for challenging such awards are provided for in the Labour Act and may be accessed through the medium of the Labour Court. No other court has jurisdiction to entertain such matters.

In the present case, the respondent has lodged an appeal with the Labour Court. The appeal is still pending. Should the respondent wish to have the arbitrator's determination suspended pending appeal or dealt with in any other interim way, it is to that court that it must direct its application.

Accordingly, for as long as the arbitral award has not been suspended or set aside on review or appeal, in terms of the Labour Act, there is no basis upon which this court may decline registration of the same.

It is therefore ordered as follows:

1. The arbitral award issued by Mr A.J. Manase, an independent arbitrator, be and is hereby registered in terms of section 98(14) of the Labour Act [Chapter 28:01].

2. In terms of the said arbitral award, the respondent shall pay the applicant an amount of US$287,491.

3. The respondent is to pay the costs of this application.

Lis Alibi Pendens or Pending Litigation re: Labour Proceedings


The legal issue that arises in this chamber application is whether the provisions of the Labour Act [Chapter 20:01] exclude the jurisdiction of the High Court in areas where the Labour Court has jurisdiction.

Section 89(6) of the Labour Act provides:

“No court, other than the Labour Court, shall have jurisdiction in the first instance to hear and determine any application, appeal or matter referred to in subsection (1).”

Section 89 of the Labour Act spells out the functions, powers, and jurisdiction of the Labour Court.

In Tuso v City of Harare 2004 (1) ZLR (H) BHUNU J had occasion to consider the legal import of section 89(6) of the Labour Act. The learned judge concluded…, as follows:

“It is manifestily clear to me, that, the intention of the legislature was to expressly exclude the jurisdiction of all other courts in areas where the Labour Court has jurisdiction in the first instance.”

I am in entire agreement with that conclusion.

It is important to note the historical context in which the Labour Court was created. Its predecessor, the Labour Relations Tribunal, was limited in terms of its powers and jurisdiction. Its decisions were subject to review by the High Court in much the same way as the decisions of any other domestic tribunal would be.

Even then, this court always took the view that a litigant must first exhaust the internal remedies availed to it, in terms of the Labour Act, before approaching it for relief.

The Labour Relations Tribunal was, in 2003, transformed into a court whose powers of review were the same as those of the High Court subject to the provisions of section 89(1) of the Labour Act.

The intention of the legislature clearly was to establish a one stop shop for all labour matters and provide finality in litigation involving labour issues; otherwise, why create a structure that is parallel to the High Court?

However, this exclusive jurisdiction only exists for matters provided for in section 89(1) of the Labour Act.

In the present application, the applicant seeks to register an arbitral award with this court in terms of section 98(14) of the Labour Act.

The respondent opposes the application on the basis, that, the arbitral award offends public policy in terms of art (s) 34 and 36 of the Arbitration Act.

It has incorporated, by reference, papers it filed under case number HC5560/10, a separate application, and has argued that the present application and that filed under case HC5560/10 be heard together.

I agree with the applicant, that, the correct procedure would have been for the respondent to file a counter chamber application in terms of Rule 229A of the High Court Rules which reads:

“Where a respondent files a notice of opposition and Opposing Affidavit, he may file, together with these documents, a counter application against the applicant, in the form 'mutatis mutandis' of a court application or a chamber application whichever is applicable.”

In any event, it would be improper to join the two applications, because, the time within which the second respondent under case number HC5560/10 (the arbitrator) must file a Notice of Opposition has not expired. The second respondent's defence in that application is therefore not yet known.

I have, however, taken the liberty to consider the heads of argument filed by the respondent under case 5560/10 for purposes of determining the present application.

I agree with the applicant, that, the extent to which the provisions of the Arbitration Act are applicable in labour matters is governed by section 98 of the Labour Act, subsection 2 of which provides:

“Subject to this section, the Arbitration Act [Cap 7:15] shall apply to a dispute referred to compulsory arbitration.”

Section 98 of the Labour Act provides for, inter alia, the referral of matters to compulsory arbitration, the appointment of arbitrators, appeals against decisions of arbitrators, reviews, and other remedies.

These provisions are detailed and comprehensive.

Clearly, it could not have been the intention of the legislature, that, parties aggrieved by the decision of an arbitrator, in a labour dispute, seek remedy in terms of section 34 or 36 of the Arbitration Act.

I agree with the applicant, that, the correct interpretation would be that, with regards the law, the Labour Act takes precedence over the Arbitration Act and any other enactment.

The intention of the legislature was to have all labour matters initiated and resolved to finality in terms of the Labour Act. Equally, the legislature must have intended that such matters be dealt with by the Labour Court to the exclusion of any other court.

Sections 34 and 36 of the Arbitration Act are not applicable in cases where the award sought to be challenged relates to a labour dispute. The mechanisms for challenging such awards are provided for in the Labour Act and may be accessed through the medium of the Labour Court. No other court has jurisdiction to entertain such matters.

In the present case, the respondent has lodged an appeal with the Labour Court. The appeal is still pending. Should the respondent wish to have the arbitrator's determination suspended pending appeal or dealt with in any other interim way, it is to that court that it must direct its application.

Accordingly, for as long as the arbitral award has not been suspended or set aside on review or appeal, in terms of the Labour Act, there is no basis upon which this court may decline registration of the same.

It is therefore ordered as follows:

1. The arbitral award issued by Mr A.J. Manase, an independent arbitrator, be and is hereby registered in terms of section 98(14) of the Labour Act [Chapter 28:01].

2. In terms of the said arbitral award, the respondent shall pay the applicant an amount of US$287,491.

3. The respondent is to pay the costs of this application.

CHIWESHE JP: The legal issue that arises in this chamber application is whether the provisions of the Labour Act [Cap 20:01] exclude the jurisdiction of the High Court in areas where the Labour Court has jurisdiction.

Section 89(6) of the Labour Act provides:

“No court other than the Labour Court, shall have jurisdiction in the first instance to hear and determine any application, appeal or matter referred to in subsection (1).”

Section 89 of the Labour Act spells out the functions, powers and jurisdiction of the Labour Court.

In Tuso v City of Harare 2004 (1) ZLR (H) BHUNU J had occasion to consider the legal import of section 89(6) of the Labour Act. The learned judge concluded at p3F as follows:

“It is manifestily clear to me that the intention of the legislature was to expressly exclude the jurisdiction of all other courts in areas where the Labour Court has jurisdiction in the first instance.”

I am in entire agreement with that conclusion.

It is important to note the historical context in which the Labour Court was created. Its predecessor, the Labour Relations Tribunal, was limited in terms of its powers and jurisdiction. Its decisions were subject to review by the High Court in much the same way as the decisions of any other domestic tribunal would be. Even then this court always took the view that a litigant must first exhaust the internal remedies availed to it in terms of the Labour Act, before approaching it for relief.

The Labour Relations Tribunal was in 2003 transformed into a court whose powers of review were the same as those of the High Court subject to the provisions of section 89(1) of the Labour Act.

The intention of the legislature clearly was to establish a one stop shop for all labour matters and provide finality in litigation involving labour issues. Otherwise why create a structure that is parallel to the High Court?

However, this exclusive jurisdiction only exists for matters provided for in section 89(1).

In the present application the applicant seeks to register an arbitral award with this court in terms of section 98(14) of the Labour Act.

The respondent opposes the application on the basis that the arbitral award offends public policy in terms of art (s) 34 and 36 of the Arbitration Act.

It has incorporated by reference papers it filed under case number HC5560/10, a separate application, and has argued that the present application and that filed under case HC5560/10 be heard together.

I agree with the applicant that the correct procedure would have been for the respondent to file a counter chamber application in terms of Rule 229A which reads:

“Where a respondent files a notice of opposition and Opposing Affidavit, he may file, together with these documents, a counter application against the applicant in the form, 'mutatis mutandis' of a court application or a chamber application whichever is applicable.”

In any event it would be improper to join the two applications because the time within which the second respondent under case number HC5560/10 (the arbitrator) must file a notice of opposition has not expired. The second respondent's defence in that application is therefore not yet known.

I have however taken the liberty to consider the heads of argument filed by the respondent under case 5560/10 for purposes of determining the present application.

I agree with the applicant that the extent to which the provisions of the Arbitration Act are applicable in labour matters is governed by section 98 of the Labour Act subsection 2 of which provides:

“Subject to this section the Arbitration Act [Cap 7:15] shall apply to a dispute referred to compulsory arbitration.”

Section 98 provides for inter alia the referral of matters to compulsory arbitration, the appointment of arbitrators, appeals against decisions of arbitrators, reviews and other remedies.

These provisions are detailed and comprehensive.

Clearly it could not have been the intention of the legislature that parties aggrieved by the decision of an arbitrator in a labour dispute seek remedy in terms of section 34 or 36 of the Arbitration Act.

I agree with the applicant that the correct interpretation would be that, with regards the law, the Labour Act takes precedence over the Arbitration Act and any other enactment.

The intention of the legislature was to have all labour matters initiated and resolved to finality in terms of the Labour Act. Equally, the legislature must have intended that such matters be dealt with by the Labour Court to the exclusion of any other court.

Sections 34 and 36 of the Arbitration Act are not applicable in cases where the award sought to be challenged relates to a labour dispute. The mechanisms for challenging such awards are provided for in the Labour Act and may be accessed through the medium of the Labour Court. No other court has jurisdiction to entertain such matters.

In the present case the respondent has lodged an appeal with the Labour Court. The appeal is still pending. Should the respondent wish to have the arbitrator's determination suspended pending appeal or dealt with in any other interim way, it is to that court that it must direct its application.

Accordingly, for as long as the arbitral award has not been suspended or set aside on review or appeal in terms of the Labour Act, there is no basis upon which this court may decline registration of the same.

It is therefore ordered as follows:

1. The arbitral award issued by Mr A.J. Manase, an independent arbitrator, be and is hereby registered in terms of section 98(14) of the Labour Act [Cap 28:01].

2. In terms of the said arbitral award, the respondent shall pay the applicant an amount of US$287,491.00.

3. The respondent is to pay the costs of this application.


Atherstone & Cook, applicant's legal practitioners

Dube, Manikai & Hwacha, respondent's legal practitioners

Back Main menu

Categories

Back to top